Fire NOC in Andhra Pradesh after the 2026 amendment: who needs one, fees, renewal and the portal

Updated By Flamekite Editorial DeskFacts checked against official sources on

Quick answer

Andhra Pradesh's amended Fire Service Act gives the department 21 days for a Provisional Fire NOC and 30 days for the final Fire Safety Certificate; a circular of 1 September 2025 cuts that to 3 working days and 10 working days. The fee is Rs 10 per m² of built-up area plus a bank guarantee of 15% of the fire-system cost for 5 years.

Since 1 December 2025 the Provisional Fire NOC covers every high-rise building (24 m or more, stilt included), every educational, institutional, assembly, industrial and hazardous building, and other occupancies with more than 500 m² on a floor or large basements. You apply online at fireservices.ap.gov.in; industries file through the Single Desk Portal. Renewal runs 1 to 5 years by occupancy.

High-rise line
24 m
Stilt floor included, since 19 December 2025
Who needs one
Provisional NOC, by circular
3 working days
21 days in the Act
File route
Fire precaution fee
Rs 10 per m²
Plus a 15% bank guarantee
Fee table
Low hazard industry renewal
5 years
Was 2 years until December 2025
Renewal table

Andhra Pradesh fire NOC at a glance

The Andhra Pradesh fire NOC in eleven rows, each with its official source.
WhatThe ruleSource
LawAP Fire Service Act, 1999 (Act 15 of 1999), section 13, as amended with effect from 1 December 2025; the AP Fire and Emergency Operations and Levy of Fee Rules, 2006Andhra Pradesh Legislative Assembly
Status of the 2026 amendmentOrdinance 9 of 2025 from 1 December 2025, replaced by Bill 12 of 2026; reported enacted as Act 15 of 2026 on 2 April 2026, with no official Act copy onlineTeamLease RegTechnews report
Issued byAP State Disaster Response and Fire Services Department (APSDR&FS), head office at Governorpet, VijayawadaAP Fire Services
StagesProvisional Fire NOC before building permission; Fire Safety Certificate (the former occupancy NOC) after construction; renewalAndhra Pradesh Legislative Assembly
High-rise building24 m or more, stilt floor included, under the AP Building Rules as amended by G.O.Ms.No.273 of 19 December 2025G.O.Ms.No.273
Time limits in the Act21 days for the Provisional Fire NOC; 30 days for the Fire Safety CertificateAndhra Pradesh Legislative Assembly
Time limits by circular3 working days for a Provisional NOC (no site inspection); 10 working days for occupancy or renewalAP circular 01.09.2025
FeeRs 10 per m² of total built-up area, basements and stilt included, plus a 15% bank guarantee for 5 yearsAP State Disaster Response and Fire Services
RenewalOccupancy NOC valid 1 year; renewals 1 to 5 years by occupancy under G.O.Ms.No.218 (2023) and G.O.Ms.No.178 (2025)G.O.Ms.No.218
Apply atfireservices.ap.gov.in (Citizen Login); industries through the AP Single Desk PortalAP circular 01.09.2025
EmergencyDial 101; state fire control room 9100108101AP Fire Services

Andhra Pradesh fire law before and after the 2026 amendment

Section 13 and the penalty sections of the AP Fire Service Act, 1999, as amended in 2006 and as amended with effect from 1 December 2025.
Option1999 Act as amended in 2006From 1 December 2025 (Ordinance 9 of 2025, then Bill 12 of 2026)Source
Final approvalFinal No Objection Certificate; licences for fire-risk premisesFire Safety Certificate; the word licence is replaced throughoutAndhra Pradesh Legislative Assembly
High-rise definition18 m, in the Act itselfWhatever the AP Building Rules say: 24 m including stilt since 19 December 2025Andhra Pradesh Legislative Assembly
Who needs a NOCCommercial above 15 m; residential 18 m and above; schools, cinemas, function halls and religious places above 500 m² of plot or 6 m and aboveAll high-rises; all educational, institutional, assembly, industrial and hazardous buildings; others with more than 500 m² on a floor, more than 300 m² of incidental assembly, or 2 basements or 1 above 500 m²Andhra Pradesh Legislative Assembly
Time to decide60 days to issue or reject21 days for the Provisional NOC; 30 days for the Fire Safety CertificateAP Act 15 of 1999
RenewalLicence renewed each calendar year under the 2006 RulesRenewed periodically as the government notifies, with a prescribed feeAndhra Pradesh Legislative Assembly
Who may install fire systemsNot restricted in the ActOnly Qualified agencies specified by rules; a false certificate means cancellation and prosecutionAndhra Pradesh Legislative Assembly
Building Fire Safety SupervisorNo such postSection 21-A: owners of buildings named by government order must appoint oneAndhra Pradesh Legislative Assembly
Fines in sections 27, 28 and 29Up to Rs 500Up to Rs 10,000Andhra Pradesh Legislative Assembly
Minimum daily fine, section 31Rs 100 a dayRs 1,000 a dayAndhra Pradesh Legislative Assembly

How to get a fire NOC in Andhra Pradesh, from plans to renewal

  1. Classify the building against section 13(1)

    Measure height from the average level of the street's centre line with the stilt floor included, and check occupancy, the largest floor area, any incidental assembly use and the basements.

  2. Register on the department portal

    Create a Citizen Login on fireservices.ap.gov.in with name, e-mail and mobile; the password comes by SMS. Industries file the same NOC through the AP Single Desk Portal.

  3. Apply for the Provisional Fire NOC

    Upload drawings with every fire system marked in red, the fire-system estimate, the Rs 10 per m² fee, a bank guarantee of 15% of that estimate for 5 years and an undertaking on Rs 100 stamp paper. The circular target is 3 working days, without a site visit.

  4. Build, in two permits if the building is a high-rise

    A high-rise may take building permission up to 24 m first and file the Fire NOC before crossing 24 m; the remaining floors are approved once it is submitted.

  5. Apply for the Fire Safety Certificate before occupation

    File the as-built details and upload photos and short videos of every system being tested. Inspection takes 5 working days and issue 5 more; no occupancy certificate may be granted without it.

  6. Renew on time, and file the yearly compliance report

    Renew after the first year at the period your occupancy carries (1 to 5 years), applying 2 months before expiry, and upload the annual fire safety compliance report on the portal.

What the AP Fire Service (Amendment) Act 2026 says about renewal

The amendment rewrote section 13 but left the renewal period to a later notification. Its renewal clause is one sentence.

Word for word

The Fire Safety Certificate issued under sub-section (3) shall be renewed periodically as notified by the government along with such fee as may be prescribed from time to time.

Section 13(4), AP Fire Service Act, 1999, as substituted by L.A. Bill No. 12 of 2026 (AP Gazette Part IV-A Extraordinary No. 12, 4 March 2026), deemed in force from 1 December 2025 Andhra Pradesh Legislative Assembly

Four pieces the amendment needs were not published by 24 October 2026: a renewal notification under section 13(4), new fee rules for section 13, rules naming Qualified agencies under section 19(3), and the order listing buildings that need a Building Fire Safety Supervisor under section 21-A. Until they appear, the department keeps working from the 2006 Levy of Fee Rules and its periodicity orders of 2023 and 2025, both issued before the amendment and still worded as Fire NOCs. The Bill's memorandum lists clauses 2(iv), 5, 7(3), 8 and 14 as needing notifications.

Does your Andhra Pradesh building need a Provisional Fire NOC?

New section 13(1) lists six cases. If none fits, the section does not ask for a Provisional Fire NOC; your plans still go to the sanctioning authority.

  1. If Any building 24 m or taller, measured with the stilt floor

    It is a high-rise under the AP Building Rules and needs a Provisional Fire NOC. You may take building permission up to 24 m first and file the NOC before crossing that height. G.O.Ms.No.273

  2. If A school, college, hospital, auditorium, factory or hazardous building, of any size

    Clause (b) covers all educational, institutional, assembly, industrial and hazardous buildings. The old 500 m² plot or 6 m floor that a 2018 MA&UD circular still quotes is not in the 2026 text. Andhra Pradesh Legislative Assembly

  3. If A shop, office, warehouse, hostel, lodge or mixed building with more than 500 m² on any one floor

    Clause (c) catches it. Residential apartment buildings are left out of this clause by name. Andhra Pradesh Legislative Assembly

  4. If More than 300 m² of assembly use on one floor, such as a banquet hall or food court inside another occupancy

    Clause (d) catches it, whatever the rest of the building is. Andhra Pradesh Legislative Assembly

  5. If Two or more basements, or one basement above 500 m²

    Clause (e) catches every occupancy, apartments included. Andhra Pradesh Legislative Assembly

  6. If A residential apartment block under 24 m with none of the above

    Section 13(1) does not list it (Flamekite's reading). A 2018 MA&UD circular asked for a Fire NOC above 18 m when high-rise meant 18 m; ask the District Fire Officer in writing which applies to your file. MA&UD circular 2018

Andhra Pradesh fire NOC renewal periods by occupancy

G.O.Ms.No.218 of 22 December 2023 set the table; G.O.Ms.No.178 of 17 December 2025 lengthened four rows. The first occupancy NOC is always for 1 year.

G.O.Ms.No.218 (2023)G.O.Ms.No.178 (2025)Period now
Occupancy NOC, first issue G.O.Ms.No.2181 yearNot changed1 year
Residential, 18 m and above, other than hotels G.O.Ms.No.2183 yearsNot changed3 years
Educational, below 30 m G.O.Ms.No.1783 years5 years5 years
Other non-residential below 18 m, hotels included G.O.Ms.No.2182 yearsNot changed2 years
Low hazard industry G.O.Ms.No.1782 years5 years5 years
Moderate hazard industry G.O.Ms.No.1782 years3 years3 years
High hazard industry G.O.Ms.No.1781 year2 years2 years
Hazardous buildings other than industry G.O.Ms.No.2181 yearNot changed1 year
Any other building 18 m and above G.O.Ms.No.2182 yearsNot changed2 years

The last column is Flamekite's reading of the two orders together: G.O.Ms.No.178 revises only the rows it names. Under G.O.Ms.No.178 an owner may choose fewer years, paying for that many annual fee cycles. Neither order is the section 13(4) notification the 2026 amendment asks for.

Andhra Pradesh fire NOC validity: how renewal works in practice

Renewal follows the department's orders, not the Act: 1 year first, then 1 to 5 years, with yearly self-reporting in between.

G.O.Ms.No.218 says the occupancy NOC is issued for one year and renewal follows after that year. The government gave its reason in the order: field officers found owners moving fire equipment from one building to another during inspections, because validity was long and many NOCs rested on the owner's own certification.

The user charges for a renewal are collected for the whole renewal period at once, and the owner must file a declaration every year that the fire systems are maintained. G.O.Ms.No.178 adds an Annual Fire Safety Compliance Report on the portal and random inspections.

NOCs issued before 22 December 2023 keep the period printed on them; the new periods apply when they expire. Before that order, G.O.Ms.No.120 of 25 October 2021 had NOCs of all categories issued for 5 years; G.O.Ms.No.218 superseded it.

Apply at least 2 months before expiry: rule 21 of the 2006 Rules renews a late application only with 25% more fee. Flamekite found no notification under the amended section 13(4) by 24 October 2026, so the 2023 and 2025 orders are what the department applies.

The validity rules in force, by instrument
WhatThe ruleSource
G.O.Ms.No.218, 22 December 2023Occupancy NOC 1 year; renewal table by occupancy; annual declarationG.O.Ms.No.218
G.O.Ms.No.178, 17 December 20255, 3 and 2 years for low, moderate and high hazard industry; 5 years for schools below 30 mG.O.Ms.No.178
Levy of Fee Rules 2006, rule 21Apply 2 months before expiry, or pay 25% extraAP State Disaster Response and Fire Services
G.O.Ms.No.146, 30 December 2021Records the 5-year period then in force under G.O.Ms.No.120 of 25 October 2021G.O.Ms.No.146

Andhra Pradesh fire NOC fees, bank guarantee and inspection charges

The 2006 Rules set Rs 10 per m² and a 15% bank guarantee; G.O.s of 2010 and 2015 add inspection charges. No new fee rules under the 2026 amendment were found.

As published

A real AP figure: for AIIMS Mangalagiri the department asked Rs 9,07,695 as fire precaution fee and a bank guarantee of Rs 1,37,20,305 before the government waived both in G.O.Rt.No.452 of 17 August 2017. By Flamekite's arithmetic that is about 90,770 m² and a fire-system estimate of about Rs 9.15 crore.

Five Andhra Pradesh buildings under the 2025 and 2026 rules

Worked examples by Flamekite from the Act, the G.O.s and the delegation circular. Heights include the stilt floor.

  1. Case 1

    30 m apartment tower in Visakhapatnam

    Residential apartments, stilt plus 9 floors, built-up area 12,000 m².

    What applies A high-rise, so it needs a Provisional NOC; building permission can come up to 24 m first. Fee 12,000 x Rs 10 = Rs 1,20,000; the Director General issues; renewal every 3 years after the first year. G.O.Ms.No.273

  2. Case 2

    21 m apartment block in Vijayawada

    Residential apartments, one 400 m² basement, no assembly use.

    What applies Below 24 m, apartments are outside clause (c) and one basement under 500 m² misses clause (e): section 13(1) does not list it. Confirm in writing, because the 2018 MA&UD circular still speaks of 18 m. Andhra Pradesh Legislative Assembly

  3. Case 3

    18 m office building, 6,000 m²

    Business occupancy in Vijayawada with a Rs 50 lakh fire system.

    What applies Needs a Provisional NOC (more than 500 m² a floor). Fee Rs 60,000, bank guarantee Rs 7.5 lakh; renewal every 2 years, with a renewal inspection charge of 50% of the fee, Rs 30,000. G.O.Ms.No.140

  4. Case 4

    Low hazard factory near Visakhapatnam

    Industrial unit applying through the Single Desk Portal.

    What applies Provisional NOC without inspection, issued by the Director General; occupancy inspected by the District and Station Fire Officers; renewal up to 5 years, or fewer if the owner chooses and pays pro rata. G.O.Ms.No.178

  5. Case 5

    12 m private school, ground plus 3

    Educational occupancy on a 450 m² plot.

    What applies Clause (b) covers every educational building. Above 10 m and below 15 m the Regional Fire Officer issues it; renewal every 5 years (schools below 30 m). AP circular 01.09.2025

How an Andhra Pradesh fire NOC file moves, in working days

The circular of 1 September 2025 sets who inspects, who signs and how long each stage takes. It cancelled the delegation memos of 2020, 2023 and 2024.

  1. 1. Online application

    Every application goes through fireservices.ap.gov.in; manual applications are refused unless they come through a District Collector. AP circular 01.09.2025

  2. 2. Provisional NOC: desk scrutiny only

    No site inspection at this stage; scrutiny and issue within 3 working days. AP circular 01.09.2025

  3. 3. Who signs, by height

    Up to 10 m or 3 floors: District Disaster Response and Fire Officer. Above 10 m and below 15 m: Regional Fire Officer. 15 m or 6 floors and above, and all industries: Director General. AP circular 01.09.2025

  4. 4. Occupancy or renewal inspection

    Station or Assistant District Fire Officers inspect, joined by the District and Regional officers for taller and higher-hazard buildings: 5 working days to inspect, 5 to issue. AP circular 01.09.2025

  5. 5. Evidence on the portal

    Photos and short videos of every fire system being tested are uploaded to the file's workflow page. AP circular 01.09.2025

  6. 6. Random audit

    The next level up re-checks at least 10% of NOCs issued or rejected below it. AP circular 01.09.2025

Fire NOC in Vijayawada and Visakhapatnam: who does what

Neither city has its own fire brigade: the state department issues every fire NOC. Five bodies touch a city file.

  • Issues the NOC

    APSDR&FS head office, Vijayawada

    The Director General's office at Governorpet signs NOCs for buildings of 15 m and above and for all industries. AP Fire Services

  • Vijayawada region

    Regional Fire Officer, Rajamahendravaram

    Region II covers Krishna and NTR districts, so Vijayawada files between 10 and 15 m are signed at Rajamahendravaram. AP Fire Services

  • Visakhapatnam region

    Regional Fire Officer, Visakhapatnam

    Region I covers Visakhapatnam, Anakapalli and 5 other northern districts. AP Fire Services

  • City portal

    GVMC Fire NOC registration

    GVMC's citizen site carries Provisional, Final, Renewal and Temporary Fire NOC registration screens. Whether they feed the department's system is not published. GVMC

  • Plan approval

    APDPMS

    Building permission runs on APDPMS, linked from the fire department's home page; under the Act the permit cannot issue without the Provisional NOC where one is needed. AP Fire Services

Andhra Pradesh fire NOC time limits and fire figures

The Act's limits, the circular's faster ones, and what the department's own statistics show for 2025-26.

Andhra Pradesh fire NOC online: the official portals

Mee Seva stopped taking fire NOC applications in 2017, and since 1 September 2025 manual files are refused. These are the official addresses.

Documents for an Andhra Pradesh Provisional NOC and Fire Safety Certificate

Rule 15 of the 2006 Rules lists the papers; the 2023 to 2025 orders add the evidence officers now want uploaded.

Andhra Pradesh fire NOC penalties after the 2026 amendment

The amendment multiplied the small fines by 20 and the minimum daily fine by 10. The larger ceilings in sections 30 and 31 did not change.

OffencePenaltyLaw
Failing to comply with a fire precaution notification or directionFine up to Rs 10,000 (was Rs 500)Section 27 Andhra Pradesh Legislative Assembly
Obstructing fire-fightingUp to 3 months, or up to Rs 10,000, or bothSection 28 Andhra Pradesh Legislative Assembly
A false fire reportUp to 3 months, or up to Rs 10,000, or bothSection 29 Andhra Pradesh Legislative Assembly
Not taking out a licence, now a Fire Safety Certificate, after a show-cause noticeUp to 3 months, or up to Rs 5,000, or bothSection 30 AP Act 15 of 1999
Wilfully breaking the Act or the rules, or ignoring a requisitionUp to 3 months, or up to Rs 25,000, or both; up to Rs 3,000 a day if it continues; at least Rs 5,000, or Rs 1,000 a day, unless the court records reasonsSection 31 Andhra Pradesh Legislative Assembly
A Qualified agency's false or incorrect certificateCertificate cancelled and criminal prosecutionSection 19(3) Andhra Pradesh Legislative Assembly
Building permission or occupancy certificate without the NOC or certificateThe authority may not grant itSection 13(5) Andhra Pradesh Legislative Assembly

The pre-2026 amounts were proof-read from the department's copy of the 1999 Act; the new amounts are from the Bill's text, deemed in force from 1 December 2025.

Andhra Pradesh fire NOC mistakes that cost owners time or money

Each of these traces to a line in an AP order or rule.

  • If Measuring height without the stilt floor

    G.O.Ms.No.273 counts the stilt: a stilt plus 7 floors can cross 24 m and become a high-rise. G.O.Ms.No.273

  • If Leaving basements and stilts out of the fee area

    The Rs 10 per m² is on the total built-up area of all floors, basements and stilt included. AP State Disaster Response and Fire Services

  • If Installing pumps through an unlisted contractor

    Section 19(3) reserves the work for Qualified agencies; the department invited certified installers to apply for empanelment until 31 December 2025. AP agency empanelment

  • If Borrowing equipment for the inspection day

    This is the practice G.O.Ms.No.218 names as the reason for 1-year occupancy NOCs; the yearly declaration and random checks follow. G.O.Ms.No.218

  • If Reading Telangana's 24 m rule as Andhra Pradesh's

    Telangana's change is a fire department circular for apartments; AP's comes from the Building Rules definition and the 2026 Act. See the Telangana page. G.O.Ms.No.273

Andhra Pradesh fire NOC myths checked against the orders

Common claims about AP fire NOCs, and what the department's own documents say.

  • You may have read

    "An AP fire NOC is valid for 5 years."

    Myth

    What the sources say

    Only for some occupancies. The first occupancy NOC is for 1 year; 5 years now applies to low hazard industry and schools below 30 m. G.O.Ms.No.178

  • You may have read

    "The District Fire Officer approves up to 15 m and the Director General above."

    Myth

    What the sources say

    Out of date. Since 1 September 2025 the District officer signs up to 10 m, the Regional Fire Officer from 10 to 15 m, the Director General above. AP circular 01.09.2025

  • You may have read

    "No NOC is needed for a building under 24 m."

    Myth

    What the sources say

    Every educational, institutional, assembly, industrial and hazardous building needs one, at any height. Andhra Pradesh Legislative Assembly

  • You may have read

    "The Fire Safety Certificate came with new fees."

    Myth

    What the sources say

    No fee rules under the 2026 amendment were found; the department's rules page still lists the 2006 Levy of Fee Rules (G.O.306) and its Rs 10 per m². AP Fire Services

  • You may have read

    "A NOC issued with plunger pumps in 2022 is safe."

    Myth

    What the sources say

    G.O.Ms.No.44 annulled those notifications, and the government asked the department to review 5,688 NOCs issued under them. Govt memo on PIL 97

Andhra Pradesh plunger-pump NOCs: what holders should do

Six gazettes of 2022 let NOCs issue with 2, 5 or 10 HP plunger pumps. After their annulment and a High Court PIL, the department sent notices on 2 September 2025.

Do

  • Reply within 30 days of the notice, stating whether the building meets the 1999 Act. AP Fire Services
  • If compliant, send photos of the fire equipment to ho.apfire@gmail.com. AP clarification 2025
  • If not, list what is installed and ask for time; the department said NOCs will not be cancelled without due procedure. AP clarification 2025
  • Plan for NBC fire pumps of 1,620, 2,280 or 2,850 LPM, the sizes G.O.Ms.No.44 contrasts with plunger pumps. G.O.Ms.No.44

Don’t

  • Don't use a middleman: the department's press note says no mediator is needed and gives 9441236448. AP Fire Services
  • Don't treat a 2022 NOC as settled: the government asked for each to be reviewed and, if contrary to the NBC, cancelled or amended. Govt memo on PIL 97
  • Don't ignore the notice: a revised NOC is issued only after the department considers your reply. AP Fire Services

How Andhra Pradesh's fire NOC rules changed, 1999 to 2025

Before 2014 these orders covered Hyderabad too; Telangana kept the 1999 Act and went its own way after the split.

  1. 11 June 1999

    The AP Fire Service Act, 1999 is published; section 13 gives the department 60 days to decide a NOC. AP Act 15 of 1999

  2. 1 February 2001 (effect)

    Act 21 of 2006 raises the high-rise line to 18 m and sets the 15 m, 18 m and 500 m² or 6 m triggers. AP Act 15 of 1999

  3. 7 December 2006

    G.O.Ms.No.306 makes the Levy of Fee Rules: Rs 10 per m² and the 15% bank guarantee. AP State Disaster Response and Fire Services

  4. 1 April 2010

    G.O.Ms.No.71 introduces inspection user charges. G.O.Ms.No.71

  5. 4 September 2015

    G.O.Ms.No.140 ties the renewal charge to 50% or 25% of the statutory fee. G.O.Ms.No.140

  6. 1 July 2017

    NOC applications through Mee Seva stop; the department's online system takes over. AP Fire Services

  7. 8 March 2018

    Industry Provisional NOCs are cut from 21 days to 7 working days. AP Fire Services

  8. 14 May 2019

    G.O.Ms.No.75 lets the Director General authorise third-party inspections for the Provisional NOC. G.O.Ms.No.75

  9. 9 August 2020

    Fire at Hotel Swarna Palace, Vijayawada, a COVID-19 care centre: officials were reported saying it had no NOC. Wikipedianews report

  10. January to October 2022

    Six gazette notifications allow plunger pumps and decentralised fire safety. G.O.Ms.No.44

  11. 22 December 2023

    G.O.Ms.No.218 cuts the occupancy NOC to 1 year and sets the renewal table. G.O.Ms.No.218

  12. 12 March 2024

    G.O.Ms.No.44 annuls the six 2022 notifications. G.O.Ms.No.44

  13. 1 September 2025

    New delegation: 3 working days for a Provisional NOC, 10 for occupancy or renewal. AP circular 01.09.2025

  14. 1 December 2025

    Ordinance 9 of 2025, promulgated on 28 November, rewrites section 13. AP Ordinance 9/2025

  15. 17 and 19 December 2025

    G.O.Ms.No.178 lengthens industrial and school renewals; G.O.Ms.No.273 moves the high-rise line to 24 m. G.O.Ms.No.273

Andhra Pradesh fire NOC news in 2026

From news reports, not yet an official source.

The amendment is in force from 1 December 2025 and reported enacted as Act 15 of 2026; its renewal notification, fee rules, Qualified agency rules and supervisor order were not published by 24 October 2026.

  • PTI reports G.O.Ms.No.161 amending the Building Rules: buildings of 24 m or more, stilt included, are high-rises, and construction may reach 24 m before the final Fire NOC is needed. PTInews report

  • The department extends applications for empanelment as Third-party Fire Audit Agencies for renewals to 15 July 2026, with a Rs 5,000 fee, interview and training. AP audit empanelment

  • G.O.Ms.No.95 (Industries) asks APIIC and park developers to build common fire mains, hydrants at most 60 m apart and pump houses, and lets the fire department approve units outside parks on pooled resources. G.O.Ms.No.95 (I&C)

  • A compliance tracker reports the Fire Service (Amendment) Act issued as Act 15 of 2026, deemed in force from 1 December 2025. TeamLease RegTechnews report

  • Bill 12 of 2026 is introduced in the Assembly to replace the ordinance, signed by Home Minister Anitha Vangalapudi. Andhra Pradesh Legislative Assembly

Andhra Pradesh fire NOC terms, from Provisional NOC to supervisor

The words in the amended Act and the department's orders, as they define them.

Provisional Fire NOC
The plan-stage approval under section 13(1), due in 21 days by law and 3 working days by circular. Andhra Pradesh Legislative Assembly
Fire Safety Certificate
The final certificate after construction and inspection, due in 30 days; it replaces the word licence in the Act. Andhra Pradesh Legislative Assembly
High-rise building
24 m or more including the stilt, measured from the average level of the street's centre line; lift and stair rooms excluded. G.O.Ms.No.273
Qualified agency
A person or firm with a recognised degree in fire, civil, mechanical, industrial safety, disaster management or chemical science, the only one allowed to install fire systems. Andhra Pradesh Legislative Assembly
Building Fire Safety Supervisor
The person an owner must appoint under section 21-A in buildings the government names, to keep fire systems working. Andhra Pradesh Legislative Assembly
DGFS, RFO, DDRFO, ADFO, SFO
Director General of Fire Services, Regional Fire Officer, District Disaster Response and Fire Officer, Assistant District Fire Officer, Station Fire Officer: the 5 levels that sign or inspect. AP circular 01.09.2025
SDP
The Single Desk Portal through which every industry files its fire NOC. AP circular 01.09.2025
Third-party Fire Audit Agency
An agency empanelled to audit buildings for renewal; B.E. Fire, the NFSC Divisional Officers' Course, or a science or engineering degree with department training. AP audit empanelment

Andhra Pradesh fire offices for Vijayawada and Visakhapatnam

Numbers as the department published them on 24 October 2026. In an emergency, dial 101.

Questions about fire NOC in Andhra Pradesh

How do I apply for a fire NOC in Andhra Pradesh?

Online at fireservices.ap.gov.in through a Citizen Login; industries apply through the AP Single Desk Portal. Upload drawings with fire systems in red, pay Rs 10 per m² and give a 15% bank guarantee. The department's target is 3 working days for a Provisional NOC.

Which buildings need a fire NOC in Andhra Pradesh?

Every building of 24 m or more including the stilt; every educational, institutional, assembly, industrial and hazardous building; others with more than 500 m² on a floor or 300 m² of incidental assembly; and any building with 2 basements or one above 500 m².

Is the AP Fire Service (Amendment) Act 2026 in force?

Yes, from 1 December 2025, the date of the ordinance it replaced. It is reported as Act 15 of 2026, but its renewal notification, new fee rules, Qualified agency rules and supervisor order had not been published by 24 October 2026.

How long is a fire NOC valid in Andhra Pradesh?

The first occupancy NOC is for 1 year. Renewals then run 5 years for low hazard industry and schools below 30 m, 3 years for apartments of 18 m and above and moderate hazard industry, 2 years for most others, and 1 year for hazardous buildings.

What is the fire NOC fee in Andhra Pradesh?

Rs 10 per m² of total built-up area, basements and stilt included, plus a bank guarantee of 15% of the fire-system estimate for 5 years. Government hospitals are exempt from the fee.

How long does an AP fire NOC take?

The Act allows 21 days for the Provisional NOC and 30 for the Fire Safety Certificate. The department's circular of 1 September 2025 sets 3 working days and 10 working days.

Who issues a fire NOC in Vijayawada or Visakhapatnam?

The state department, not the city corporation. The District officer signs up to 10 m, the Regional Fire Officer from 10 to 15 m, and the Director General above 15 m and for every industry.

What is a Fire Safety Supervisor in Andhra Pradesh?

A person the owner of a building named by government order must appoint under section 21-A to keep fire systems working. The order naming the buildings and the qualifications had not been published by 24 October 2026.

Keep reading

Sources

Each source was opened and read on the date shown. How Flamekite checks its sources

  1. Andhra Pradesh Legislative Assembly (PRS copy of AP Gazette Part IV-A No. 12, 4 March 2026): Andhra Pradesh Fire Service (Amendment) Bill, 2026 (L.A. Bill No. 12 of 2026): new section 13 thresholds, 21-day and 30-day timelines (opens in a new tab)checked 24 October 2026
  2. Andhra Pradesh Gazette Part IV-B Extraordinary No. 9, 1 December 2025 (PRS copy): Andhra Pradesh Fire Service (Amendment) Ordinance, 2025 (Ordinance No. 9 of 2025), promulgated 28 November 2025 (opens in a new tab)checked 24 October 2026
  3. AP State Disaster Response and Fire Services (copy of the Act with the 2006 amendment): Andhra Pradesh Fire Service Act, 1999 (Act 15 of 1999): sections 2, 13, 14 and 26 to 32 (Chapter V, penalties) (opens in a new tab)checked 24 October 2026
  4. AP State Disaster Response and Fire Services: AP Fire and Emergency Operations and Levy of Fee Rules, 2006 (G.O.Ms.306, 8 December 2006) (opens in a new tab)checked 24 October 2026
  5. Government of Andhra Pradesh, Home (Prisons and Fire) Department (copy hosted by AP Fire Services): G.O.Ms.No.218, 22 December 2023: periodicity of renewal of No Objection Certificates for non-residential and residential buildings (opens in a new tab)checked 24 October 2026
  6. Government of Andhra Pradesh, Home (Prisons and Fire) Department (copy hosted by AP Fire Services): G.O.Ms.No.178, 17 December 2025: Ease of Doing Business, revised renewal periodicity for industries and educational buildings (opens in a new tab)checked 24 October 2026
Show all 35 sourcesShow fewer
  1. Government of Andhra Pradesh, Home (Prisons and Fire) Department (copy hosted by AP Fire Services): G.O.Ms.No.146, 30 December 2021: fire precaution fee exempted for government hospital buildings (opens in a new tab)checked 24 October 2026
  2. Government of Andhra Pradesh, Health, Medical and Family Welfare (C) Department (copy hosted by AP Fire Services): G.O.Rt.No.452, 17 August 2017: fire precaution fee and bank guarantee waived for AIIMS Mangalagiri (opens in a new tab)checked 24 October 2026
  3. Government of Andhra Pradesh, MA&UD (M) Department, final notification (copy hosted by Simpliance): G.O.Ms.No.273, 19 December 2025: amendments to the AP Building Rules, 2017 (high-rise at 24 m; Fire NOC before 24 m) (opens in a new tab)checked 24 October 2026
  4. Government of Andhra Pradesh, MA&UD (M) Department (copy hosted by AP Fire Services): Circular Memo No. MAU01-28029/67/2018, 26 July 2018: NOCs by the Fire Services Department under the AP Building Rules, 2017 (opens in a new tab)checked 24 October 2026
  5. AP State Disaster Response and Fire Services: Circular Memorandum Rc.No.3350/Audit/NOC/2012, 1 September 2025: delegation of powers and time limits for Provisional, Occupancy and Renewal NOCs (opens in a new tab)checked 24 October 2026
  6. AP State Disaster Response and Fire Services: G.O.s and circulars: the department's list of 65 rules, orders and circulars (opens in a new tab)checked 24 October 2026
  7. AP State Disaster Response and Fire Services: Contact department officers: head office, Additional Directors and Regional Fire Officers (opens in a new tab)checked 24 October 2026
  8. Government of Andhra Pradesh, Home (Prisons.A) Department (copy hosted by AP Fire Services): G.O.Ms.No.71, 1 April 2010: user charges for inspections towards No Objection Certificates (opens in a new tab)checked 24 October 2026
  9. Government of Andhra Pradesh, Home (Prisons and Fire Services) Department (copy hosted by AP Fire Services): G.O.Ms.No.140, 4 September 2015: renewal inspection charge revised to 50% or 25% of the statutory fee (opens in a new tab)checked 24 October 2026
  10. Greater Visakhapatnam Municipal Corporation: GVMC citizen services: Fire NOC registration (Provisional, Final, Renewal, Temporary) (opens in a new tab)checked 24 October 2026
  11. AP State Disaster Response and Fire Services: AP Fire Services home page: Apply for Fire NOC, APDPMS link, documents (opens in a new tab)checked 24 October 2026
  12. AP State Disaster Response and Fire Services: Fire statistics: fire and emergency calls by financial year, 2006-07 to 2026-27, and fire vehicles (opens in a new tab)checked 24 October 2026
  13. AP State Disaster Response and Fire Services: GIS-based emergency service coverage and gap analysis: 182 stations, 52% coverage, 207 proposed (opens in a new tab)checked 24 October 2026
  14. AP State Disaster Response and Fire Services: User manual: Fire Safety Recommendation Report (before construction) and Fire Safety Inspection Report (after construction and renewal) (opens in a new tab)checked 24 October 2026
  15. AP State Disaster Response and Fire Services: Memorandum Rc.No.3350/MSB/2017: industry NOC applications through the AP Single Desk Portal only; Mee Seva discontinued (opens in a new tab)checked 24 October 2026
  16. AP State Disaster Response and Fire Services: Rc.No.5862/Genl/2023, 27 November 2025: empanelment of certified agencies for supply and installation of fire-fighting equipment (opens in a new tab)checked 24 October 2026
  17. Government of Andhra Pradesh, Home (Prisons and Fire) Department (copy hosted by AP Fire Services): Memo No.2439074/P&F/A2/2024, 10 February 2025: W.P.(PIL) No.97 of 2024, review of 5,688 NOCs issued under the annulled notifications (opens in a new tab)checked 24 October 2026
  18. AP State Disaster Response and Fire Services: Press note: notices to managements holding NOCs based on the 2021 and 2022 gazette notifications (opens in a new tab)checked 24 October 2026
  19. AP State Disaster Response and Fire Services: Clarification note Rc.No.1983/Legal/2024, 14 October 2025, on the notices of 2 September 2025 (opens in a new tab)checked 24 October 2026
  20. Government of Andhra Pradesh, Home (Prisons and Fire) Department (copy hosted by AP Fire Services): G.O.Ms.No.44, 12 March 2024: six 2022 gazette notifications on plunger pumps and decentralised fire safety annulled (opens in a new tab)checked 24 October 2026
  21. AP State Disaster Response and Fire Services: Letter Rc.No.3350/Audit/NOC/2012, 27 October 2017: NOC applications through Mee Seva discontinued from 1 July 2017 (opens in a new tab)checked 24 October 2026
  22. AP State Disaster Response and Fire Services: Circular Memorandum Rc.No.10951/MSB/2017, 8 March 2018: industry Provisional NOC within 7 working days instead of 21 days (opens in a new tab)checked 24 October 2026
  23. Government of Andhra Pradesh, Home (Prisons and Fire) Department (copy hosted by AP Fire Services): G.O.Ms.No.75, 14 May 2019: third party authorised to inspect for the Provisional NOC (opens in a new tab)checked 24 October 2026
  24. AP State Disaster Response and Fire Services: Rc.No.5862/Genl/2023, 29 June 2026: empanelment of Third-party Fire Audit Agencies (Qualified Agency) for renewal of Fire NOC, with the application form (opens in a new tab)checked 24 October 2026
  25. Government of Andhra Pradesh, Industries and Commerce (Prog.III) Department (copy hosted by AP Fire Services): G.O.Ms.No.95, 8 May 2026: common fire safety infrastructure in industrial parks and for units outside them (opens in a new tab)checked 25 October 2026
  26. AP State Disaster Response and Fire Services: Fire station list by district, with addresses and phone numbers (opens in a new tab)checked 24 October 2026
  27. TeamLease RegTech: Andhra Pradesh Fire Service (Amendment) Act, 2026 (Act 15 of 2026, deemed in force 1 December 2025) (opens in a new tab)News report · checked 24 October 2026
  28. Wikipedia: 2020 Vijayawada fire (Hotel Swarna Palace, 9 August 2020) (opens in a new tab)News report · checked 24 October 2026
  29. PTI via ThePrint, 29 July 2026: Andhra notifies major changes to building rules to speed up approvals (G.O.Ms.No.161) (opens in a new tab)News report · checked 24 October 2026