Fire NOC for a petrol pump: PESO Form XIV, the district NOC, fire rules and fees

Updated By Flamekite Editorial DeskFacts checked against official sources on

Quick answer

A petrol pump needs a PESO Form XIV licence and a district NOC under rule 144 that records fire service comments; Rajasthan and Gujarat add a fire NOC. The NOC comes from the District Magistrate, or the Commissioner of Police in a commissionerate city, and must be decided within 3 months.

Form XIV costs Rs 5,000 a year for each class of fuel up to 50 KL, and runs to 31 December for at most 3 years. Every pump needs 2 extinguishers and 2 drums of dry sand. A new pump stays 50 m from schools, hospitals of 10 beds or more and designated housing, and never under 30 m.

PESO licence for the tanks
Form XIV
Issued by a PESO circle or sub-circle
The terms
District NOC decision within
3 months
Rule 144(5), with fire service comments since 2024
The NOC file
Fire kit for each pump
2 extinguishers
And 2 tins or drums of dry sand (condition 20)
Checklist
Never closer to a school than
30 m
50 m is the CPCB rule; 30 m the floor
The siting rule

Petrol pump fire NOC and PESO licence at a glance: 10 facts

How the Petroleum Rules, PESO, the district authority and the state fire services treat a petrol pump, each fact with the instrument behind it. Last verified 25 October 2026.
WhatThe ruleSource
Central lawPetroleum Act, 1934 and the Petroleum Rules, 2002 (G.S.R. 204(E) of 13 March 2002), as amended by G.S.R. 154(E) of 4 March 2024G.S.R. 154(E), 2024
LicenceForm XIV: to store petroleum in tanks connected to a pump outfit for fuelling motor vehicles (First Schedule, article 5)Petroleum Rules 2002
Who licensesPESO Circle and Sub Circle offices grant, renew, amend and transfer Form XIVPESO SOP
District NOCRule 144: from the District Authority (Commissioner or Deputy Commissioner of Police in a commissionerate town, District Magistrate elsewhere), within 3 monthsPetroleum Rules 2002
Fire service's saySince 4 March 2024 the NOC proforma records the Fire Department's comments on fire tender access and emergency preparednessG.S.R. 154(E), 2024
Licence feeRs 5,000 a year for each class up to 50 KL, plus Rs 50 per further KL, at most Rs 50,000 a year per class (Part A of the First Schedule, since 10 August 2018)G.S.R. 762(E), 2018
ValidityTo 31 December of the final year, at most 3 years; apply 30 days before expiry, no renewal more than 30 days after it (rules 142 and 148)Petroleum Rules 2002
Fire kitEach pump: at least 2 tins or drums of dry sand and 2 foam or dry chemical extinguishers (Form XIV, condition 20)Petroleum Rules 2002
SitingCPCB, 7 January 2020: new outlets 50 m from schools, hospitals of 10 or more beds and designated residential areas; never under 30 m; no high-tension line overheadKerala High Court
State fire NOCAll petrol pumps in Rajasthan; listed hazardous premises in Gujarat, Odisha, Jammu and Kashmir, Lakshadweep and Tripura; an enclosure to the district NOC in MeghalayaRajasthan UDH

Petrol pump fire NOC rules in 17 states and UTs

What each state's fire instrument says about petrol pumps and fuel stations, with who issues and the term or fee where the instrument sets one. Where Flamekite found no petrol-pump line, the row says so. Checked 25 October 2026.
OptionWhat the instrument says about fuel stationsWho issues, term or feeInstrumentSource
RajasthanTable 1 lists petrol pumps and hazardous buildings: all need a fire NOCRs 2, 1.50 or 1 per sq ft by local body; generally yearly; Rs 5,000 under s.291 if missingUDH order of 14 September 2023Rajasthan UDH
GujaratPetrol pump and gas station in the hazardous storage and handling row; fuel dispensing pumps irrespective of area and heightSingle storey: Rs 5,000 plan, Rs 20 per m² certificate, Rs 5,000 renewal; Advance or Specialist FSOFire Regulations 2023, Tables 1 and 2Gujarat Fire Safety Compliance Portal
OdishaPetrol retail outlets and LPG godowns form one certificate classAssistant Fire Officer; certificate valid 2 yearsOrder 50908 of 19 November 2019Order 50908 of 2019
Jammu and KashmirPetrol pumps and CNG stations are use class C3, which needs a fire NOCFilling stations 30 m from the nearest house, school or health centre, 300 m from junctions and from each otherUBBL 2021, 2.18(2); S.O. 304 of 1 December 2025J&K H&UDD
Andaman and NicobarStorage and sale of petroleum products is 1 of 9 clearance classesChecklist: 2 DCP 10 kg per dispenser, 1 CO2 4.5 kg at the meter room, 2 emergency shutdown switchesFire Service online portalA&N Fire Service portal
LakshadweepPremises with petroleum, LPG, gases or chemicals need a provisional certificate at any sizeBefore the building permitRules 2026, r.8(1) and 11(2)Lakshadweep Gazette Extraordinary Vol. LXII No. 42, 3 September 2026
TripuraRetail outlets of petrol, diesel and gas can never self-certifyFull certificate route at any sizeFire Safety Rules 2026, r.6Directorate of Fire and Emergency Services, Tripura
Madhya PradeshFuel filling centres apply in the separate Fire and Explosive categoryUploads the LOI or A-12, the SDM's land diversion order and the approved layoute-Nagar Palika manual, 2025MP e-Nagar Palika manual
MeghalayaA fire department NOC is an enclosure to the District Magistrate's petroleum NOC60 days, no fee, Rs 10 court-fee stampDM (Arms) SOPMeghalaya DM SOP
KeralaPetrol bunk or gas store NOC under the Petroleum ActRs 20,000, once in 2 yearsG.O.(Ms)No.272/2024/HomeKerala Fire and Rescue Services
PunjabPetrol pumps in the high-hazard fee groupRs 50,000 (2021 schedule; the current one was not read)Letter 41343 of 8 October 2021Local Govt Punjab
GoaPOL outlet NOC is a time-bound fire serviceDeputy Director, 15 daysRTS notification of 3 November 2022, item 85Goa Gazette 2022
UttarakhandPetrol pump NOC recommendation is a notified service15 daysCitizen charter, order 1337 of 28 October 2011UFES charter
AssamPetroleum products premises file Form VII on Sewa SetuForms of the 1989 Rules; the 1985 Act was repealed on 24 December 2025Sewa Setu service listSewa Setu Assam
Maharashtra (Pune)Fuel stations are 1 of PMC's 9 fire NOC service typesPune Municipal Corporation fire brigadePMC online servicesPMC
Tamil NaduA building includes petrol, diesel or gas lines, installations or pumpsNot found: no separate petrol-pump lineAct 37 of 2025, s.2(b)Government of Tamil Nadu, Gazette Extraordinary No. 263, 6 June 2025
Uttar PradeshPremises storing petroleum products are defined in the rulesNot found: no separate petrol-pump lineRules 2024, r.2(v)UP Rules 2024

Getting a petrol pump licence and fire NOC in 8 steps

  1. Hold the site and the Letter of Intent

    An oil company's Letter of Intent and lawful possession of the land come first; Meghalaya's district SOP asks for both, and PESO wants an undertaking of legal physical possession.

  2. Check the siting before buying

    Keep the fill point, dispensers and vent 50 m from schools, hospitals of 10 or more beds and designated housing, and never under 30 m. Jammu and Kashmir adds 300 m between filling stations.

  3. Take the state fire service's view

    In Rajasthan and Gujarat a fire NOC is required in its own right; in Meghalaya the fire department's NOC is an enclosure to the district file.

  4. Apply for the rule 144 NOC

    File two copies of the site plan with the District Authority. It collects revenue, police, municipal, NHAI or PWD and fire comments, and must decide within 3 months.

  5. Get PESO's prior approval of plans

    Form IX with drawings showing protected works within 100 m, tanks, vents, pumps and fire fighting facilities, a CPCB undertaking and the Rs 2,000 scrutiny fee.

  6. Build to the approved plan

    Underground tanks in a pit, vent pipes at least 4 m high, a 1.2 m wall on sides other than the drive way, approved Ex electrical apparatus.

  7. Test, certify and get Form XIV

    A competent person or TPIA tests the tanks (rule 126) and signs the certificate of safety (rule 130); then the circle office grants the licence.

  8. Diary the renewals

    Form XIV runs to 31 December, at most 3 years; file 30 days early. Renew the state fire certificate on its own clock: generally yearly in Rajasthan, every 2 years in Odisha.

Form XIV, rule 144 and the words a petrol pump file uses

The Petroleum Rules use their own words for a petrol pump and the officers around it. These 10 come from the rules, the 2024 amendment and PESO's SOP.

Service station
Premises specially prepared for fuelling motor vehicles, with any servicing places the licensing authority approves; since 2024 also non-fuelling facilities outside the hazardous areas (rule 2(1)(xxiv)). G.S.R. 154(E), 2024
Form XIV
The licence to store petroleum in tanks in connection with a pump outfit for fuelling motor conveyances; granted by PESO's Circle and Sub Circle offices. PESO SOP
Form IX
The application form to import and store petroleum, used for a Form XIV licence and its renewal, amendment and transfer. PESO SOP
District Authority
In a town with a Commissioner of Police, the Commissioner or a Deputy Commissioner of Police; anywhere else, the District Magistrate, which includes an Additional District Magistrate. Petroleum Rules 2002
Rule 144 NOC
The District Authority's no-objection certificate for the site, with an endorsed plan, forwarded to PESO with Form IX; accepted for 3 years from issue. G.S.R. 154(E), 2024
Protected works
Buildings where people live or assemble, docks, timber and coal yards, furnaces and chimneys, public roads and overhead high-tension lines; the plan shows those within 100 m. Petroleum Rules 2002
Class A and Class B
Petroleum with a flash point below 23 °C (petrol) and from 23 °C to below 65 °C; a Form XIV licence states the kilolitres of each. PESO SOP
Competent person or TPIA
An engineer with 5 years' experience in petroleum tanks, or a recognised third party inspection agency, who tests tanks and signs the certificate of safety. G.S.R. 154(E), 2024
Form G
The Gas Cylinders Rules licence to dispense CNG or compressed bio gas as automotive fuel from a mother, daughter or online station. Gas Cylinders Rules
Form LS-1B
The SMPV Rules licence to store and dispense auto-LPG at an auto-LPG dispensing station, valid to 30 September for at most 10 years (5 until G.S.R. 374(E) of 5 June 2025). G.S.R. 374(E), 2025

The rule 144 district NOC for a petrol pump: 5 departments comment

The 2024 proforma lists 5 views the District Authority considers before it signs. The fire service's view travels in this file even where the state issues no separate fire NOC.

  1. 1. Revenue Department

    Confirms the applicant's lawful possession of the site and the owner's or leaseholder's authority to develop it for petroleum storage. G.S.R. 154(E), 2024

  2. 2. Police

    Comments on traffic density and the outlet's impact on traffic. G.S.R. 154(E), 2024

  3. 3. Municipal body or gram panchayat

    Comments on conformity with local planning, including schools and hospitals, and any mitigating measures. G.S.R. 154(E), 2024

  4. 4. NHAI or PWD

    Comments on road safety, road alignment and access to the road. G.S.R. 154(E), 2024

  5. 5. Fire Department

    Comments on the access of fire tenders to the site in an emergency and the fire service's preparedness to combat it. G.S.R. 154(E), 2024

  6. 6. The decision

    Within 3 months of the application; a refusal needs written reasons and a hearing, and an appeal lies to the next superior authority within 60 days. Petroleum Rules 2002

CPCB siting rule for new petrol pumps: 50 m, never under 30 m

PESO asks every Form XIV applicant for an undertaking to follow the CPCB guidelines. Their siting paragraph, dated 7 January 2020, is quoted in full by the Kerala High Court.

Word for word

In case of siting criteria for petrol pumps new Retail Outlets shall not be located within a radial distance of 50 meters (from fill point/dispensing units/vent pipe whichever is nearest) from schools, hospitals (10 beds and above) and residential areas designated as per local laws. In case of constraints in providing 50 meters distance, the retail outlet shall implement additional safety measures as prescribed by PESO. In no case the distance between new retail outlet from schools, hospitals (10 beds and above) and residential area designated as per local laws shall be less than 30 meters. No high tension line shall pass over the retail outlet.

CPCB guidelines of 7 January 2020, paragraph H, as extracted in WP(C) No. 12226 of 2025, High Court of Kerala, 18 August 2025 Kerala High Court

The court held that a college is not a school under paragraph H, because CPCB told the National Green Tribunal its expert committee had left colleges out; PESO could not refuse a pump for a college within 30 m. In a 2026 Kerala case reported by LiveLaw, the High Court measured a school's distance from its compound wall, not its building, and upheld a refusal at 25.15 m. Which 'additional safety measures' PESO prescribes between 30 m and 50 m was not found in an official text.

Hazardous zones at a petrol pump: fill point, vent and dispenser

The Fourth Schedule, Part C, sets how far the hazardous area runs around each fitting. Only PESO-approved Ex electrical apparatus may stand inside it (Chapter IV).

ZoneExtent of the hazardous area
Tank filling point Petroleum Rules 2002Zone 1Any pit, sump or box below grade in a zone, and up to 45 cm above grade within 3 m of the fill point
Tank vent, close Petroleum Rules 2002Zone 1Within 90 cm of the open end, in all directions
Tank vent, outer Petroleum Rules 2002Zone 2From 90 cm to 1.5 m of the open end, in all directions
Dispenser cabinet Petroleum Rules 2002Zone 1Inside the cabinet up to 1.2 m above the base, and 45 cm around it
Dispenser, outdoor Petroleum Rules 2002Zone 2From 45 cm to 6 m of the cabinet, up to 45 cm above grade
Lubrication or service room Petroleum Rules 2002Zone 1 in a pit; zone 2The whole pit; up to 45 cm above the floor in the whole room
Sales, storage or rest room Petroleum Rules 2002Zone 1The entire room, if it has any opening within a zone 1 or zone 2 area

Zone 1: vapour is expected in normal operation; zone 2: only on failure, as PESO's SOP describes. Condition 14 of Form XIV bars any light that could ignite vapour within these areas during night fuelling. Two figures in PESO's consolidated text read 'metres' where centimetres are evidently meant; they are left out here.

Petrol pump fire safety checklist from Form XIV: 12 items

These 12 points come from the Petroleum Rules and the Form XIV conditions. A PESO inspector or fire officer can check each one on site.

  • At least 2 extinguishers (foam or dry chemical) and 2 tins or drums of dry sand at each pump, kerbside or portable (condition 20). Petroleum Rules 2002
  • Staff conversant with the extinguishers and operations under an experienced, safety-trained supervisor (rules 117 and 118). Petroleum Rules 2002
  • No smoking, matches or naked light except in places the licensing authority authorises (rule 117). Petroleum Rules 2002
  • A boundary wall or fence 1.2 m high on all sides other than the drive way (rule 121(2)). Petroleum Rules 2002
  • Underground tanks only, in a pit packed with sand, earth or clay, or a tested welded tank at least 1.5 m from the boundary (condition 2). Petroleum Rules 2002
  • A separate vent pipe for each tank, at least 4 m high and 4 m from neighbours and the sales room, with 2 layers of wire gauze (condition 5). Petroleum Rules 2002
  • Tank earthing with 2 connections, resistance to earth not over 7 ohms, tested at least once every 12 months and recorded (rules 127 and 128). Petroleum Rules 2002
  • Only Ex electrical apparatus approved by the Chief Controller in the hazardous areas, and the electrical certificate signed by an electrical engineer since 2024 (rules 102 and 114). PESO SOP
  • No tank filling between sunset and sunrise unless the licence allows it (condition 10). Petroleum Rules 2002
  • The licence number displayed, and extracts of the rules and conditions posted where they can be seen (rules 133 and 134). Petroleum Rules 2002
  • The ground kept clean of vegetation, waste and rubbish, and no petroleum let into drains or public roads (rule 119; condition 19). Petroleum Rules 2002
  • Any fire with death or serious injury reported at once to the nearest Magistrate or police station and to PESO (condition 22). Petroleum Rules 2002

Fuelling and tanker decanting at a petrol pump: 4 dos, 4 don'ts

Most petrol pump fires start at the nozzle or the decantation pit. These rules come from Form XIV and an MP High Court record of a 2022 decantation fire.

Do

  • Stop the engine before fuelling, and refuel a hire vehicle licensed for more than 6 passengers only after the passengers get out (condition 15). Petroleum Rules 2002
  • Fill containers only in the 4 cases allowed: clearing a tank, testing the pump, an approved can up to 25 litres for a vehicle that ran dry, or Class B in approved containers up to 200 litres (condition 16). Petroleum Rules 2002
  • Keep running vehicles at least 4.5 m from a Class B container being filled and from that pump (condition 16(iv)). Petroleum Rules 2002
  • Run the tank-truck decantation to the oil company's SOP, with a dedicated unloading hose and non-static material, as HPCL's committee recommended after the Indore fire. MP High Court

Don’t

  • Don't wipe spilled petrol with a sponge: at Indore on 2 May 2022 that started the fire, and the pump was sealed the next day. MP High Court
  • Don't keep more than 400 litres in reserve within 6 m when a portable pump stands in for a broken one, and not for more than 1 month (condition 17). Petroleum Rules 2002
  • Don't move a pump or tank, or replace a tank, without PESO's written sanction (condition 6; rule 146). Petroleum Rules 2002
  • Don't allow any light within 9 m of barrels while filling an underground tank from them (condition 11). Petroleum Rules 2002

CNG, auto-LPG and LNG stations: which licence each fuel needs

A fuel station adding gas takes a second licence under different rules. Since 5 June 2026 none of the gas licences needs a District Authority NOC.

  • Petrol and diesel

    Form XIV, Petroleum Rules

    PESO Controller; rule 144 NOC; Rs 5,000 a year per class up to 50 KL; to 31 December, at most 3 years. G.S.R. 762(E), 2018

  • CNG or CBG

    Form G, Gas Cylinders Rules

    Chief Controller; Rs 10,000 in Schedule V as substituted in 2025; to 30 September, at most 10 years. Rule 48's District Authority NOC was omitted on 5 June 2026. G.S.R. 447(E), 2026

  • Auto-LPG

    Form LS-1B, SMPV Rules

    Chief Controller or an authorised Controller; same fee as LS-1A; to 30 September, at most 10 years since June 2025. Rule 47's District Authority NOC was omitted on 5 June 2026. G.S.R. 448(E), 2026

  • LNG

    Form LS-1C, SMPV Rules

    An LNG dispensing station; a Form XIV licence that is part of it needs no rule 144 NOC since 4 March 2024. G.S.R. 154(E), 2024

  • Pump plus gas

    Form XIV inside a gas station

    Since 4 March 2024, a Form XIV licence that forms part of a CNG station (Form G), auto-LPG station (LS-1B) or LNG station (LS-1C) needs no District Authority NOC (rule 144(6a)). G.S.R. 154(E), 2024

  • Mobile refueller

    Form XIX

    Rs 2,000 a year (since 2018); 2 buckets of dry sand and 2 extinguishers during refuelling, 9 m clear of protected works. Petroleum Rules 2002

Petrol pump safety rules in numbers

  • 4 m

    Minimum height of each tank's vent pipe, and its distance from neighbours and the sales room Petroleum Rules 2002

  • 1.2 m

    Height of the boundary wall or fence on sides other than the drive way Petroleum Rules 2002

  • 100 m

    Radius of protected works the plan for PESO's prior approval must show PESO SOP

  • 7 ohms

    Maximum resistance to earth of a tank, tested every 12 months Petroleum Rules 2002

  • 6 m

    Outer edge of the zone 2 hazardous area around an outdoor dispenser Petroleum Rules 2002

  • 6 m

    Minimum distance between a CNG dispenser and a petrol or diesel dispenser (Form G, Table II) Gas Cylinders Rules

  • 10 kg

    DCP extinguisher at each CNG dispensing unit, compressor and cascade area Gas Cylinders Rules

  • 30 days

    Latest a Form XIV renewal can reach PESO before expiry and still keep the licence in force Petroleum Rules 2002

Petrol pump licence and fire NOC fees in the official schedules

These are the fees an Act, rule or order sets. Dealer selection fees, construction and consultants are private costs and are not listed.

As published

  • Form XIV licence, each class of petroleumRs 5,000 a yearFor the first 50 KL, plus Rs 50 per further KL; at most Rs 50,000 a year per class. Part A of the First Schedule as substituted by G.S.R. 762(E) of 10 August 2018 (Rs 1,000 in 2002); unchanged by the 2019, 2021 and 2024 amendments G.S.R. 762(E), 2018
  • Competent person's inspection and certificate (rule 130)Rs 3,000 per stationPlus Rs 1,000 for each underground tank tested under rule 126 (Part B) G.S.R. 762(E), 2018
  • Prior approval of plans (rule 131)Rs 2,000Rs 400 in 2002, Rs 2,000 since 2018, kept in the 2024 Part C; alteration approval, amendment and transfer are Rs 2,000 each G.S.R. 154(E), 2024
  • Late Form XIV renewalTwice the feeFor the first year, if the application misses 30 days before expiry or comes within 30 days after it Petroleum Rules 2002
  • Form G CNG dispensing licenceRs 10,000Rs 5,000 for micro and small enterprises and startups, Rs 2,000 for women entrepreneurs (Schedule V as substituted on 9 June 2025) G.S.R. 386(E) of 2025
  • Fuel dispenser type approval (PESO)Rs 2,000 per componentPlus Rs 2,000 for the whole assembly PESO SOP
  • District NOC, MeghalayaNo feeRs 10 court-fee stamp on the identity enclosure; 60 days Meghalaya DM SOP
  • Gujarat fire certificate, single-storey petrol pumpRs 5,000 + Rs 20 per m²Plan approval Rs 5,000, certificate Rs 20 per m² built-up, renewal Rs 5,000; Rs 7,000 + Rs 30 per m² above one floor Gujarat Fire Safety Compliance Portal
  • Rajasthan fire NOCRs 2, 1.50 or 1 per sq ftNagar Nigam, Parishad or Palika; renewal Rs 10,000, 7,500 or 5,000 Rajasthan UDH
  • Kerala petrol bunk NOCRs 20,000Once in 2 years Kerala Fire and Rescue Services
  • Punjab fire NOC, petrol pumpRs 50,000High-hazard group in the 2021 schedule Local Govt Punjab

PESO fees are paid by e-payment or the Non-Tax Receipt Portal (rule 13 as amended in 2024). Every state's fire NOC schedule is on the fire NOC fees page.

Penalties for a petrol pump without a licence, NOC or renewal

The Petroleum Act's fines are small, at Rs 1,000 to Rs 5,000; the rules add suspension, cancellation and refusal to renew. Rajasthan fines a missing fire NOC.

OffencePenaltyLaw
Storing petroleum without a licence, or breaking the rules or licence conditionsUp to 1 month, a fine up to Rs 1,000, or both; a later offence up to 3 months, Rs 5,000, or bothSection 23, Petroleum Act 1934 Petroleum Act 1934
Contravening the Act, rules or a licence conditionSuspension of up to 3 months, or cancellation; interim suspension without a hearing where danger is imminentRule 152, Petroleum Rules 2002 Petroleum Rules 2002
Losing the right to use the siteThe rule 144 NOC can be cancelled, and the licence then stands cancelledRules 150 and 152(1)(ii) Petroleum Rules 2002
Renewal received more than 30 days after expiryNo renewal; a fresh licence is neededRule 148(8) Petroleum Rules 2002
Altering the premises without prior approvalLicence liable to cancellation if premises do not match the approved planForm XIV; rule 146 Petroleum Rules 2002
No fire NOC, or equipment missing or not working, RajasthanRs 5,000Municipalities Act 2009, s.291, applied by the 2023 order Rajasthan UDH
Breaking a Form G CNG licence conditionLiable to cancellation, and punishable as section 9B of the Explosives Act providesForm G, Gas Cylinders Rules 2016 Gas Cylinders Rules

A draft Petroleum (Amendment) Bill, 2026 proposes up to 3 years or Rs 25 crore for unlicensed activity; it is a draft, reported in the news section below. Every state's fire NOC penalties are on the penalties page.

Where petrol pump approvals fail, and the fix

Most refusals and cancellations turn on who signs, how distance is measured and what was changed after approval. These 7 come from the rules and 3 High Court records.

  • If The District Magistrate signs or cancels the NOC in a police commissionerate city

    File with the Commissioner or Deputy Commissioner of Police; the MP High Court quashed an Indore DM's 2022 cancellation for want of jurisdiction. MP High Court

  • If A district authority cancels the NOC after a fire

    Rule 150 allows cancellation only where the right to the site ends; safety lapses go to PESO under rule 152, as the MP High Court held. MP High Court

  • If PESO refuses because a college is within 30 m

    The CPCB rule names schools, hospitals of 10 or more beds and designated housing; the Kerala High Court set such a refusal aside in 2025. Kerala High Court

  • If A school's distance measured to its building, not its wall

    The Kerala High Court treated the school and its compound as one unit in 2026; measure to the compound wall. LiveLawnews report

  • If A drawing that leaves out a neighbouring boundary

    PESO told the Kerala High Court an approval was obtained without showing a college wall; show every protected work within 100 m. Kerala High Court

  • If An NOC more than 3 years old when the licence is sought

    PESO accepts a rule 144 NOC only within 3 years of its issue; apply again. G.S.R. 154(E), 2024

  • If Renewal sent after expiry

    Within 30 days after expiry it costs twice the fee; later, there is no renewal at all. Petroleum Rules 2002

Does your petrol pump or CNG station need a fire NOC? 10 cases

Every petrol pump needs Form XIV and, unless it sits in a gas station, the rule 144 NOC. Whether the state also issues a fire NOC depends on the state.

  1. If A new petrol pump in Jaipur, Kota or Udaipur

    Yes: Table 1 of the 2023 order lists all petrol pumps, renewed generally every year. Fire NOC Rajasthan Rajasthan UDH

  2. If A highway petrol pump in Gujarat

    Yes: petrol pumps sit in the hazardous storage and handling row; fees from Rs 5,000 plus Rs 20 per m². Fire NOC Gujarat Gujarat Fire Safety Compliance Portal

  3. If A retail outlet in Cuttack or Puri

    Yes: an Assistant Fire Officer issues it, valid 2 years. Fire NOC Odisha Order 50908 of 2019

  4. If A filling station in Jammu or Srinagar

    Yes: class C3 needs a fire NOC, and S.O. 304 keeps it 30 m from the nearest house, school or health centre. Fire NOC Jammu and Kashmir J&K H&UDD

  5. If A fuel outlet in Agartala

    Yes, and never by self-certification, whatever its size. Fire NOC Tripura 2026 Directorate of Fire and Emergency Services, Tripura

  6. If A petrol pump in Gwalior or Bhopal

    The e-Nagar Palika Fire and Explosive route, with the LOI and the SDM's land diversion order. Fire NOC MP MP e-Nagar Palika manual

  7. If A petrol bunk in Kochi

    A petrol bunk NOC under the Petroleum Act at Rs 20,000, paid once in 2 years under the 2024 fee order. Fire NOC Kerala Kerala Fire and Rescue Services

  8. If A pump outside Shillong

    The fire department's NOC is an enclosure to the District Magistrate's NOC, decided in 60 days. Fire NOC Meghalaya Meghalaya DM SOP

  9. If A CNG station anywhere in India

    Form G from PESO with no District Authority NOC since 5 June 2026; the state's fire rules still apply. G.S.R. 447(E), 2026

  10. If A pump in Indore, a commissionerate city

    The rule 144 NOC is the Commissioner of Police's, not the District Magistrate's. MP High Court

Petrol pump licence and NOC worked cases: 6 sites

Flamekite's reading of the rules for 6 example outlets; the sites are illustrations, the figures are the instruments'.

  1. Case 1

    A town pump with 20 KL of petrol and 40 KL of diesel

    2 underground tanks, 4 pumps.

    What applies Each class is under 50 KL, so Form XIV costs Rs 5,000 + Rs 5,000 = Rs 10,000 a year, or Rs 30,000 for a 3-year renewal (Flamekite's arithmetic). 4 pumps need at least 8 extinguishers and 8 sand drums. G.S.R. 762(E), 2018

  2. Case 2

    A highway pump with 30 KL of petrol and 120 KL of diesel

    3 tanks on a national highway.

    What applies Petrol Rs 5,000; diesel Rs 5,000 + 70 x Rs 50 = Rs 8,500; Rs 13,500 a year in all (Flamekite's arithmetic). NHAI comments in the rule 144 file. G.S.R. 762(E), 2018

  3. Case 3

    A new pump 40 m from a primary school

    Fill point and vent measured to the school's compound wall.

    What applies Inside 50 m but over 30 m: possible only with the additional safety measures PESO prescribes. Under 30 m it is barred. Kerala High Court

  4. Case 4

    A pump in Ahmedabad with a 120 m² sales building

    Single storey under 15 m.

    What applies Plan approval Rs 5,000, certificate 120 x Rs 20 = Rs 2,400, renewal Rs 5,000 (Flamekite's arithmetic, on built-up area). Gujarat Fire Safety Compliance Portal

  5. Case 5

    A pump in a Jaipur Nagar Nigam area, 1,500 sq ft built-up

    A sales room and office of 1,500 sq ft gross built-up area.

    What applies 1,500 x Rs 2 = Rs 3,000 for the NOC, renewed generally every year at Rs 10,000 (Flamekite's arithmetic). Rajasthan UDH

  6. Case 6

    An existing pump adding a CNG dispenser

    Mother-station gas, a compressor and cascade on site.

    What applies Form G with no District Authority NOC since 5 June 2026; the CNG dispenser stays 6 m from petrol and diesel dispensers, and each CNG unit gets a 10 kg DCP. Gas Cylinders Rules

Petrol pump rules, dated: 1934 to 2026

Fourteen dated steps that shaped what a petrol pump owes today.

  1. 1934

    The Petroleum Act, 1934 (Act 30 of 1934) sets classes A, B and C and, in section 23, fines of Rs 1,000 and Rs 5,000. Petroleum Act 1934

  2. 13 March 2002

    The Petroleum Rules, 2002 (G.S.R. 204(E)) replace the 1976 Rules, with Form XIV and the rule 144 NOC. Petroleum Rules 2002

  3. 28 October 2011

    Uttarakhand notifies the petrol pump NOC recommendation as a 15-day service. UFES charter

  4. 22 November 2016

    The Gas Cylinders Rules, 2016 bring Form G for CNG stations. Gas Cylinders Rules

  5. 6 March 2019

    Odisha lists retail outlets as a fire-risk class in rule 9(1)(e). Odisha Rules 2019

  6. 7 January 2020

    CPCB sets the 50 m and 30 m siting criteria for new retail outlets. Kerala High Court

  7. 2 May 2022

    A decantation fire at an Indore pump; the outlet is sealed on 3 May. MP High Court

  8. 8 September 2022

    The MP High Court quashes the NOC cancellation: no jurisdiction in a commissionerate city, and rule 150 is only about the site. MP High Court

  9. 14 September 2023

    Rajasthan's UDH order lists every petrol pump in Table 1. Rajasthan UDH

  10. 13 December 2023

    Gujarat's Fire Regulations put petrol pumps in the hazardous fee row. Gujarat Fire Safety Compliance Portal

  11. 4 March 2024

    G.S.R. 154(E): fire department comments in the NOC proforma, no NOC for Form XIV in gas stations, Rs 2,000 plan fee. G.S.R. 154(E), 2024

  12. 18 August 2025

    The Kerala High Court holds that colleges are outside the CPCB distance rule. Kerala High Court

  13. 1 December 2025

    Jammu and Kashmir's S.O. 304 sets 30 m and 300 m siting rules for filling stations. J&K H&UDD

  14. 5 June 2026

    G.S.R. 447(E) and 448(E) omit the District Authority NOC for CNG and auto-LPG licences. G.S.R. 447(E), 2026

Petrol pump law changes and court rulings in the news, 2025 to 2026

From news reports, not yet an official source.

Two drafts were open for comment in autumn 2026. Neither was law on 25 October 2026, and Flamekite did not find MoPNG's own notice of the draft Bill.

  • Outlook Business (PTI) reports India's fuel stations crossed 1,00,266 at the end of November 2025 on PPAC data, up from 50,451 in 2015; IOC runs 41,664. Outlook Businessnews report

  • LiveLaw reports the Kerala High Court upheld an ADM's refusal of a rule 144 NOC where a school's compound wall was 25.15 m away; the oil company had already obtained the fire department's NOC. LiveLawnews report

  • TeamLease RegTech reports draft Petroleum (Amendment) Rules, 2026 (G.S.R. 781(E)) that add a definition of District Fire Officer; the Gazette text was not found. TeamLease RegTechnews report

  • Outlook Business reports MoPNG's draft Petroleum (Amendment) Bill, 2026: up to 3 years or Rs 25 crore for unlicensed activity, and civil penalties up to Rs 2.5 crore for licence breaches. Outlook Businessnews report

Petrol pump NOC myths, checked against the rules

  • You may have read

    The PESO licence is the fire NOC.

    Myth

    What the sources say

    Form XIV licenses the storage. Rajasthan, Gujarat, Odisha and Jammu and Kashmir also require a state fire NOC, and the district NOC records the fire service's comments since 2024. G.S.R. 154(E), 2024

  • You may have read

    The District Magistrate always signs the petrol pump NOC.

    Myth

    What the sources say

    In a town with a Commissioner of Police, the Commissioner or a Deputy Commissioner of Police is the District Authority under rule 2. Petroleum Rules 2002

  • You may have read

    A pump must be 50 m from any college or institution.

    Myth

    What the sources say

    The CPCB rule names schools, hospitals of 10 or more beds and designated residential areas; the Kerala High Court held colleges are not covered. Kerala High Court

  • You may have read

    A new CNG station needs the District Magistrate's NOC.

    Myth

    What the sources say

    Rule 48 of the Gas Cylinders Rules, which required it, was omitted on 5 June 2026. G.S.R. 447(E), 2026

  • You may have read

    A Form XIV licence lasts for ever once granted.

    Myth

    What the sources say

    It runs to 31 December of the final year, at most 3 years, and cannot be renewed more than 30 days after expiry. Petroleum Rules 2002

  • You may have read

    After a fire the district can cancel a pump's NOC.

    Myth

    What the sources say

    Rule 150 allows it only where the right to the site ends; the MP High Court quashed a 2022 cancellation made for a safety lapse. MP High Court

Where a petrol pump owner applies online

These 7 official portals took petrol pump licences, gas station licences or state fire applications on 25 October 2026.

PESO offices that issue petrol pump licences

Form XIV is granted by PESO's circle and sub-circle offices. These 8 addresses are as PESO publishes them; the full list of sub-circles is on its contact page.

  • Chief Controller of Explosives, Head Office PESO contacts

    PESO headquarters

    Address
    A Block, CGO Complex, Fifth floor, Seminary Hills, Nagpur 440006
  • North Circle, Faridabad PESO contacts

    Joint Chief Controller of Explosives

    Address
    Hall No 502 and 507, Level-5, Block B, Old CGO Complex, NH IV, Faridabad 121001
  • South Circle, Chennai PESO contacts

    Joint Chief Controller of Explosives

    Address
    A and D Wing, Block 1-8, Second Floor, Shastri Bhavan, 26 Haddows Road, Nungambakkam, Chennai 600006
  • East Circle, Kolkata PESO contacts

    Joint Chief Controller of Explosives

    Address
    8th floor, 2nd MSO Building, 234/1 A.J.C. Bose Road, Nizam Palace, Kolkata 700020
  • West Circle, Navi Mumbai PESO contacts

    Joint Chief Controller of Explosives

    Address
    A-1 and A-2 Wing, 5th Floor, C.G.O. Complex, CBD Belapur, Navi Mumbai 400614
  • Central Circle, Agra PESO contacts

    Joint Chief Controller of Explosives

    Address
    A-Wing, 2nd Floor, Kendralaya, 63/4 Sanjay Place, Agra 282002
  • Bhopal Circle Office PESO contacts

    Joint Chief Controller of Explosives

    Address
    E-7/77, IInd floor, Lala Lajpatrai Society, Near 12 No. Bus Stop, Arera Colony, Bhopal 462016
  • Hyderabad Circle Office PESO contacts

    Joint Chief Controller of Explosives

    Address
    Room No. 602, 6th floor, C.G.O. Towers, Kavadiguda, Secunderabad 500080

What Flamekite could not confirm about petrol pump rules

Six questions a petrol pump owner asks that no official text we read on 25 October 2026 answers.

OISD-STD-225 (petroleum retail outlets, October 2010 edition, as OISD listed it on 24 October 2026) could not be read: oisd.gov.in failed with a certificate error on 25 October 2026 and was not bypassed, so no OISD clause is quoted here. We also found no official text of the 'additional safety measures' PESO prescribes for a pump between 30 m and 50 m of a school, and did not read the CPCB guideline PDF itself, only its paragraph H as the Kerala High Court quotes it.

PESO's consolidated text of the Petroleum Rules predates at least one amendment: the 2024 amendment refers to a Form XIV condition 24 that the copy does not print, so a numbered condition here may have moved. Whether Form G's Rs 10,000 is charged once or for each year of the licence is not stated in the Schedule V row we read, and the SMPV fee for an auto-LPG licence after its 2025 amendments was not read; the June 2026 draft Third Amendment to the Gas Cylinders Rules, which touches CNG stations, was not read either.

We found no petrol-pump-specific fire NOC line for Telangana, Karnataka, Delhi, Haryana, Bihar or West Bengal, or Maharashtra beyond Pune, and Punjab's fee schedule after 2021 was not readable. The draft Petroleum (Amendment) Bill, 2026 and draft rules G.S.R. 781(E) of 3 September 2026 are known only from news summaries; what the proposed District Fire Officer would do was not confirmed.

Questions about fire NOCs for petrol pumps

Is a fire NOC mandatory for a petrol pump?

Every petrol pump needs a PESO Form XIV licence and, outside gas stations, the District Authority's rule 144 NOC, which records fire department comments since March 2024. A separate state fire NOC is required in Rajasthan for all pumps, and in Gujarat, Odisha, Jammu and Kashmir, Tripura and Lakshadweep as listed premises.

Who gives the NOC for a petrol pump?

The District Authority under rule 144 of the Petroleum Rules, 2002: the Commissioner or a Deputy Commissioner of Police in a commissionerate town, the District Magistrate or an Additional District Magistrate elsewhere. It must decide within 3 months, and PESO accepts the NOC for 3 years.

How much is the PESO licence fee for a petrol pump?

Form XIV costs Rs 5,000 a year for each class of petroleum up to 50 KL, plus Rs 50 for every further KL, capped at Rs 50,000 a year per class (Part A of the First Schedule since 10 August 2018). Plan approval is Rs 2,000, and a late renewal costs twice the fee.

How far must a petrol pump be from a school?

Under CPCB's guidelines of 7 January 2020, a new outlet's fill point, dispensers and vent should be 50 m from schools, hospitals of 10 or more beds and designated residential areas; with PESO's added safety measures it may be closer, but never under 30 m. Kerala's High Court measures to the school's compound wall.

How many fire extinguishers does a petrol pump need?

Form XIV condition 20 asks for at least 2 foam or dry chemical extinguishers and 2 tins or drums of dry sand for each pump. A CNG station adds a 10 kg DCP at each dispenser, compressor and cascade area, and a 4.5 kg CO2 per 25 m² of electrical room.

How long is a petrol pump licence valid?

A Form XIV licence runs to 31 December of the year it is granted or renewed for, at most 3 years. Apply at least 30 days before expiry to keep it in force; within 30 days after expiry it costs twice the fee, and later it cannot be renewed.

Does a CNG station need a district NOC?

No, since 5 June 2026: G.S.R. 447(E) omitted rule 48 of the Gas Cylinders Rules. A Form XIV licence inside a CNG, auto-LPG or LNG station has needed no rule 144 NOC since 4 March 2024. State fire rules still apply.

Can the district cancel a petrol pump NOC after a fire?

Under rule 150 the District Authority or State Government may cancel the NOC only if the licensee loses the right to use the site. The MP High Court quashed a 2022 cancellation made after a fire; safety breaches are for PESO, which can suspend for up to 3 months or cancel.

Keep reading

Free tools for this

Words on this page, explained

Sources

Each source was opened and read on the date shown. How Flamekite checks its sources

  1. Gazette of India Extraordinary, 5 June 2025 (copy hosted by Petroleum and Explosives Safety Organisation (PESO), DPIIT): Static and Mobile Pressure Vessels (Unfired) (Amendment) Rules, 2025, G.S.R. 374(E) of 5 June 2025: Schedule I substituted with MSE, startup and women-entrepreneur fees, 10-year licences, rule 11A online filing, rule 47(1A), (1B), (7) and (8), Form LS-1D and Schedule V for liquefied hydrogen (opens in a new tab)checked 25 October 2026
  2. Petroleum and Explosives Safety Organisation (PESO), DPIIT: consolidated text of G.S.R. 204(E), 13 March 2002: The Petroleum Rules, 2002: rule 2 definitions, Chapter IV electrical, rules 116 to 155 (storage, licences, NOC, renewal, cancellation, appeals), Form XIV and its conditions, the First Schedule fees and the Fourth Schedule hazardous areas (opens in a new tab)checked 25 October 2026
  3. Gazette of India Extraordinary, Part II Section 3(i), 10 August 2018 (Ministry of Petroleum and Natural Gas; eGazette ID 188439): Petroleum (Amendment) Rules, 2018 (G.S.R. 762(E), 10 August 2018): fixed rupee amounts in the rules replaced by references to the First Schedule, and a new First Schedule in Parts A (licence fees), B (competent person fees) and C (other fees) (opens in a new tab)checked 26 October 2026
  4. Gazette of India Extraordinary, Part II Section 3(i), No. 142, 4 March 2024 (Ministry of Petroleum and Natural Gas; copy hosted by PESO): Petroleum (Amendment) Rules, 2024 (G.S.R. 154(E)): rule 144(6a), the new NOC proforma with fire department comments, rules 117, 122, 126, 130, Form XIV conditions and the Part C fees (opens in a new tab)checked 25 October 2026
  5. Petroleum and Explosives Safety Organisation (PESO), DPIIT: Guidelines for issuing licences under the Petroleum Rules, 2002: who issues Form XIV, the documents for each transaction, the CPCB undertaking, approved dispensers and online filing through the National Single Window (opens in a new tab)checked 25 October 2026
  6. Petroleum and Explosives Safety Organisation (PESO), DPIIT: bilingual copy of G.S.R. 1081(E), 22 November 2016: Gas Cylinders Rules, 2016: CNG station definitions, rule 48 (district NOC, as made), rule 51 validity, Schedule V fee and Form G licence conditions for CNG dispensing stations (opens in a new tab)checked 25 October 2026
Show all 44 sourcesShow fewer
  1. Petroleum and Explosives Safety Organisation (PESO), DPIIT: bilingual copy of the Gazette text: Static and Mobile Pressure Vessels (Unfired) Rules, 2016: auto-LPG dispensing stations, Form LS-1B, rule 51 validity and the Schedule I fees (opens in a new tab)checked 25 October 2026
  2. Oil Industry Safety Directorate (OISD), Ministry of Petroleum and Natural Gas: OISD standards list: OISD-STD-117, 118, 210, 225 and 244 with their editions (105 standards) (opens in a new tab)checked 24 October 2026
  3. Petroleum Act, 1934 as amended (consolidated copy hosted by the Appellate Tribunal for Electricity): The Petroleum Act, 1934 (Act 30 of 1934): section 2 classes A, B and C, sections 7 and 8 (storage without a licence) and section 23 (penalties) (opens in a new tab)checked 25 October 2026
  4. Home Department, Government of Odisha: Odisha Fire Prevention and Fire Safety (Amendment) Rules, 2019, notification No. 10573/H of 6 March 2019: rule 9(1) classes, rules 10, 13(3) and 22(5) (opens in a new tab)checked 24 October 2026
  5. Jammu and Kashmir Official Gazette (Extraordinary), copy hosted by the Housing and Urban Development Department: J&K Official Gazette, Vol. 134, No. 39-4, 24 December 2021: the Jammu and Kashmir Unified Building Bye-Laws, 2021 (opens in a new tab)checked 24 October 2026
  6. Gazette of Meghalaya No. 12, Part IIA, 25 March 2021 (copy hosted by the Urban Affairs Department): Meghalaya Building Bye-Laws, 2021 (No. UAU.73/2016/Pt/402 of 9 March 2021): A2.30 high-rise, A2.59 special buildings, A4.1.3, A10 occupancy and fire clearance, C11 (opens in a new tab)checked 25 October 2026
  7. High Court of Kerala (copy of the judgment hosted by Verdictum): WP(C) No. 12226 of 2025, Bindhu Kuniparambath v. Joint Chief Controller of Explosives, 18 August 2025 (2025:KER:62117): CPCB siting criteria para H quoted; colleges are not schools (opens in a new tab)checked 25 October 2026
  8. Urban Development, Housing and Local Self Government Departments, Rajasthan: Joint order No. P.11(9)UDH/2020 Part, 14 September 2023, on the fire safety certificate and fire NOC (18-page Hindi scan) (opens in a new tab)checked 25 October 2026
  9. High Court of Madhya Pradesh, Indore Bench: WP No. 17389 of 2022, M/s Laxmi Service Station v. Union of India, 8 September 2022: decantation fire, NOC cancellation under rule 150 quashed (opens in a new tab)checked 25 October 2026
  10. Gazette of India Extraordinary (Ministry of Commerce and Industry, DPIIT; copy hosted by PESO): Gas Cylinders (Second Amendment) Rules, 2026 (G.S.R. 447(E), 5 June 2026): rule 48, the District Authority NOC, omitted (opens in a new tab)checked 25 October 2026
  11. Gazette of India Extraordinary (Ministry of Commerce and Industry, DPIIT; copy hosted by PESO): Static and Mobile Pressure Vessels (Unfired) (Amendment) Rules, 2026 (G.S.R. 448(E), 5 June 2026): rule 47, the District Authority NOC, omitted (opens in a new tab)checked 25 October 2026
  12. Gazette of India Extraordinary, 16 June 2025 (copy hosted by Petroleum and Explosives Safety Organisation (PESO)): Gas Cylinders (Amendment) Rules, 2025, G.S.R. 386(E) of 9 June 2025: Schedule V substituted, with lower fees for micro and small enterprises, startups and women entrepreneurs (opens in a new tab)checked 25 October 2026
  13. Office of the District Magistrate (Arms), Meghalaya (Invest Meghalaya single window): Standard Operating Procedure and Checklist: NOC for setting up petroleum, diesel and naphtha storage and sale, with the fire department NOC among the enclosures (opens in a new tab)checked 25 October 2026
  14. Gujarat Fire Safety Compliance Portal (GujFireSafety CoP): Gujarat Fire Prevention and Life Safety Measures Regulations, 2023 (fees in Annexure 8) (opens in a new tab)checked 25 October 2026
  15. Kerala Fire and Rescue Services: Fee structure, G.O.(Ms)No.272/2024/Home (opens in a new tab)checked 24 October 2026
  16. Directorate of Local Government, Punjab (Wayback Machine copy of 21 March 2022 of the portal's fee download): Letter No. S4-DSMS-(Fire)-2021/41343 of 8 October 2021: new fees for online fire NOCs, by NBC zone, with provisional, renewal and 30-day rules (opens in a new tab)checked 25 October 2026
  17. Home Department, Government of Odisha: Order No. 50908 of 19 November 2019: procedure for issue and renewal of Fire Safety Certificates and Fire Safety Recommendations (issuing officer, validity, inspecting team and time limit by building type) (opens in a new tab)checked 25 October 2026
  18. Housing and Urban Development Department, Government of Jammu and Kashmir: Notification S.O. 304 of 1 December 2025 (No. HUD-LSG/39/2025): amendments to the J&K Unified Building Bye-Laws 2021, online portal, 21-day NOCs, Common Application Form (opens in a new tab)checked 25 October 2026
  19. Directorate of Fire and Emergency Services, Tripura: Tripura Fire Safety Rules, 2026 (Tripura Gazette, 2 June 2026) (opens in a new tab)checked 24 October 2026
  20. Urban Administration and Development Department, Madhya Pradesh (e-Nagar Palika): User manual, citizen side: Fire Safety Certificate, version 1.0 (15 November 2025, in force from 30 May 2025) (opens in a new tab)checked 24 October 2026
  21. Uttarakhand Fire and Emergency Services: Services notified under the Right of Service: 32 services with designated officers, time limits, appellate officers and notifying orders (opens in a new tab)checked 24 October 2026
  22. Petroleum and Explosives Safety Organisation (PESO), DPIIT: PESO online licensing portal for the Petroleum, Gas Cylinders and SMPV Rules (login) (opens in a new tab)checked 25 October 2026
  23. National Single Window System, Government of India: NSWS: PESO approvals and licences filed through the national single window (opens in a new tab)checked 25 October 2026
  24. Gujarat State Fire Prevention Services: FSCOP citizen login: FSPA, FSCA, FSCR, inspections and mock drills (opens in a new tab)checked 24 October 2026
  25. Urban Administration and Development Department, Madhya Pradesh (e-Nagar Palika): e-Nagar Palika home and user-manual pages: citizen login, Fire NOC MIS, helpline (opens in a new tab)checked 24 October 2026
  26. Local Self Government Department, Rajasthan: Fire service: Fire NOC registration and certificate verification (nodal officer and helpline) (opens in a new tab)checked 24 October 2026
  27. Sewa Setu, Government of Assam: Fire NOC for one storied, multi-storied or high-rise building (Form I): required documents, and the Form II to XIII services (opens in a new tab)checked 25 October 2026
  28. Petroleum and Explosives Safety Organisation (PESO), DPIIT: Contact us: head office at Nagpur and the circle and sub-circle offices with addresses, phones and email (opens in a new tab)checked 25 October 2026
  29. Fire Service Department, Andaman and Nicobar Administration (NIC portal): Online Service Portal of Fire Service Department: new and renewal Fire Clearance Certificates, inspections, incident certificates, the 9 premises classes, critical-activity checklists and the Aberdeen Bazar contact (last modified 28 July 2025) (opens in a new tab)checked 25 October 2026
  30. Lakshadweep Gazette Extraordinary Vol. LXII No. 42, 3 September 2026: Lakshadweep Fire and Emergency Services Rules, 2026 (Rule 12: 5-year fire safety certificate) (opens in a new tab)checked 24 October 2026
  31. Government of Goa, Official Gazette Series II No. 31 (Extraordinary No. 3), 3 November 2022: Notification 41/1/2022/PG(Notification)/235 under the Goa (Right of Citizens to Time-bound Delivery of Public Services) Act, 2013: DFES services 81 to 116 with designated officers, time limits and appellate authorities (opens in a new tab)checked 24 October 2026
  32. Pune Municipal Corporation: PMC online services (9 fire NOC service types on services.pmc.gov.in) (opens in a new tab)checked 24 October 2026
  33. Government of Tamil Nadu, Gazette Extraordinary No. 263, 6 June 2025: Tamil Nadu Fire and Rescue Services Act, 2025 (TN Act 37 of 2025) (opens in a new tab)checked 25 October 2026
  34. Uttar Pradesh Gazette Extraordinary, 18 January 2024 (copy hosted by UP Fire and Emergency Services): Uttar Pradesh Fire and Emergency Services Rules, 2024, Notification No. 181/VI-Pu-8-2024-801(1)-2023: rules 40 to 56, 65, 66 and 72, Schedules VI and VII, Forms A-4, A-8 and A-11 to A-13 (opens in a new tab)checked 25 October 2026
  35. LiveLaw, 9 January 2026: District Authority can reject petrol pump NOC for violating CPCB distance norms from schools: Kerala High Court (Ashwin Abraham Cherian v. HPCL, WP(C) 7794 of 2024) (opens in a new tab)News report · checked 25 October 2026
  36. Outlook Business (PTI), 25 December 2025: India's petrol pump count crosses 1 lakh, doubles in a decade (PPAC data to end-November 2025) (opens in a new tab)News report · checked 25 October 2026
  37. TeamLease RegTech: Draft Petroleum (Amendment) Rules, 2026 (G.S.R. 781(E), issued 3 September 2026): a District Fire Officer definition, e-payment and ISO tank procedure (opens in a new tab)News report · checked 25 October 2026
  38. Outlook Business, 30 September 2026: Petroleum (Amendment) Bill 2026: decriminalisation of licence breaches, Rs 25 crore fine, the MoPNG draft explained (opens in a new tab)News report · checked 25 October 2026