Fire NOC in Telangana: the 24 m residential rule, fees, timelines and renewal

Updated By Flamekite Editorial DeskFacts checked against official sources on

Quick answer

In Telangana a fire NOC is issued by the Telangana Fire, Disaster Response, Emergency and Civil Defence Department (TGFD) under section 13 of the Fire Service Act, 1999, in two stages: a Provisional NOC before plan approval and an Occupancy NOC before the building is used. You apply online at fire.telangana.gov.in.

Since 7 October 2026, circular Rc.No.3455/MSB/2026 requires a Provisional NOC for residential apartment buildings only at 24 m and above (it was 18 m). Every other occupancy keeps its old trigger: above 15 m for commercial buildings, and 6 m or a 500 m² plot for schools, cinemas, function halls and places of worship.

Residential apartment trigger
24 m
Was 18 m; from 7 October 2026
Before and after
Official timeline
7 or 14 days
Up to 15 m, or above 15 m
Timelines
Fire precaution fee
Rs 10 per m²
Of total built-up area
Fee table
Renewal period
5 years or 1 year
Two official sources disagree
The conflict

Telangana fire NOC at a glance

The Telangana fire NOC in ten rows, each with its official source.
WhatThe ruleSource
LawFire Service Act, 1999, section 13 (the NOC provision), with the Telangana Fire and Emergency Operations and Levy of Fee Rules, 2006TSDRFS circular 2016
Issued byTelangana Fire, Disaster Response, Emergency and Civil Defence Department (TGFD), earlier styled Telangana State Disaster Response and Fire Services (TSDRFS); the Director General approvesTGFD circular 3455
StagesProvisional NOC at the plan stage; Occupancy NOC before use; Renewal of NOC after thatTGFD circulars
Residential apartments24 m and above, for fresh Provisional NOC applications received on or after 7 October 2026 (18 m and above before)TGFD circular 3455
Commercial or businessMore than 15 m; unchanged in 2026TSDRFS circular 2016
Schools, cinemas, function halls, places of worshipPlot above 500 m² or height 6 m and above; unchanged in 2026TSDRFS circular 2016
Official timeline7 days for buildings up to 15 m; 14 days above 15 mTGFD Fire NOC note
Fire precaution feeRs 10 per m² of total built-up area (G.O.Ms.No.142 of 9 August 2016)G.O.Ms.No.142
RenewalConflicting: every 5 years under the 2016 circular, every year in the department FAQ and Citizen CharterTGFD FAQ
Apply atfire.telangana.gov.in, Building NOC login (Login1.aspx)TGFD Building NOC

Telangana fire rules before and after 7 October 2026

The four requirements circular Rc.No.3455/MSB/2026 revised, in the circular's own table order.
OptionBefore 7 October 2026From 7 October 2026 (fresh Provisional NOC applications)Source
Provisional NOC, residential apartmentsRequired at 18 m and aboveRequired at 24 m and above, for residential apartment buildings only; no change for other occupancy typesTGFD circular 3455
Fire towerRequired above 15 mRequired at 24 m and above, for all occupancy typesTGFD circular 3455
Fire Command Centre (FCC) roomRequired above 15 mRequired at 24 m and above, for all occupancy typesTGFD circular 3455
DG room ventilation in basementsEnclosed by a 120-minute fire-rated wall with a fire doorLouvres allowed above a fire-rated wall at least 1 m high, if the wall has a 2-hour fire-resistance ratingTGFD circular 3455
Applications coveredAll applications filed up to 6 October 2026Only fresh Provisional NOC applications received on or after 7 October 2026TGFD circular 3455

How to get a fire NOC in Telangana, from plans to renewal

  1. Check whether section 13 catches your building

    Measure the height and plot area against the Telangana triggers: residential apartments 24 m and above (fresh applications from 7 October 2026), commercial above 15 m, schools and assembly buildings 6 m or a 500 m² plot.

  2. Apply for the Provisional NOC before plan sanction

    Register on the Building NOC login at fire.telangana.gov.in, upload the drawings with fire systems marked in red, and pay the fee online. The sanctioning authority may not approve plans without this NOC (section 13).

  3. Track the file online

    You get an SMS at each stage. The department's target is 7 days for a building up to 15 m and 14 days above 15 m; the certificate is e-mailed and can be downloaded.

  4. Build to the approved drawings

    Deviations from the approved fire drawings invite prosecution of the builder, architect and site engineer under sections 31 and 32 of the Fire Service Act, 1999.

  5. Apply for the Occupancy NOC before anyone moves in

    Upload the Provisional NOC and the as-built plans. A committee inspects the gates, open spaces, means of escape and a working test of every fire system before the Director General approves.

  6. Renew and upload fire audits

    Apply for Renewal of NOC on the same portal before the period on your certificate ends, and upload the third-party fire audit certificate through the Fire Audit module every January, or every January and July for the tallest and riskiest buildings (circular of 28 January 2020). G.O.Ms.No.15 of 2026 (para 7) also asks the owner for a certificate each January and July.

What Telangana circular Rc.No.3455/MSB/2026 actually says

The 24 m change is a Director General's circular memorandum dated 26 September 2026, not a Government Order. Its operative paragraph is one sentence.

Word for word

These instructions shall come into force with effect from 07.10.2026 and shall apply only to fresh applications for Provisional NOCs received on or after that date.

Circular Memorandum Rc.No.3455/MSB/2026, para 3, Telangana Fire, Disaster Response, Emergency and Civil Defence Department, 26 September 2026 TGFD circular 3455

The circular follows G.O.Ms.No.95 of the Municipal Administration and Urban Development (Plg. III) Department of 21 March 2026, which amended building regulations, a Telangana Builders Federation letter of 19 August 2026, and a meeting of CREDAI, NAREDCO and the Federation with the Director General on 23 September 2026. Its table changes the residential apartment row only and says, in so many words, "No change for other occupancy types." It was copied to ADS Softek and the Centre for Good Governance to change the online application and scrutiny system.

Telangana fire NOC triggers and risk categories by occupancy

The 2016 renewal circular sorts every section 13 building into four risk categories, R1 to R4, which set how often the department makes random inspections. Only the residential apartment row moved in 2026.

Height or area in the 2016 tableRisk categoryRandom inspectionsChange on 7 October 2026
Residential apartments TGFD circular 3455Above 18 mR4, lowOnce in 5 yearsNOC now from 24 m for fresh Provisional applications
Lodging and rooming houses TSDRFS circular 2016Above 18 mR4, lowOnce in 5 yearsNone: the circular names residential apartment buildings only
Educational TSDRFS circular 2016Above 6 m or above 500 m²R1, higherBi-annualNone
Assembly (D-1 to D-5) TSDRFS circular 2016Above 6 m or above 500 m²R1, higherBi-annualNone
Institutional (hospitals, sanatoria, nursing homes) TSDRFS circular 2016Above 15 mR2, highAnnualFire tower and FCC now from 24 m
Mercantile (incl. underground shopping) TSDRFS circular 2016Above 15 mR2, highAnnualFire tower and FCC now from 24 m
Business TSDRFS circular 2016Above 15 mR3, mediumTwice in 5 yearsFire tower and FCC now from 24 m
Industries (low hazard) TSDRFS circular 2016Above 15 mR3, mediumTwice in 5 yearsFire tower and FCC now from 24 m
Storage TSDRFS circular 2016Above 15 mR3, mediumTwice in 5 yearsFire tower and FCC now from 24 m
Hazardous TSDRFS circular 2016Above 15 mR3, mediumTwice in 5 yearsFire tower and FCC now from 24 m

Hotels sit in R3 with business buildings. Buildings covered by G.O.Ms.No.154 (built before the 1999 Act, or built without a fire NOC after it) are always treated as R1. Source: Circular Memorandum Rc.No.4039-2/EODB/2015 of 5 March 2016, para 9.

Does your Telangana building need a fire NOC? Find your line

Section 13 of the Fire Service Act, 1999 and the October 2026 circular decide it. Pick the line that fits your building.

  1. If A residential apartment building of 24 m or more, or any height filed before 7 October 2026 at 18 m or more

    You need a Provisional NOC before plan approval and an Occupancy NOC before use. TGFD circular 3455

  2. If A residential apartment building below 24 m, with a fresh Provisional application on or after 7 October 2026

    The circular no longer requires a Provisional fire NOC. Your plans still go to the sanctioning authority under the building rules. TGFD circular 3455

  3. If A commercial or business building of more than 15 m

    A fire NOC is required, exactly as before October 2026. Only the fire tower and Fire Command Centre trigger moved to 24 m. TSDRFS circular 2016

  4. If A school, cinema hall, function hall or place of worship 6 m or taller, or on a plot above 500 m²

    A fire NOC is required. The 24 m change does not touch public congregation buildings. TSDRFS circular 2016

  5. If An existing school, of any size

    The 2016 circular records the Supreme Court's direction that every school gets a fire safety inspection and a NOC as a condition for running. TSDRFS circular 2016

  6. If A pandal or temporary structure

    Apply through the separate Temporary Structures and Pandals NOC module on the department site. TGFD website

Five Hyderabad buildings under the 2026 Telangana rules

Worked examples by Flamekite from the circular's text. Heights are measured as your sanctioning authority measures them.

  1. Case 1

    21 m apartment block, filed 15 October 2026

    Residential apartments, stilt plus 6 floors, fresh Provisional NOC application in Hyderabad.

    What applies Below 24 m and filed after 7 October 2026, so the circular no longer requires a Provisional fire NOC, a fire tower or an FCC room. TGFD circular 3455

  2. Case 2

    The same block, filed 30 September 2026

    Identical drawings, but the Provisional NOC application reached the department before 7 October 2026.

    What applies The circular applies only to applications received on or after 7 October 2026, so the earlier 18 m requirement governs this file. TGFD circular 3455

  3. Case 3

    20 m office building

    Business occupancy in the Financial District, 20 m tall.

    What applies Still needs a fire NOC (business above 15 m). Under the circular it no longer needs a fire tower or FCC room, which now start at 24 m. TGFD circular 3455

  4. Case 4

    30 m residential tower

    Residential apartments, 30 m, with a DG set in the basement.

    What applies Needs Provisional and Occupancy NOCs, a fire tower and an FCC room. The DG room may use louvres above a 1 m, 2-hour fire-rated wall. TGFD circular 3455

  5. Case 5

    7 m function hall on a 600 m² plot

    Assembly use, ground plus one floor.

    What applies Needs a fire NOC under section 13 (6 m and above, plot above 500 m²) and falls in risk category R1. TSDRFS circular 2016

Telangana's 24 m rule: five misreadings to avoid

Two news reports read the October 2026 change far wider than the circular does. These are the errors that cost builders an approval.

  • If "No building under 24 m needs a fire NOC in Telangana"

    Wrong. Deccan Chronicle and Legal Suvidha reported a general exemption; the circular's table limits the change to residential apartment buildings and says no change for other occupancy types. Deccan Chroniclenews report

  • If Treating a 16 to 23 m office block as exempt

    Commercial buildings above 15 m still need a NOC, and the circular leaves every non-residential NOC trigger as it was. Only the fire tower and FCC room trigger moved to 24 m. TGFD circular 3455

  • If Assuming files lodged before 7 October 2026 benefit

    The circular applies only to fresh Provisional NOC applications received on or after that date. TGFD circular 3455

  • If Reading 24 m as Telangana adopting NBCS 2026

    It is a state circular tied to G.O.Ms.No.95. BIS withdrew NBC 2016 on 30 April 2026 and replaced it with NBCS 2026, but Flamekite found no Telangana circular adopting NBCS 2026 as of 24 October 2026. Gazette of India

  • If Citing a G.O. number for the 24 m change

    There is none: the instrument is Circular Memorandum Rc.No.3455/MSB/2026. G.O.Ms.No.95 is the MA&UD building-rules order it responds to. TGFD circular 3455

Telangana fire NOC fees and inspection charges

The fire precaution fee is Rs 10 per m² of total built-up area. Inspection user charges come on top, set by G.O.Ms.No.71 of 1 April 2010 and tabled in the 2016 circular.

As published

  • Fire precaution feeRs 10 per m²Of total built-up area; G.O.Ms.No.142, Home (Ser.IV), 9 August 2016, amending the Levy of Fee Rules, 2006 G.O.Ms.No.142
  • Second and later inspections on revised drawings5% of statutory fee, max Rs 25,000Each occasion the applicant asks for one TSDRFS circular 2016
  • Inspection for a revised NOC10% of statutory fee, max Rs 50,000 TSDRFS circular 2016
  • Inspection for the Occupancy certificateA share of statutory fee, max Rs 50,000The percentage is cut off in the department's scan; ask the office TSDRFS circular 2016
  • Inspection for renewal of NOCRs 10,000 TSDRFS circular 2016
  • Inspection of fire safety measuresRs 10,000 TSDRFS circular 2016
  • Inspection on a complaintRs 2,500 TSDRFS circular 2016
  • Mock drill in a multi-storeyed or hazardous buildingRs 5,000Government buildings excepted TSDRFS circular 2016

Flamekite's arithmetic, not a department quote: a 12,000 m² built-up area pays 12,000 x Rs 10 = Rs 1,20,000 as fire precaution fee. The department does not publish a separate Provisional versus Occupancy fee table online; the portal shows the amount due before payment.

Telangana fire NOC timelines and figures

The official timeline is 7 or 14 days. The Act itself allows the Director General up to 60 days.

  • 7 days

    Department timeline for a NOC on a building up to 15 m TGFD Fire NOC note

  • 14 days

    Department timeline for a NOC on a building above 15 m TGFD Fire NOC note

  • 60 days

    Outer limit in section 13(b) of the Fire Service Act, 1999 to issue or reject TSDRFS circular 2016

  • 24 m

    New residential apartment trigger, and the new fire tower and FCC trigger for all occupancies TGFD circular 3455

  • 6 months

    Audit cycle for residential from 45 m, malls, hospitals above 15 m, and hotels, business and mercantile above 30 m; others upload yearly in January TG fire circular 2020

  • 29

    Station-officer entries tagged to Hyderabad district on the department's list TGFD station officers

Telangana fire NOC validity: 5 years or every year?

The department's own documents disagree: 5 years or 1 year. A 2016 circular fixes renewal every 5 years; its FAQ and Citizen Charter still say every year. Flamekite shows both because neither has been withdrawn.

Circular Memorandum Rc.No.4039-2/EODB/2015 of 5 March 2016 records that builders asked for the renewal period to rise from 1 year to 5 years to ease the cost of annual renewal for multi-storeyed buildings. Para 8 then fixes 5 years for renewals of NOC for every occupancy under section 13 that holds an Occupancy NOC, backed by risk-based random inspections.

The department's FAQ page and Citizen Charter Handbook, both still live on 24 October 2026, say renewal is mandatory every year and is issued within 14 days. The Circulars page lists a second entry for the 2016 revision dated 3 June 2016, but its file is the same 5 March circular.

A 2024 circular, Rc.No.15009/MSB/CR/RR/2013 of 1 July 2024, lists Renewal of NOC as a dashboard service with Public Service Delivery Guarantee timelines but states no period. Flamekite found no later order that settles the point.

What to do: read the validity printed on your issued Occupancy NOC or renewal, and diarise renewal from that date. If the certificate is silent, ask the District Fire Officer in writing which period applies. The renewal inspection charge is Rs 10,000 either way.

The two official positions on renewal
WhatThe ruleSource
Circular of 5 March 2016Every 5 years, for occupancies holding an Occupancy NOCTSDRFS circular 2016
Department FAQEvery yearTGFD FAQ
Citizen Charter HandbookEvery year; renewal issued in 14 daysTGFD Citizen Charter

Telangana fire NOC online: the official portals

Every Telangana fire NOC is filed online. These are the official addresses, with what each one does.

How a Telangana fire NOC file moves inside the department

The department's procedure note sets out 5 stops between your upload and the certificate, with an SMS at each.

  1. 1. Online application

    You file on fire.telangana.gov.in and pay; the file lands on the Director General's dashboard. TGFD procedure

  2. 2. Committee assigned

    The Director General assigns the file to a committee of officers. For risk-based inspections, the 2016 circular has the computer name the officers: one from the local jurisdiction and one at random. TSDRFS circular 2016

  3. 3. Inspection and report

    The committee inspects and uploads its report. A flash news item says Provisional NOC applications no longer need a site inspection or site photos, so expect the visit at the Occupancy stage. TGFD website

  4. 4. Regional Fire Officer

    The Regional Fire Officer scrutinises the report and forwards it. TGFD procedure

  5. 5. Director General decides

    Approval or rejection. An approved certificate is e-mailed to you and can also be downloaded from the portal. TGFD procedure

Documents and plan certifications for a Telangana fire NOC

The department's procedure note lists the drawings; two plan-sheet certifications catch most high-rise files.

  • Site plan, basement plans and stilt or ground floor plan TGFD procedure
  • Every floor plan, the terrace plan, sections and elevations TGFD procedure
  • All fire protection systems marked in red on the drawings TGFD procedure
  • For a high-rise with setback concessions: the note "Minimum setback area clear without any Obstructions" on the site plan, with at least 7 m clear all round TGFD procedure
  • Where a 2 m green strip is proposed: a certificate that it is soft planting that lets fire vehicles move TGFD procedure
  • For the Occupancy NOC: a copy of the Provisional NOC TGFD procedure
  • For a residential apartment filed on or after 7 October 2026: the measured height, to show whether the 24 m trigger applies TGFD circular 3455

Passing the Telangana Occupancy NOC inspection

The department publishes what its officers check. Use it as your pre-inspection list.

Do

  • Keep entry gates at least 4.5 m wide with 5 m of head clearance for fire engines. TGFD Fire NOC note
  • Run a working test of every fire system: inspectors do a functional test, not a paper check. TGFD Fire NOC note
  • Have smoke management, air-conditioning fire safety, emergency lighting and exit signage working on the day. TGFD Fire NOC note
  • Show an evacuation plan and occupants who know it. TGFD Fire NOC note

Don’t

  • Don't let parking or structures fill the setbacks: open spaces and means of escape are inspected, and high-rise site plans certify 7 m clear all round. TGFD procedure
  • Don't deviate from the approved fire drawings; sections 31 and 32 of the 1999 Act reach the builder, architect and site engineer. TGFD procedure
  • Don't forget overhead HT lines and road width: they are the 2 items officers check at the Provisional stage. TGFD Fire NOC note

Fire NOC in Hyderabad: TGFD, GHMC, BuildNow and HYDRAA

Hyderabad has no municipal fire brigade. The state department issues every fire NOC in the city; four other bodies touch the process.

  • Issues the NOC

    TGFD

    Provisional, Occupancy and Renewal NOCs in Hyderabad come from the state department, with two District Fire Officers for Hyderabad district. TGFD district officers

  • Plan sanction

    GHMC on BuildNow

    GHMC building permissions moved to BuildNow; TG-bPASS stopped accepting GHMC applications from 3 April 2025. GHMC

  • Existing bars

    GHMC Fire Prevention Wing

    A GHMC form for existing pubs, bars and restaurants asks for a Rs 10,000 inspection charge by challan at the GHMC head office. The form dates from about 2018; whether it is still used is not confirmed. GHMC form

  • Disaster response

    HYDRAA

    HYDRAA's own site lists a Disaster Management Wing for fire hazards and rescue, and no NOC role. HYDRAA

  • Unconfirmed

    A HYDRAA NOC portal?

    A July 2026 Siasat headline reports a HYDRAA portal for online fire NOC applications. Flamekite could not confirm its scope on any official page, so file building NOCs with TGFD. The Siasat Dailynews report

Telangana fire NOC terms, from Provisional to Occupancy NOC

The words on Telangana's portal and circulars, defined from the department's own documents.

Provisional NOC
The plan-stage NOC under section 13, needed before the sanctioning authority approves building plans. The 2026 circular applies to fresh Provisional applications only. TGFD circular 3455
Occupancy NOC
The final NOC after construction, issued after inspection; Rule 15 of the Levy of Fee Rules, 2006 requires it for high-rise buildings. TSDRFS circular 2016
Renewal of NOC
The periodic renewal for buildings holding an Occupancy NOC; its period is in conflict between official sources (5 years or 1 year). TSDRFS circular 2016
MSB
Multi-storeyed building. The 2016 circular draws random inspection lists of MSBs, and the 2026 circular carries the MSB file number Rc.No.3455/MSB/2026. TGFD circular 3455
Fire tower
A requirement in the circular's table: above 15 m until 6 October 2026, and at 24 m and above in all occupancies from 7 October 2026. TGFD circular 3455
Fire Command Centre (FCC)
A dedicated FCC room, moved by the same circular from buildings above 15 m to buildings of 24 m and above, in every occupancy. TGFD circular 3455
PSDG
Public Service Delivery Guarantee: the law whose timelines the department's 2024 online dashboard reports for each NOC service. TGFD circulars
Risk category R1 to R4
The 2016 grading of buildings that sets random inspections, from bi-annual (R1) to once in 5 years (R4). TSDRFS circular 2016

How Telangana's fire NOC rules changed, 1999 to 2026

Telangana's regime is a 1999 Act carried over from Andhra Pradesh, reshaped by circulars and orders.

  1. 1999

    The Fire Service Act, 1999 (enacted as the Andhra Pradesh Fire Service Act) makes section 13 the NOC provision; Telangana carries it over. TSDRFS circular 2016

  2. 2006

    The Fire and Emergency Operations and Levy of Fee Rules, 2006 set fees, the high-rise Occupancy NOC (Rule 15) and licence renewal (Rule 21). TSDRFS circular 2016

  3. 1 April 2010

    G.O.Ms.No.71 introduces user charges for inspections, including Rs 10,000 for a renewal inspection. TSDRFS circular 2016

  4. 5 March 2016

    Renewal moves from 1 year to 5 years for occupancy-NOC holders, with R1 to R4 random inspections. TSDRFS circular 2016

  5. 9 August 2016

    G.O.Ms.No.142 sets the fire precaution fee at Rs 10 per m² of built-up area. G.O.Ms.No.142

  6. 1 July 2024

    An Ease of Doing Business circular puts Provisional, Occupancy and Renewal NOCs on a live online dashboard. TGFD circulars

  7. 20 January 2026

    G.O.Ms.No.15 empanels third-party fire and life safety auditors and system integrators, superseding G.O.Ms.No.44 of 2023. G.O.Ms.No.15

  8. 21 March 2026

    G.O.Ms.No.95 of the MA&UD Department amends building regulations, which builders' associations then contest. TGFD circular 3455

  9. 26 September 2026

    The Director General signs Rc.No.3455/MSB/2026 after meeting CREDAI, NAREDCO and the Telangana Builders Federation on 23 September. TGFD circular 3455

  10. 7 October 2026

    The 24 m residential apartment trigger and the 24 m fire tower and FCC triggers take effect. TGFD circular 3455

Telangana fire NOC news in 2026

From news reports, not yet an official source.

Draft amendments to the Fire Services Act, 1999 were open for comment until 13 May 2026; Flamekite found no enacted amendment by 24 October 2026.

  • Legal Suvidha reports the 24 m change as an exemption for any building under 24 m. The circular does not say that; the site itself notes it may carry AI-generated content. Legal Suvidhanews report

  • PTI, via Siasat, reports the residential-only change and quotes no change for other occupancy types, matching the circular. The Siasat Dailynews report

  • OneIndia reports the new residential height limit, also residential-only. OneIndianews report

  • Deccan Chronicle reports fire NOCs are no longer needed for any building under 24 m and a 21 m high-rise definition; both conflict with the circular's text. Deccan Chroniclenews report

  • The department invites section-wise suggestions on draft amendments to the Fire Services Act, 1999 by e-mail or post, closing 13 May 2026. TGFD press note

Telangana fire NOC penalties under the 1999 Act

The department names the sections it prosecutes under, and its own copy of the 1999 Act sets the amounts.

OffencePenaltyLaw
Wilfully contravening the Act or rules, or ignoring a lawful requisitionUp to 3 months or a fine up to Rs 25,000, or both; up to Rs 3,000 a day if it continues after conviction; at least 1 month and Rs 5,000 absent special reasonsSection 31, Fire Service Act, 1999 TG Fire Service Act
Building in deviation from approved fire drawingsProsecution of the builder, architect and site engineerSections 31 and 32, Fire Service Act, 1999 TGFD procedure
Violating the conditions of a no objection certificateLiable to be proceeded against under the ActSection 13(d), Fire Service Act, 1999 TSDRFS circular 2016
Plan sanction without a required NOCThe approving authority may not grant approvalSection 13(c), Fire Service Act, 1999 TSDRFS circular 2016

Amounts from the department's own copy of the 1999 Act, read from page 12 on 25 October 2026. Section 30 adds up to 3 months or Rs 5,000 for failing to take out a licence after a show-cause notice.

Telangana fire department and Hyderabad fire offices

Official numbers as published by the department on 24 October 2026. In an emergency, dial 101 or 112.

Questions about Telangana

How do I apply for a fire NOC in Telangana?

Online, on the Building NOC login at fire.telangana.gov.in. Upload the drawings with fire systems marked in red and pay the fee. Apply for the Provisional NOC before plan sanction and the Occupancy NOC after construction. The certificate is e-mailed and can be downloaded.

What is the 24 metre rule in Telangana?

Circular Rc.No.3455/MSB/2026 of 26 September 2026 requires a Provisional fire NOC for residential apartment buildings only at 24 m and above, up from 18 m. It applies to fresh applications received on or after 7 October 2026. Other occupancies keep their thresholds.

Do commercial buildings under 24 m still need a fire NOC in Telangana?

Yes, if they are taller than 15 m. The circular changed only the residential apartment trigger. For commercial buildings it moved the fire tower and Fire Command Centre requirement from above 15 m to 24 m.

How long is a fire NOC valid in Telangana?

The official sources conflict. A circular of 5 March 2016 fixes renewal every 5 years for buildings with an Occupancy NOC. The department FAQ and Citizen Charter still say every year. Follow the validity printed on your certificate.

What is the fire NOC fee in Telangana?

The fire precaution fee is Rs 10 per m² of total built-up area under G.O.Ms.No.142 of 2016. Inspection charges are extra, for example Rs 10,000 for a renewal inspection.

How long does a Telangana fire NOC take?

The department's timeline is 7 days for buildings up to 15 m and 14 days above 15 m. Section 13 of the Act allows up to 60 days.

Who issues a fire NOC in Hyderabad?

The state department (TGFD), not GHMC. GHMC handles building permission through BuildNow, and HYDRAA's site shows no NOC role.

What is the difference between a Provisional and an Occupancy fire NOC in Telangana?

The Provisional NOC clears the drawings before plan approval. The Occupancy NOC follows an inspection of the finished building and is needed before it is used.

Keep reading

Sources

Each source was opened and read on the date shown. How Flamekite checks its sources

  1. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Circular Memorandum Rc.No.3455/MSB/2026, 26 September 2026: revised requirements for Fire NOCs in the context of G.O.Ms.No.95 (in force 7 October 2026) (opens in a new tab)checked 25 October 2026
  2. Telangana State Disaster Response and Fire Services Department: Circular Memorandum Rc.No.4039-2/EODB/2015, 5 March 2016: revision of the period of renewal of NOC, risk categories and random inspections (quotes section 13 of the Fire Service Act, 1999) (opens in a new tab)checked 25 October 2026
  3. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Frequently asked questions (fire NOC and renewal) (opens in a new tab)checked 24 October 2026
  4. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Citizen Charter Handbook (opens in a new tab)checked 24 October 2026
  5. Government of Telangana, Home (Ser.IV) Department: G.O.Ms.No.142, Home (Ser.IV), 9 August 2016: fire precaution fee amending the Levy of Fee Rules, 2006 (opens in a new tab)checked 24 October 2026
  6. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Fire NOC: timelines and inspection checklist (FireNOC.pdf) (opens in a new tab)checked 24 October 2026
Show all 29 sourcesShow fewer
  1. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Procedure and documents required for Fire NOC (opens in a new tab)checked 24 October 2026
  2. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Online Building NOC login (Provisional and Occupancy NOC) (opens in a new tab)checked 24 October 2026
  3. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Circulars (includes Rc.No.15009/MSB/CR/RR/2013 of 1 July 2024 on the online dashboard for Provisional, Occupancy and Renewal NOCs) (opens in a new tab)checked 24 October 2026
  4. Greater Hyderabad Municipal Corporation: GHMC home page notice: building permissions on BuildNow; TG-bPASS stopped accepting GHMC applications from 3 April 2025 (opens in a new tab)checked 24 October 2026
  5. Hyderabad Disaster Response and Asset Protection Agency (HYDRAA): HYDRAA home page: Disaster Management Wing (fire hazards, rescue, DRF deployment) (opens in a new tab)checked 24 October 2026
  6. Gazette of India (Bureau of Indian Standards notification): Gazette of India Extraordinary, Part III Sec 4, No. 299, 30 April 2026: SP 7:2026 established, SP 7:2016 withdrawn (Ref HQ-PUB013/1/2020-PUB-BIS (1529)) (opens in a new tab)checked 25 October 2026
  7. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Department home page: online services (Building NOC, Fire Audit, temporary structures) and flash news (opens in a new tab)checked 24 October 2026
  8. Director General, Telangana State Disaster Response and Fire Services: Circular Memorandum Rc.No.6402/MSB/2019, 28 January 2020: conducting of fire audit in all high-rise and non-high-rise buildings; third-party certificate uploaded every January, or every January and July, by height and use, with the 13-point certificate format (read from the page images) (opens in a new tab)checked 25 October 2026
  9. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Station Fire Officers list (29 entries tagged Hyderabad district) (opens in a new tab)checked 24 October 2026
  10. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Fire Audit module login (opens in a new tab)checked 25 October 2026
  11. Telangana fire DCR auto-scrutiny portal (linked from fire.telangana.gov.in): DCR portal for fire: auto-scrutiny of provisional NOC drawings (opens in a new tab)checked 24 October 2026
  12. Government of Telangana: TG-bPASS: building permission approval and self-certification system (opens in a new tab)checked 24 October 2026
  13. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: District Fire Officers: names, phones and e-mail (opens in a new tab)checked 24 October 2026
  14. Greater Hyderabad Municipal Corporation, Town Planning: Application form of existing assembly buildings (pubs, bars and restaurants) for fire safety inspections (file 371684/2018/DFO(HO)) (opens in a new tab)checked 24 October 2026
  15. Government of Telangana, Home (Services.IV) Department: G.O.Ms.No.15, 20 January 2026: empanelment of Third-Party Fire and Life Safety Auditors and Fire and Life Safety System Integrators (opens in a new tab)checked 25 October 2026
  16. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Press note, 13 April 2026: draft amendments to the Fire Services Act, 1999 placed for suggestions until 13 May 2026 (opens in a new tab)checked 24 October 2026
  17. Telangana Fire, Disaster Response, Emergency and Civil Defence Department (the department's copy of the Act and the 2006 Rules): Telangana Fire Service Act, 1999 (adapted by G.O.Ms.No.75, Home (Legal), 17 November 2015), with the Telangana Fire and Emergency Operations and Levy of Fee Rules, 2006 and Forms 16 to 20: sections 13, 19 to 22 and 27 to 33; rules 25, 26 and 28; Form 20 conditions (opens in a new tab)checked 25 October 2026
  18. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Contact us: Director General's office, control room and portal support (opens in a new tab)checked 24 October 2026
  19. The Siasat Daily (PTI): Telangana revises fire NOC guidelines for residential buildings (9 October 2026) (opens in a new tab)News report · checked 24 October 2026
  20. OneIndia: Telangana changes fire NOC rules for residential buildings: check new height limit (date not shown on the copy read) (opens in a new tab)News report · checked 24 October 2026
  21. Deccan Chronicle: Fire safety protocols mandatory for buildings taller than 24 mts (date not shown on the copy read) (opens in a new tab)News report · checked 24 October 2026
  22. The Siasat Daily: HYDRAA launches portal for online fire NOC applications (July 2026) (opens in a new tab)News report · checked 24 October 2026
  23. Legal Suvidha: Telangana raises residential fire NOC height to 24 metres (10 October 2026) (opens in a new tab)News report · checked 24 October 2026