Fire NOC for an industry or MSME: industrial estates, single windows and MSME Acts
Updated By Flamekite Editorial DeskFacts checked against official sources on
Quick answer
MSMEs still need a fire NOC: Punjab and Haryana list it in right-to-business Acts, UP files it with the MSME declaration, RIICO cancels leases after fires.
Six state laws Flamekite read let a new MSME start on a declaration and defer most approvals: 3 years in Rajasthan and Gujarat, 3 years and 6 months in Kerala and Punjab, 1,000 days in Uttar Pradesh and 36 months in Haryana since 18 September 2026. None of these Acts waives fire safety standards, and Haryana's lets the fire authority inspect during the moratorium. Inside an industrial estate the corporation adds its own rules: GIDC hands over plug-and-play sheds with a fire NOC for the whole structure, and RIICO caps buildings at 15 m unless the fire service clears more.
- Punjab certificate in an approved park
- 5 working days
- Deemed issued if not decided (Act 14 of 2025)
- 14 states
Free, on WhatsApp. Or set a renewal reminder
Fire NOC for industries and MSMEs at a glance: 12 facts
| What | The rule | Source |
|---|---|---|
| Who issues inside an estate | The state fire service or local body; MIDC runs its own fire service, with each region's Divisional Fire Officer deciding | MIDC EoDB |
| What an MSME is since 1 April 2025 | Micro up to Rs 2.5 crore investment and Rs 10 crore turnover; small Rs 25 and Rs 100 crore; medium Rs 125 and Rs 500 crore (S.O. 1364(E)) | Gazette of India |
| Udyam registration | Free, online, paperless and self-declared; no documents uploaded, Aadhaar only | Udyam portal |
| Uttar Pradesh MSME Act, 2020 | Acknowledgement counts as approval for 1,000 days; the declaration carries a fire safety application form | UP Act 30 of 2020 |
| Rajasthan and Gujarat MSME Acts, 2019 | 3 years as an approval, then 6 months to obtain every approval, a no-objection included | Rajasthan Act 14 of 2019 |
| Kerala MSME Act as amended in 2024 | Certificate of in-principal approval valid 3 years and 6 months | Kerala Act 16 of 2019 |
| Punjab Right to Business Act | Fire NOC under the 2024 fire Act is in the schedule; 5 working days in an approved park, else deemed issued | Punjab Right to Business Act |
| Haryana Right to Business Act, 2026 | 36-month moratorium for Udyam-registered MSME manufacturing units; fire NOC for low-risk industries scheduled | Haryana Act 28 of 2026 |
| Tamil Nadu Act 15 of 2026 | Approval limits above 21 days cut to 21; the Schedule names the 2025 fire Act, not yet in force | TN Act 15 of 2026 |
| BRAP 2024 Reform No. 357 | Self-certification for low-risk inspections, third-party certification for medium-risk ones | Meghalaya PIPSD |
| GIDC plug-and-play shed | Comes with a fire department NOC for the whole structure; a plot does not | GIDC |
| RIICO after a negligent fire | Show cause under rule 24(1), 45 days to reply, then cancellation of allotment (circular of 16 February 2026) | RIICO circular 2026 |
Industrial development corporations and the fire NOC: 11 bodies
| Option | Who issues the unit's fire NOC | Estate rule that touches fire | Not confirmed | Source |
|---|---|---|---|---|
| MIDC, Maharashtra | MIDC's Fire Department, which also joins the occupancy inspection | Occupancy by joint inspection with the Fire Department; low and medium risk buildings skip the site visit; report online in 48 hours | Nothing open; the plot-to-Form B route is on the factories page | MIDC EoDB |
| GIDC, Gujarat | The state fire service, applied for on the Investor Facilitation Portal | 239 functional estates; plug-and-play sheds come with a fire NOC for the whole structure, plots do not | Whether GIDC estates keep their own fire officers | GIDC |
| RIICO, Rajasthan | The local body's fire wing, listed on Raj Nivesh as an LSG service | Industrial buildings to 15 m; 18 m only with a fire NOC; 4.5 m fire engine passage on plots of 4,001 m² or more | Whether the 3-year MSME exemption is applied to fire NOCs | RIICO land rules |
| UPSIDA, Uttar Pradesh | UP Fire and Emergency Services, through Nivesh Mitra | The 2020 MSME Act names UPSIDC's regional manager and the District Fire Safety Officer to the district committee | UPSIDA's own fire procedure: its sites did not load | UP Act 30 of 2020 |
| APIIC, Andhra Pradesh | AP Fire Services, on the Single Desk Portal | G.O.Ms.No.95 of 8 May 2026: common fire mains and yard hydrants in parks; APIIC may levy user charges | Which parks have the common system running | G.O.Ms.No.95 (I&C) |
| HSIIDC, Haryana | The Haryana fire service; for low-risk MSME manufacturing, a scheduled approval under the 2026 Act | HSIIDC building plans and the plinth certificate sit in the same schedule | Rules under the 2026 Act: none found | Haryana Act 28 of 2026 |
| PSIEC, Punjab | The Punjab fire service; the fire NOC application is serial 3 of the Right to Business schedule | PSIEC building plans and completion-cum-occupation are serial 10 of that schedule | PSIEC's own fire rules | Punjab Right to Business Act |
| TGIIC, Telangana | Telangana Fire Services; portal times are on the Telangana page | TS-iPASS rules let the Government notify which clearances are deemed approved when the deadline passes | The TS-iPASS fire entry: the portal was down | Telangana G.O.Ms.No.50 |
| KIADB, Karnataka | Karnataka Fire and Emergency Services; Seva Sindhu lists 60 working days for a high-rise NOC | Not found | KIADB's fire rule: the single-window and fire service sites failed security checks | Seva Sindhu |
| SIPCOT, Tamil Nadu | Tamil Nadu Fire and Rescue Services, on the Tamil Nadu Single Window Portal | Multi-storied buildings of 18.3 m and above take the TNFRS NOC route | SIPCOT's own fire procedure | TNSWP |
| SIDCUL, Uttarakhand | Uttarakhand Fire and Emergency Services, on Invest Uttarakhand | Pre-establishment fire NOC 15 days; pre-operational 30 days | SIDCUL's own route: its site did not respond | Invest Uttarakhand single window |
An MSME's fire NOC through an estate or single window in 8 steps
Register on Udyam and fix the hazard class
Udyam is free and self-declared and decides who counts as an MSME; the hazard class of the process decides the fire systems, as the factories page sets out.
Read the estate's own rules first
On a RIICO plot, keep to 15 m unless the fire service clears 18 m, and leave 4.5 m round a building on 4,001 m² or more. In GIDC, check whether you take a shed with a fire NOC or a bare plot.
Choose the MSME route or the regular route
The certificate under the MSME and right-to-business Acts is optional in Punjab and Haryana; a unit may apply for each approval directly at any time.
File on the state single window
In Uttar Pradesh the declaration carries a fire safety application form; in Punjab the statutory fees are paid online with the declaration.
Get the plan-stage fire approval or fire fighting scheme
Haryana's schedule lists a fire fighting scheme for white and green category low-risk industries; elsewhere it is the provisional fire NOC.
Install and audit
In Tripura, a medium or large industry adds a third-party safety audit report to the post-operative application.
Final NOC and occupancy
Expect a joint inspection where the estate runs one: MIDC sends its Fire Department with planning and water officers.
Close every approval before the holiday ends
Haryana wants all pending approvals in the last 6 months of the 36; Uttar Pradesh allows 100 days after the 1,000; Rajasthan and Gujarat 6 months after 3 years.
Single-window fire NOC timelines for industry in 14 states
The single window an industrial unit files on, the time it promises for the fire NOC, and whether a missed deadline counts as approval. Deemed approval in the MSME laws attaches to the in-principle certificate, not to the fire NOC itself.
| Single window | Fire NOC time limit | Deemed approval | |
|---|---|---|---|
| Uttar Pradesh UP Fire dashboard | Nivesh Mitra | 15 days at each stage; median 5 days on the fire dashboard | Not for the fire NOC; the MSME route gives 1,000 days instead |
| Rajasthan Raj Nivesh | Raj Nivesh | 15 days (LSG fire NOC) | Not found |
| Gujarat Gujarat IFP | Investor Facilitation Portal | 7 working days | Not found |
| Andhra Pradesh AP Fire Services | Single Desk Portal | Industry Provisional NOC in 7 working days since 2018 | Not found |
| Telangana TGFD Fire NOC note | TG-iPASS or the fire portal | 7 days up to 15 m, 14 days above | The rules let the Government notify deemed clearances; the fire entry was not read |
| Tamil Nadu TN Act 15 of 2026 | Tamil Nadu Single Window Portal | Any longer limit cut to 21 days under Act 15 of 2026 | Reaches fire once the 2025 fire Act starts; it is in the Schedule |
| Punjab Punjab Right to Business Act | State single window | In-principle certificate in 5 working days in an approved park; 15 or 18 outside | Yes, for the certificate: deemed issued if not decided |
| Haryana Haryana Act 28 of 2026 | Invest Haryana Single Window Portal | Certificate in 15 working days, then 10 days at the Enterprises Promotion Centre | Yes, for the certificate, then issued within 3 days |
| Kerala (large units) Kerala Act 16 of 2019 | Investment Facilitation Bureau | 7 working days on a complete composite application | The Bureau's decision counts as the fire service's own |
| Uttarakhand Invest Uttarakhand single window | Invest Uttarakhand | 15 days pre-establishment, 30 pre-operational | Not found |
| Tripura Tripura Home (F&ES) | SWAAGAT | 21 working days provisional, 28 for the NOC, 21 for renewal | Not found |
| Goa Directorate of Fire and Emergency Services, Goa | Goa Online | 5 to 15 days | No: "Provision not available" |
| Dadra and Nagar Haveli and Daman and Diu DNH and DD single window portal | DNH and DD single window | 30 working days | The Single Window Agency is the deemed-approval authority |
| Karnataka Seva Sindhu | Seva Sindhu | 60 working days for a high-rise NOC | Not found |
Every state's time limits for all buildings are on the processing-time page. The Uttar Pradesh median is from the fire service dashboard printed on 24 October 2026.
MSME facilitation Acts and the fire NOC: 6 state laws compared
Each Act lets a new MSME start on a declaration and treats the certificate as every state approval for a period. Their definitions of approval all include a no-objection; only Punjab and Haryana name the fire NOC outright.
Uttar Pradesh Act 30 of 2020
1,000 days, with a fire safety form
The declaration of intent carries a fire safety application form, and the District Fire Safety Officer sits on the district committee that meets after 72 hours. The certificate counts as approval for 1,000 days; approvals then follow within 100 days. Crackers and Red category products are excluded. UP Act 30 of 2020
Rajasthan Act 14 of 2019
3 years, Municipalities Act overridden
Approval covers any no-objection under a Rajasthan law, and section 9(2) names the Municipalities Act, 2009, under which the fire NOC is issued. A 2023 Bill to make it 5 years was reported passed on 20 March 2023. Rajasthan Act 14 of 2019
Gujarat Act 26 of 2019
3 years, with a fire safety undertaking
The unit signs an undertaking to ensure adequate fire safety. An inspector may still visit within the 3 years once the unit has applied for the permission. Gujarat Act 26 of 2019
Kerala Act 16 of 2019
3 years and 6 months since 2024
Act 26 of 2024 renamed the certificate one of in-principal approval and lengthened it. Larger units go to an Investment Facilitation Bureau with the Director General of Fire and Rescue Services as a member. Kerala Act 16 of 2019
Punjab Act 1 of 2020
Fire NOC named in the schedule
Serial 3 of the schedule substituted in October 2025 is the application for a fire NOC under the Punjab Fire and Emergency Service Act, 2024. The certificate runs 3 years and 6 months. Punjab Right to Business Act
Haryana Act 28 of 2026
36 months for low-risk manufacturing
Only Udyam-registered MSME manufacturing units qualify. The Fire Department's fire fighting scheme and NOC for low-risk industries are scheduled approvals. Haryana Act 28 of 2026
Haryana's 2026 Act: the fire safety inspection a moratorium cannot stop
The newest MSME law, in force since 18 September 2026, bars inspections for 36 months but keeps one door open for the fire authority.
Word for word
The Head of the concerned competent authority may suo motu for reasons to be recorded in writing, order an inspection to be conducted in cases of land use violations, unauthorized construction or issues relating to public safety, structural integrity or fire safety.
The older Acts say the same in their savings clauses. Section 10 of Rajasthan's 2019 Act, section 13 of Uttar Pradesh's 2020 Act and section 17 of Punjab's 2020 Act each provide that nothing exempts an enterprise from any law in force or the "regulatory measures and standards" under it, except as the Act expressly says. A certificate defers the paperwork and the routine visit; it does not lower the fire systems the building needs. Haryana's report of such an inspection must reach the unit online within 48 hours.
Which fire route fits your industrial unit: 12 cases
Match your unit to one line. The estate and the state's MSME law decide the route more than the size does.
If A plot in an MIDC industrial area
MIDC's own fire service issues the plan-stage and final approvals; the full route and documents are on the factories page. Fire NOC for Factory MIDC EoDB
If A plug-and-play shed in a GIDC estate
The shed is handed over with a fire department NOC for the whole structure, among 9 pre-approved clearances. GIDC
If A bare plot in a GIDC estate
Only NA permission and blanket environment clearance are pre-approved; apply for the fire NOC on the Investor Facilitation Portal, 7 working days. Fire NOC Gujarat Gujarat IFP
If A new MSME in Uttar Pradesh outside the Red category
File the declaration with its fire safety form; the certificate counts as approval for 1,000 days. Fire NOC UP UP Act 30 of 2020
If A new MSME in Rajasthan
The 2019 Act's certificate covers no-objections under the Municipalities Act for 3 years; no fire service order applying it to fire NOCs was found, so file the fire NOC on Raj Nivesh too. Fire NOC Rajasthan Rajasthan Act 14 of 2019
If A unit in an approved industrial park in Punjab
The in-principle certificate comes in 5 working days or is deemed issued; the fire NOC application is a scheduled service. Fire NOC Punjab Punjab Right to Business Act
If A low-risk MSME manufacturing unit in Haryana
With Udyam registration, a 36-month moratorium; the fire fighting scheme and NOC are scheduled; fire safety inspections may still be ordered. Fire NOC Haryana Haryana Act 28 of 2026
If A large non-MSME unit in Kerala outside the Red category
One composite application to the Investment Facilitation Bureau, decided in 7 working days; the approval runs 5 years. Fire NOC Kerala Kerala Act 16 of 2019
If A medium or large industry in Tripura
Apply on SWAAGAT and add a third-party safety audit report to the post-operative NOC. Fire NOC Tripura 2026 Tripura Home (F&ES)
If A unit inside an Andhra Pradesh industrial park
G.O.Ms.No.95 builds common fire mains and hydrants for the park; APIIC may charge for them. Fire NOC Andhra Pradesh G.O.Ms.No.95 (I&C)
If A unit in an industrial estate in Mizoram
A Common Fire NOC in the estate authority's name may cover the units once rule 57(A) is gazetted; it was signed on 20 August 2026. Fire NOC Mizoram 2026 Mizoram Home Dept
If A unit in Tamil Nadu
Apply on the single window; Act 15 of 2026 will hold the fire clearance to 21 days once the 2025 fire Act commences. Fire NOC Tamil Nadu TN Act 15 of 2026
A RIICO plot's fire approvals in Rajasthan, from allotment to lease risk
Rajasthan has no separate fire Act; the local body issues the NOC and RIICO's land rules and lease add the estate's own fire conditions. Read on 25 October 2026.
1. Allotment and lease
The lease with RIICO is the base document; rule 24(1) of the Disposal of Land Rules lets RIICO cancel it for a breach after a show cause notice. RIICO circular 2026
2. Building plans
NBC and the UDH Model Building Regulations, 2025 apply for fire definitions; plans must show active and passive fire protection and fire engine movement. RIICO land rules
3. Height and access
Up to 15 m as of right; up to 18 m by the Unit Head with a fire NOC and an 18 m road; above 18 m only through the Land Plan Committee. RIICO land rules
4. Fire NOC on Raj Nivesh
The single window lists the local body's FIRE NOC with a 15-day limit. Raj Nivesh
5. Fee and term
Rs 2, Rs 1.50 or Rs 1 per sq ft by size of town; G1 renews every 5 years, G2 every 3, G3 yearly. Rajasthan UDH
6. The MSME option
A new MSME may instead start on a 3-year acknowledgement under the 2019 Act and close its approvals within 6 months after. Rajasthan Act 14 of 2019
7. After a fire
Where negligence or unapproved hazardous stock caused it, the Unit Head starts rule 24(1) proceedings; the lessee gets 45 days to reply. RIICO circular 2026
An estate unit's fire file: 10 items to hold
What the estate rules, the MSME laws and the single windows ask an industrial unit to have ready, beyond the fire NOC itself.
- The Udyam registration, which Haryana's 2026 Act requires before a unit can seek the certificate. Haryana Act 28 of 2026
- In Uttar Pradesh, the fire safety application form filed with the declaration of intent. UP Act 30 of 2020
- In Gujarat, the signed undertaking that the unit will ensure adequate fire safety. Gujarat Act 26 of 2019
- On a RIICO plot, drawings showing active and passive fire protection to NBC and the fire engine path round the building. RIICO land rules
- On a RIICO plot of 4,001 m² or more, a clear 4.5 m passage round the building kept free of setback structures. RIICO land rules
- A fire or explosives NOC for the location and size of any diesel (HSD) storage tank in the setback. RIICO land rules
- In GIDC, plan approval within 3 months of the offer-cum-allotment letter. GIDC
- In Tripura, a third-party safety audit report for a medium or large industry at the post-operative stage. Tripura Home (F&ES)
- In Tripura, a self-certification of non-deviation with the NOC and each renewal. Tripura Home (F&ES)
- Proof that every regular approval was applied for on the single window inside the moratorium. Haryana Act 28 of 2026
What an estate unit pays around the fire NOC: official charges
Charges an industrial unit meets on the estate and single-window route, as the official pages print them. State fire NOC rates are on the fees page; consultants' prices are private and not shown.
As published
- Udyam registrationFree"No Costs or Fees are to be paid to anyone" Udyam portal
- GIDC plan approval scrutinyRs 5 per m²Of built-up area; process fee Rs 0.20 per m² of plot; service and amenities Rs 50 per m²; GST 18% GIDC
- Gujarat fire NOC renewal through the IFPRs 2,500 per blockFor the site inspection, plus Rs 1,000 at issue Gujarat IFP
- RIICO height above 15 m10% of the allotment rateBetterment levy, and only with a fire NOC RIICO land rules
- RIICO land for a fire stationRe 1Up to 4,000 m² to a municipality; industry associations pay 50% of the allotment rate RIICO land rules
- Punjab fire NOC for an MSME unitRs 5,000Letter of 8 October 2021 Local Govt Punjab
- Punjab statutory fees under the Right to Business ActPaid upfrontOnline with the declaration, before the certificate (section 19) Punjab Right to Business Act
- MIDC Fire Protection Fund feeNot publishedA demand note is generated online after scrutiny MIDC EoDB
- Tripura fire NOCNot published"As decided by the Government" Tripura Home (F&ES)
GIDC's plan approval fees are the estate's building charges, not fire fees. Every published state fire NOC rate is on the fire NOC fees page.
Why an MSME's fire NOC stalls in an estate or single window
Nine traps drawn from the Acts, the estate rules and the single-window sheets.
If The unit treats its MSME certificate as a fire clearance and builds without fire systems
The savings clauses keep every regulatory standard in force; design to the fire rules from day 1. Rajasthan Act 14 of 2019
If A cracker or Red category unit files under Uttar Pradesh's MSME Act
Section 11 excludes both; take the regular fire NOC route on Nivesh Mitra. UP Act 30 of 2020
If A RIICO building is drawn at 20 m
Above 18 m needs the Land Plan Committee, a fire NOC, an 18 m road and the betterment levy; plan for it or stay at 15 m. RIICO land rules
If Sheds or stores built in the setback of a large RIICO plot
Plots of 4,001 m² or more must keep 4.5 m clear for fire engines; setback facilities may not obstruct fire tenders. RIICO land rules
If A tenant of a GIDC shed assumes the shed's NOC covers any process
The pre-approved NOC is for the whole structure; tell the fire service before bringing in a hazardous process. GIDC
If A medium industry in Tripura files the post-operative NOC alone
Annex the third-party safety audit report; the checklist asks for it. Tripura Home (F&ES)
If Approvals left until the Haryana moratorium ends
The Act wants all pending approvals in the last 6 months; after that the fire service may act. Haryana Act 28 of 2026
If Hazardous stock moved onto a RIICO plot without approval
That is a ground for lease cancellation under the 2026 circular; get the permissions first. RIICO circular 2026
If Waiting for a Goa fire NOC to be deemed granted
Goa's BRAP sheet says deemed approval is not available; follow up or appeal. Directorate of Fire and Emergency Services, Goa
What an estate unit risks: lease, certificate and moratorium rules
Beyond the state fire law's own penalties, an industrial unit answers to its lease and to the MSME law it used.
| Offence | Penalty | Law |
|---|---|---|
| A fire caused by negligence, unauthorised activity or unapproved inflammable stock on a RIICO plot | Show cause notice, 45 days to reply, then cancellation of allotment, determination of the lease and resumption | RIICO Disposal of Land Rules, rule 24(1); circular of 16 February 2026 RIICO circular 2026 |
| False or fraudulent information in a Haryana declaration of intent | Certificate revoked after a hearing | Haryana Right to Business Act, 2026, section 12(1) Haryana Act 28 of 2026 |
| No approvals obtained by the end of Haryana's 36-month moratorium | Action, coercive measures included, under the applicable law | Section 12(3) Haryana Act 28 of 2026 |
| Uttar Pradesh approvals not obtained within 100 days after the 1,000 | The acknowledgement stops counting as an approval | UP MSME Act, 2020, section 9(1) UP Act 30 of 2020 |
| Rajasthan approvals not obtained within 6 months after the 3 years | The acknowledgement stops counting as an approval | Rajasthan MSME Act, 2019, section 6(1) Rajasthan Act 14 of 2019 |
| A serious complaint during Punjab's certificate period | Inspection ordered by the head of the authority, by an officer of Joint Director rank or above | Punjab Right to Business Act, section 8(6) Punjab Right to Business Act |
Fire law penalties for running without a NOC are on the fire NOC penalties page.
Industrial and MSME fire NOC reforms, dated: 2014 to 2026
Nineteen dated steps that shaped how an industrial unit gets its fire NOC today.
2014
Telangana's TS-iPASS Act (Act 3 of 2014) sets up a self-certified industrial single window. Telangana G.O.Ms.No.50
2017
Andhra Pradesh moves industry fire NOC applications to the Single Desk Portal only. AP Fire Services
28 July 2017
Telangana's G.O.Ms.No.50 lets the Government notify clearances that are deemed approved after the deadline. Telangana G.O.Ms.No.50
8 March 2018
Andhra Pradesh cuts the industry Provisional NOC to 7 working days from 21. AP Fire Services
17 July 2019
Rajasthan's MSME Act receives assent, deemed in force from 4 March 2019. Rajasthan Act 14 of 2019
16 December 2019
Gujarat's MSME Act receives assent, deemed in force from 24 October 2019. Gujarat Act 26 of 2019
6 February 2020
Punjab's Right to Business Act is gazetted, with the fire NOC in its schedule. Punjab Right to Business Act
28 August 2020
Uttar Pradesh's MSME Act receives assent: 1,000 days. UP Act 30 of 2020
1 March 2024
West Bengal moves low-hazard factories up to 15 m and 500 m² to yearly self-certification. WB notification 1930
24 January 2025
RIICO records that it has built fire stations and bought tenders for its areas. RIICO circular 2025
12 March 2025
Meghalaya tells DPIIT it has no third-party agencies for BRAP 2024 Reform 357. Meghalaya PIPSD
1 April 2025
New MSME limits: medium up to Rs 125 crore investment and Rs 500 crore turnover. Gazette of India
18 October 2025
Punjab Act 14 of 2025: 5 working days in approved parks; the fire NOC moves to the 2024 fire Act. Punjab Right to Business Act
10 December 2025
Maharashtra order 1763 lets low-hazard industry up to 2,000 m² self-certify its fire approval. MFS office order 2025
16 February 2026
A fire in RIICO's Khushkhera (Bhiwadi) area causes casualties; RIICO orders lease action after negligent fires. RIICO circular 2026
8 May 2026
Andhra Pradesh orders common fire infrastructure in industrial parks. G.O.Ms.No.95 (I&C)
20 August 2026
Mizoram signs a Common Fire NOC rule for industrial estates, awaiting the Gazette. Mizoram Home Dept
12 September 2026
Tamil Nadu's Act 15 of 2026 receives assent: a 21-day cap on scheduled clearances. TN Act 15 of 2026
18 September 2026
Haryana's Right to Business Act takes effect: 36 months for low-risk MSME manufacturing. Haryana Act 28 of 2026
MSME and estate fire NOC myths, checked against the Acts
You may have read
Udyam registration is all an MSME needs to start.
Myth
What the sources say
Udyam is a free, self-declared registration with no documents; it decides who may use the MSME laws, not whether the building is safe. Udyam portal
You may have read
An MSME acknowledgement certificate exempts the unit from fire safety.
Myth
What the sources say
It defers approvals and routine inspections; the savings clauses keep every regulatory standard in force. UP Act 30 of 2020
You may have read
If the fire service misses its deadline, the fire NOC is deemed granted.
Myth
What the sources say
Punjab and Haryana deem the MSME certificate issued, not a fire NOC; Goa says deemed approval is not available for the fire NOC. Directorate of Fire and Emergency Services, Goa
You may have read
No inspector can enter during an MSME moratorium.
Myth
What the sources say
Haryana allows fire safety inspections on the head of the authority's order; Punjab allows them on serious complaints. Haryana Act 28 of 2026
You may have read
An estate with its own fire station needs no fire systems in each unit.
Myth
What the sources say
RIICO still wants each plan to show active and passive fire protection to NBC. RIICO land rules
You may have read
Third-party fire certification is available in every state.
Myth
What the sources say
Meghalaya told DPIIT in March 2025 that it had no third-party agencies for Reform 357. Meghalaya PIPSD
MSME fire compliance in an estate: 6 dos and 5 don'ts
From the MSME Acts, the estate rules and the single-window sheets.
Do
- Register on Udyam first; Haryana's 2026 Act admits only Udyam-registered units. Haryana Act 28 of 2026
- Apply for the fire NOC early: in Gujarat an inspector may visit once you have applied, even inside the 3 years. Gujarat Act 26 of 2019
- Pay the scheduled fees with the declaration in Punjab, or the certificate will not issue. Punjab Right to Business Act
- Keep a 4.5 m fire engine path round a building on a large RIICO plot. RIICO land rules
- In an Andhra Pradesh park, ask APIIC whether the common fire main and hydrants serve your plot. G.O.Ms.No.95 (I&C)
- Keep the third-party audit report on file if your Tripura unit is medium or large. Tripura Home (F&ES)
Don’t
- Don't use the certificate to build against the master plan's land use; every Act forbids it. Punjab Right to Business Act
- Don't place a diesel tank in a RIICO setback without its fire or explosives NOC. RIICO land rules
- Don't let setback structures block fire tenders on a RIICO plot. RIICO land rules
- Don't file a declaration with false facts in Haryana; the certificate can be revoked. Haryana Act 28 of 2026
- Don't store highly inflammable material on a RIICO plot without approval. RIICO circular 2026
MSME fire NOC worked cases: 7 units in 7 states
Flamekite's reading of each state's Act for 7 example units. The units are illustrations; the rules and figures are the instruments'.
Case 1
A food-processing MSME near Lucknow
New micro unit, Green category, 600 m² shed.
What applies Files the declaration with its fire safety form; the certificate counts for 1,000 days, then all approvals, the fire NOC included, within 100 days. UP Act 30 of 2020
Case 2
A garment unit in a Ludhiana focal point
New small unit in an approved industrial park.
What applies In-principle certificate in 5 working days or deemed issued; fees paid with the declaration; regular approvals applied for within 3 years. Punjab Right to Business Act
Case 3
An engineering MSME in an HSIIDC estate
Low-risk manufacturing, Udyam-registered.
What applies 15 working days at the district, then 10 at the Enterprises Promotion Centre, deemed approved if neither decides; 36 months to finish the fire NOC and the rest. Haryana Act 28 of 2026
Case 4
A plug-and-play shed in a GIDC estate
Multi-level shed taken on allotment.
What applies The shed already holds a fire NOC for the whole structure; at renewal, Rs 2,500 per block for the inspection and Rs 1,000 at issue on the IFP. Gujarat IFP
Case 5
A 20 m plant building at Bhiwadi
RIICO plot of 5,000 m² on an 18 m road.
What applies Above 18 m, so the Land Plan Committee, a fire NOC and a 10% betterment levy; 4.5 m kept clear round the building. RIICO land rules
Case 6
A medium-scale unit near Agartala
Applying for the post-operative NOC.
What applies SWAAGAT application with a third-party safety audit and a self-certification; 28 working days. Tripura Home (F&ES)
Case 7
A large non-MSME plant in Kerala
Orange category, applying to the Bureau.
What applies One composite application decided in 7 working days, binding on the fire service; approval runs 5 years, with a compliance certificate within 1 year. Kerala Act 16 of 2019
Industrial estates and MSME fire rules in numbers
1,000 days
Uttar Pradesh MSME certificate counted as every approval UP Act 30 of 2020
36 months
Haryana's moratorium for low-risk MSME manufacturing Haryana Act 28 of 2026
21 days
Tamil Nadu's cap on scheduled clearances under Act 15 of 2026 TN Act 15 of 2026
45 days
A RIICO lessee's time to answer a show cause notice after a fire RIICO circular 2026
239
Functional GIDC estates in Gujarat GIDC
4,000 m²
RIICO land for a fire station at a token Re 1 RIICO land rules
48 hours
MIDC inspectors' deadline to upload an occupancy inspection report MIDC EoDB
5,51,55,843
Udyam registrations on 25 October 2026 Udyam portal
Single-window and MSME terms: declaration of intent to deemed approval
- Declaration of intent
- The MSME's filing that starts the certificate; in Uttar Pradesh it carries land, electrical, pollution, labour and fire safety forms. UP Act 30 of 2020
- Acknowledgement certificate
- The certificate that counts as every state approval for a period: 3 years in Rajasthan and Gujarat. Gujarat Act 26 of 2019
- Certificate of in-principle approval
- Punjab's, Kerala's and Haryana's name for it; 3 years and 6 months in Punjab and Kerala. Punjab Right to Business Act
- Moratorium period
- Haryana's 36 months from the certificate in which no routine inspection or coercive step is taken. Haryana Act 28 of 2026
- Deemed approval
- Approval treated as given once a deadline passes; in Haryana after the Enterprises Promotion Centre's 10 days. Haryana Act 28 of 2026
- Approved Industrial Park
- In Punjab: an industrial area, focal point, estate, mixed-use park, SEZ, textile, biotech, IT or food park, township or growth centre. Punjab Right to Business Act
- Eligible enterprise
- Haryana: an Udyam-registered MSME manufacturing unit, new or expanding. Haryana Act 28 of 2026
- Reform No. 357
- BRAP 2024's self-certification and third-party ecosystem for low- and medium-risk inspections. Meghalaya PIPSD
- Plug-and-play shed
- A GIDC multi-level shed allotted with 9 clearances already in place, the fire NOC among them. GIDC
- Investment Facilitation Bureau
- Kerala's 7-working-day window for large units, with the fire service head as a member. Kerala Act 16 of 2019
Where an industrial unit applies: 9 single-window portals
Official addresses that held the industrial approval forms and procedures on 25 October 2026.
Rajasthan
Raj Nivesh services
Rajasthan's single window, listing the local body's fire NOC at 15 days Raj Nivesh
rajnivesh.rajasthan.gov.in/Home/ServicesGujarat
Investor Facilitation Portal
Gujarat's fire licence or NOC and its renewal, and GIDC plan approval Gujarat IFP
ifp.gujarat.gov.inGujarat, GIDC
GIDC plug and play
Which clearances a GIDC shed or plot comes with GIDC
gidc.gujarat.gov.in/Pages/Contents/Plug-and-PlayMaharashtra, MIDC
MIDC Ease of Doing Business: occupancy
Risk-based occupancy inspection with the Fire Department MIDC EoDB
eodb.midcindia.org/Occupancy_Info.aspxHaryana
Invest Haryana
The single window the 2026 Act names for every approval during the moratorium Haryana Act 28 of 2026
investharyana.inUttarakhand
Invest Uttarakhand
Pre-establishment and pre-operational fire NOCs Invest Uttarakhand single window
investuttarakhand.uk.gov.in/site/ServiceListingNew/iw/Y/id/ALLTripura
SWAAGAT
Tripura's single window for provisional, final and renewal fire NOCs Tripura Home (F&ES)
swaagat.tripura.gov.inGoa
Goa Online
Goa's Initial, Final and renewal fire NOCs under Ease of Doing Business Directorate of Fire and Emergency Services, Goa
goaonline.gov.inAll India
Udyam Registration
Free MSME registration on Aadhaar Udyam portal
udyamregistration.gov.in
Industrial area fire and approval news, 2023 to 2026
From news reports, not yet an official source.
Press reports, not instruments. They show the direction: more fire stations in estates, tighter estate enforcement and shorter approval clocks.
14 October 2026
Tamil Nadu: the 21-day deadline for industrial approvals was reported in force; Flamekite did not read the commencement notification. DT Nextnews report
30 April 2026
RIICO earmarks Rs 25 crore for 12 new fire stations and 37 fire tenders in Rajasthan's industrial areas. Swarajyanews report
23 March 2026
Goa's industrial development corporation starts a fire safety audit of its 24 industrial estates. The Goannews report
4 July 2025
Delhi discusses moving fire inspections and NOCs to a third party or the MCD, with NOCs on empanelled agencies' audits for large industrial units; a proposal only. The Weeknews report
21 March 2023
Rajasthan's Assembly passes the MSME amendment raising the exemption from 3 to 5 years. KNN Indianews report
Offices behind estate and MSME approvals: RIICO, GIDC, HEPC, Udyam
Only as published on the pages Flamekite read. For your own unit, the state fire service and the estate's regional office decide.
Rajasthan State Industrial Development and Investment Corporation (RIICO) RIICO circular 2026
Issues the fire-incident circulars and the land rules for its industrial areas
- Address
- Udyog Bhawan, Tilak Marg, C-Scheme, Jaipur 302005
- Website
- riico.rajasthan.gov.in
Gujarat Industrial Development Corporation (GIDC) GIDC
Runs 239 functional estates and the plug-and-play sheds
- Website
- gidc.gujarat.gov.in
Haryana Enterprises Promotion Centre Haryana Act 28 of 2026
Its Deputy CEO decides MSME declarations the district has not decided, within 10 days
- Website
- investharyana.in
Udyam Registration, Ministry of MSME Udyam portal
Free MSME registration that the Haryana Act requires
- Website
- udyamregistration.gov.in
What Flamekite could not confirm about industrial fire routes
Five estate bodies publish no fire route Flamekite could read on 25 October 2026, and two laws wait on notifications.
Karnataka: the state single window's fire service page failed with an expired security certificate and the fire service site refused the connection, so KIADB's fire rule is not shown. Seva Sindhu's 60-working-day high-rise NOC is the only Karnataka timeline here.
Uttar Pradesh, Uttarakhand and Telangana: UPSIDA's sites returned an error or no response, SIDCUL's did not respond, and the TG-iPASS portal was down. The TS-iPASS Act on India Code returned 403, so its sections on deemed approval and the fire line of Annexure VI were not read. SIPCOT's services page names NOCs but no fire procedure.
Rajasthan: the 2019 MSME Act's definition reaches a no-objection under the Municipalities Act, but Flamekite found no fire service order applying the 3-year holiday to fire NOCs. The 2023 amendment to 5 years was reported passed on 20 March 2023; the amending Act was not read. Uttar Pradesh's MSME Act starts on a notified date that Flamekite did not read.
Haryana and Tamil Nadu: rules under Haryana's 2026 Act were not found, so the forms and fees are open. Tamil Nadu's 21-day cap reaches the 2025 fire Act, which has no commencement notification, and the 1985 Act in force is not in the Schedule.
| What | The rule | Source |
|---|---|---|
| KIADB fire rule | Not read: Karnataka single window certificate expired on 25 October 2026 | Seva Sindhu |
| TS-iPASS fire entry | Not read: only the 2017 rule amendment was available | Telangana G.O.Ms.No.50 |
| Rajasthan 5-year amendment | Reported passed 20 March 2023; Act not read | PRS bill summarynews report |
| Haryana rules | Not found; the 2026 Act leaves forms and fees to rules | Haryana Act 28 of 2026 |
| Tamil Nadu 21-day cap for fire | Waits on the 2025 fire Act's start | Government of Tamil Nadu, Gazette Extraordinary No. 263, 6 June 2025 |
Questions about fire NOCs for industries and MSMEs
Do MSMEs need a fire NOC?
- Yes, wherever the state's fire line catches the building. The MSME laws only defer approvals: Uttar Pradesh for 1,000 days, Rajasthan and Gujarat for 3 years, Punjab and Kerala for 3 years and 6 months, Haryana for 36 months. Punjab and Haryana list the fire NOC as a scheduled approval, and fire safety standards stay in force throughout.
Does Udyam registration replace a fire NOC?
- No. Udyam is a free, online, self-declared registration with no documents to upload. It tells the state which enterprises are MSMEs; Haryana's 2026 Act uses it to decide who may seek the certificate. The fire NOC is still issued by the state fire service or local body.
Does an MSME acknowledgement certificate cover the fire NOC?
- For a period, in some states. Each Act's approval includes a no-objection, and Punjab's schedule names the fire NOC application. But the savings clauses keep every regulatory standard in force, and the unit must obtain the regular fire NOC before the period ends or within 6 months or 100 days after it.
How do I get a fire NOC in an industrial area?
- Through the state single window, unless your estate runs its own fire service as MIDC does. Read the estate's rules first: RIICO caps buildings at 15 m without a fire NOC, and GIDC sheds come with one. Then file the plan-stage fire approval, install, and pass the final inspection.
Is there deemed approval for a fire NOC?
- Rarely for the fire NOC itself. Goa says it is not available. Punjab and Haryana deem the MSME certificate issued when a deadline passes, and the DNH and DD single window is a deemed-approval authority. Telangana's rules let the Government notify deemed clearances, but the fire entry was not read.
How long does a fire NOC take through a single window?
- From 5 days to 60 working days. Goa promises 5 to 15 days, Gujarat 7 working days, Telangana 7 days up to 15 m, Rajasthan and Uttar Pradesh 15 days, Tripura 28 working days and Karnataka 60 working days for a high-rise NOC. Tamil Nadu's law will cap scheduled clearances at 21 days.
What is third-party certification under BRAP for industry?
- BRAP 2024 Reform No. 357 asks states to move low-risk inspections to self-certification and medium-risk ones to accredited third parties. Tripura already asks medium and large industries for a third-party safety audit; Meghalaya told DPIIT in March 2025 it had no such agencies.
Can RIICO cancel my plot after a fire?
- Yes, if the fire came from negligence, unauthorised activity, unapproved inflammable or hazardous stock or a lease breach. RIICO's circular of 16 February 2026 orders a show cause notice under rule 24(1), 45 days to reply, then cancellation of allotment and resumption of the plot.
Keep reading
- Fire NOC in IndiaThe law, issuer, portal and validity in all 36 states and UTs.
- Fire NOC for factoriesNBC Group G systems, state factory lines and the OSH Code.
- Fire NOC for warehousesStorage buildings: lines, systems and terms.
- Fire NOC processing timeEvery state's time limits, appeals and real waits.
- Apply for a fire NOC onlineEvery state's fire portal and single window.
- Fire NOC feesEvery published state rate, per m² and per stage.
- Fire NOC validityTerms for every occupancy, industry included.
- Third-party fire auditWho may audit, where the law asks for it.
Free tools for this
Words on this page, explained
Keep exploring
Fire NOC for other industrial and storage buildings
Fire NOC: the steps
Sources
Each source was opened and read on the date shown. How Flamekite checks its sources
- Uttar Pradesh Gazette, 31 August 2020, English translation (copy hosted by Invest UP): Uttar Pradesh Micro, Small and Medium Enterprises (Facilitation of Establishment and Operation) Act, 2020: sections 2(c), 3(2), 7(1)(e), 8, 9, 11 and 13 (opens in a new tab)
- Rajasthan Gazette, 18 July 2019 (copy hosted by PRS Legislative Research): Rajasthan Micro, Small and Medium Enterprises (Facilitation of Establishment and Operation) Act, 2019: sections 2(b), 3, 5, 6, 7, 9(2) and 10 (opens in a new tab)
- Gujarat Government Gazette Extraordinary, 17 December 2019 (copy hosted by PRS Legislative Research): Gujarat Micro, Small and Medium Enterprises (Facilitation of Establishment and Operation) Act, 2019: sections 2(b), 2(l) undertaking on fire safety, 3, 5 and 6 (opens in a new tab)
- Kerala Gazette (copy hosted by PRS Legislative Research): Kerala Micro Small and Medium Enterprises and Other Enterprises Facilitation Act, 2019, with Act 32 of 2021 (Investment Facilitation Bureau, sections 6A to 6C) and Act 26 of 2024 (Certificate of in-principal approval, 3 years and 6 months) (opens in a new tab)
- Punjab Government Gazette Extraordinary, 6 February 2020, 3 January 2022 and 18 October 2025 (copies hosted by PRS Legislative Research): Punjab Right to Business Act, 2020 (Act 1 of 2020) with the 2022 amendment and Act 14 of 2025: sections 8, 10, 18 (schedule serial 3: fire NOC under the Punjab Fire and Emergency Service Act, 2024) and 19 (opens in a new tab)
- Haryana Government Gazette Extraordinary, 18 September 2026 (copy hosted by PRS Legislative Research): Haryana Right to Business Act, 2026 (Act 28 of 2026): sections 2, 9 to 13 and the Schedule (Fire Department: fire fighting scheme and fire NOC for low-risk industries) (opens in a new tab)
Show all 45 sourcesShow fewer
- Tamil Nadu Government Gazette Extraordinary (copy hosted by PRS Legislative Research): Tamil Nadu Business Facilitation Act, 2018 with the Amendment Act 15 of 2026 (assent 12 September 2026): substituted section 11 (21-day limit) and the Schedule (item 22, Tamil Nadu Fire and Rescue Services Act, 2025) (opens in a new tab)
- Gazette of India, Ministry of Micro, Small and Medium Enterprises: Notification S.O. 1364(E), 21 March 2025: revised investment and turnover limits for micro, small and medium enterprises from 1 April 2025 (opens in a new tab)
- Udyam Registration, Ministry of Micro, Small and Medium Enterprises: Udyam Registration home page: free, online, paperless, self-declared registration; factsheet of 25 October 2026 (opens in a new tab)
- Rajasthan State Industrial Development and Investment Corporation (RIICO): RIICO Disposal of Land Rules, 1979, as amended up to 8 April 2026: rule 3(O) fire fighting stations and Building Regulations for industrial plots (2.1, 3, 5.2, 6.1.13, 6.2.5, 7.1 to 7.5) (opens in a new tab)
- Rajasthan State Industrial Development and Investment Corporation (RIICO): Circular No. RIICO/Tech/2026, 16 February 2026: show cause notice under rule 24(1) and cancellation of allotment or determination of lease in cases of fire incidents and prohibited activities (read off the page images) (opens in a new tab)
- Gujarat Industrial Development Corporation (GIDC): Plug and Play: pre-approved clearances for multi-level sheds (fire NOC for the whole structure) and for plots (last updated 23 October 2026) (opens in a new tab)
- Planning, Investment Promotion and Sustainable Development Department, Government of Meghalaya: Letter No. PLR 44/2020/Pt-IV/75, 12 March 2025, to DPIIT: BRAP 2024 Reform No. 357, self-certification and third-party ecosystem, no third-party agencies in Meghalaya (opens in a new tab)
- Government of Tamil Nadu, Gazette Extraordinary No. 263, 6 June 2025: Tamil Nadu Fire and Rescue Services Act, 2025 (TN Act 37 of 2025) (opens in a new tab)
- Maharashtra Industrial Development Corporation: Fire NOC procedure on the MIDC Ease of Doing Business pages: an existing factory attaches its Form B with Annexure; applications go to the regional Divisional Fire Officer (opens in a new tab)
- Uttar Pradesh Fire and Emergency Services: Dashboard: provisional, final and renewal applications, approvals and days to certificate (printed 24 October 2026) (opens in a new tab)
- Raj Nivesh, Government of Rajasthan single window: Services and timelines: LSG FIRE NOC 15 days, LSG building plan approval 30 days (opens in a new tab)
- Investor Facilitation Portal, Government of Gujarat: Application for Fire License/NoC: process flow, checklist, fee details and 7-working-day timeline (opens in a new tab)
- AP State Disaster Response and Fire Services: Circular Memorandum Rc.No.10951/MSB/2017, 8 March 2018: industry Provisional NOC within 7 working days instead of 21 days (opens in a new tab)
- Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Fire NOC: timelines and inspection checklist (FireNOC.pdf) (opens in a new tab)
- Invest Uttarakhand single window: Service listing: fire services 26.0 and 27.0 (opens in a new tab)
- Home (F&ES) Department, Government of Tripura: Annexure-A: checklist for Provisional NOC (Form A), NOC (Form B) and renewal (Form C) (opens in a new tab)
- Directorate of Fire and Emergency Services, Goa: BRAP 2024 item 284: fire NOC fees and timeline (opens in a new tab)
- DNH and DD single window portal: Fire and Emergency Services DNHDD: online services and reform points (opens in a new tab)
- Seva Sindhu, Government of Karnataka: Application for No Objection Certificate (High rise Building) - Fire & Emergency: documents, fee under G.O. of 13-09-2019, 60 working days (opens in a new tab)
- Government of Andhra Pradesh, Industries and Commerce (Prog.III) Department (copy hosted by AP Fire Services): G.O.Ms.No.95, 8 May 2026: common fire safety infrastructure in industrial parks and for units outside them (opens in a new tab)
- Home Department, Government of Mizoram (copy on the Mizoram Fire and Emergency Services site): Notification No. B-20011/2/2026-HM(F&ES), 20 August 2026: Mizoram Fire and Emergency Services (Superintendence and Control of the Fire Force and Fire Safety and Prevention) (Amendment) Rules, 2026, substituting Rule 57 and inserting Rules 57(A) and 57(B) (opens in a new tab)
- Urban Development, Housing and Local Self Government Departments, Rajasthan: Joint order No. P.11(9)UDH/2020 Part, 14 September 2023, on the fire safety certificate and fire NOC (18-page Hindi scan) (opens in a new tab)
- Gujarat Industrial Development Corporation (GIDC): Application for plan approval: IFP route, 3 months from the OCA letter, risk classes for site inspection, 15 days, fees per m² (opens in a new tab)
- Investor Facilitation Portal, Government of Gujarat: Renewal of Fire License/NoC: Rs 2,500 per block site inspection, Rs 1,000 issuance, 7 working days (opens in a new tab)
- Directorate of Local Government, Punjab (Wayback Machine copy of 21 March 2022 of the portal's fee download): Letter No. S4-DSMS-(Fire)-2021/41343 of 8 October 2021: new fees for online fire NOCs, by NBC zone, with provisional, renewal and 30-day rules (opens in a new tab)
- Industries and Commerce Department, Government of Telangana (copy hosted by GHMC): G.O.Ms.No.50, 28 July 2017: amendments to the TS-iPASS Rules, 2015 (rule 10 time limits and deemed approval, rule 19 computerised inspections) (opens in a new tab)
- AP State Disaster Response and Fire Services: Memorandum Rc.No.3350/MSB/2017: industry NOC applications through the AP Single Desk Portal only; Mee Seva discontinued (opens in a new tab)
- Department of Fire and Emergency Services, Government of West Bengal: Notification 1930/FES/O/MISC-08/2023, 1 March 2024: 12 occupancies moved to yearly self-certification (with forwarding letter 1961 of 5 March 2024) (opens in a new tab)
- Rajasthan State Industrial Development and Investment Corporation (RIICO): Circular of the Executive Director, January 2025: RIICO fire stations and fire tenders; unit heads to attend and report fires immediately (opens in a new tab)
- Directorate of Maharashtra Fire and Emergency Services: Office Order No. MFS-2025/1763, 10 December 2025: self-certified fire approval for low-hazard industries up to 2,000 m² and below 18 m, Form B in January and July where no renewal is due, and 10% of cases picked for inspection (read from the page images) (opens in a new tab)
- Gujarat Industrial Development Corporation (GIDC): Advantage of being in a GIDC estate: 239 functional estates (last updated 23 October 2026) (opens in a new tab)
- Maharashtra Industrial Development Corporation (MIDC), Ease of Doing Business: Occupancy certificate: risk-based site inspection, joint inspection with the Fire Department, report online in 48 hours, 30 days (opens in a new tab)
- Guidance Tamil Nadu, Tamil Nadu Single Window Portal: No Objection Certificate for Multi Storied Buildings (18.3 m and above) from TNFRS: procedure, documents, timelines and fees (opens in a new tab)
- PRS Legislative Research (bill summary): Rajasthan MSME (Facilitation of Establishment and Operation) (Amendment) Bill, 2023: validity from 3 to 5 years; introduced 28 February 2023 (opens in a new tab)
- DT Next: Deadline for industrial nod reduced after Governor's assent (14 October 2026) (opens in a new tab)
- Swarajya: Rs 1,500 crore for Rajasthan's industrial infrastructure in FY27: 12 new fire stations and 37 fire tenders (30 April 2026) (opens in a new tab)
- The Goan: GIDC rolls out fire safety audit across industrial estates (23 March 2026) (opens in a new tab)
- The Week (PTI): Delhi govt plans to relieve Fire Service of inspection, issuing NOC tasks (4 July 2025): a proposal under discussion (opens in a new tab)
- KNN India: Rajasthan Assembly passes MSME Bill, increases approval and inspection exemption period to 5 years (21 March 2023) (opens in a new tab)