Fire NOC documents 28 min read

Documents required for a fire NOC: stage-wise lists, state checklists and form numbers

Updated By Flamekite Editorial DeskFacts checked against official sources on

Quick answer

Every fire NOC file in India rests on the same core: building plans with the fire systems marked, proof of ownership or tenancy, the applicant's ID and the fee receipt; later stages add the earlier NOC and an installer's certificate. The exact list is your state's: Flamekite read 14 official checklists on 24 October 2026.

Official lists run from 3 enclosures (Meghalaya's plan-stage SOP) to 19 items (PMRDA's final NOC near Pune). Tripura dropped affidavits for self-certification in October 2026, Kerala rejects fire plans that are not on its A1 template, and Uttar Pradesh, Bihar and Haryana publish no document list Flamekite could find.

Official checklists read
14
States and UTs, plus 4 city lists
State table
Length of an official list
3 to 19 items
Meghalaya SOP to PMRDA final NOC
The numbers
Kerala fire plan sheet
84.1 cm x 59.4 cm
A1 template since 14 July 2025
Drawing rules
Tripura affidavits dropped
October 2026
Self-attested copies instead
The notice

Fire NOC documents at a glance

What the official document lists have in common, and where they differ, with the source of each fact.
WhatThe ruleSource
Shortest official list3 enclosures: ID proof, a building plan and a fire layout plan (Meghalaya, plan stage)Invest Meghalaya
Longest official list19 items for a final NOC from PMRDA, including pump, pressure and fire door certificatesPMRDA
Maharashtra, Director areas14 rows for a provisional NOC and 6 for a final NOC on the MFS e-fire pageMFS e-fire
Drawing conventionFire fighting systems marked in red on 7 drawings, plans signed by the owner and a technical person (Telangana)TGFD procedure
Sheet standardKerala: A1 template with a 10 cm x 8 cm QR space, mandatory since 14 July 2025Kerala Fire and Rescue Services
Installer's proofForm A from a licensed agency; Maharashtra's list of such agencies prints 861 rowsMFS agency list
AffidavitNot needed for Tripura's self-certification Forms D, J, N and R from October 2026: self-attested copies onlyDirectorate of Fire and Emergency Services, Tripura
Renewal fileAs small as 3 documents in Punjab: ownership proof, the applicant's ID and the old NOCPunjab Fire Services
Upload limitsFrom 2 MB per PDF in Rajasthan to 10 MB per JPG or PDF in ChhattisgarhCG Fire NOC
Last verified24 October 2026, against each state's own checklist page or PDFNot stated

Fire NOC documents by stage: provisional, final and renewal in 9 states

What each official list asks for at the plan stage, at completion and at renewal. Where a state's list does not cover a stage, the cell says so.
OptionProvisional or plan stageFinal or occupancy stageRenewalSource
Maharashtra (MFS, Director areas)14 rows: letterhead application, 2 sets of metric drawings, area certificate, activity note, architect's compliance certificate, Fire Protection Fund receipt6 rows: approved or revised drawings, the provisional NOC, and a licensed agency's or CFO's certificateNo list on the e-fire pageMFS e-fire
Kerala4 soft copies: application cum checklist, fire system plans, civil plan, treasury challan5: the building-permit NOC, plus as-built checklist, fire plans, civil plans and challan3: final NOC, challan, civil planKerala Fire and Rescue
Tripura (SWAAGAT checklist)Form A, plans marked in red and certified, trade licence, Form 1, fee receiptForm B, as-built plans marked in red, Form 2, non-deviation self-certificate, third-party audit for medium and large industryForm C, last NOC, checklist, trade licence, non-deviation self-certificateTripura Home (F&ES)
Tamil NaduApplication, Appendices 1 and 2, 3 sets of plansCopy of the NOC, details of fire safety measures, fire safety plan with alarm and hydrant layoutCopy of the previous year's licenceTamil Nadu Fire and Rescue Services
ChhattisgarhBuilding registration certificate and a layout plan marking each required systemRegistration certificate and building permission, or an affidavit where there is noneBoth of those, plus the previous NOCCG Fire NOC
Telangana7 drawings with fire systems in red: site, basement, stilt or ground, floors, terrace, section, elevationThe same 7 drawings plus the provisional or revised provisional NOCNot in this listTGFD procedure
Goa7: ownership proof, TCP-approved plan, fire protection plan, project report, Form I, Form U undertaking, Form FThe same set without Form UNot in the BRAP checklist; renewal valid 5 yearsDirectorate of Fire and Emergency Services, Goa
PunjabOne new-NOC list: ownership proof, fire drawing, owner's checklist, ID proofCovered by the new-NOC list3: ownership proof, applicant's ID, old NOCPunjab Fire Services
Gujarat (FSCOP)Fire Safety Plan Approval: no self-declaration requiredFire Safety Certificate Approval: 3 self-declarations, on maintenance, an AMC and electrical safetyRenewal through a private Fire Safety Officer chosen on the portal, approved by the Regional or Chief Fire Officer since 24 June 2024Gujarat FSCOP guide

How to put together a fire NOC document file, step by step

  1. Download your state's current list

    Open the checklist on the fire service portal itself, not a copy. Ahmedabad's fire NOC list online today is a PDF created on 29 June 2015, so check the date of whatever you download.

  2. Fix who signs and who applies

    Decide whether the owner or the appointed architect files. MFS accepts either, but an architect or company filing needs an authorisation letter on letterhead.

  3. Collect the identity and ownership papers

    Gather 1 ID proof and 1 ownership or tenancy proof: an allotment letter, jamabandi, rent or lease deed, or a power of attorney, as Punjab lists them.

  4. Have the fire drawings drawn to the state's format

    Mark every fire system in red where Telangana or Tripura asks, use the A1 template in Kerala, and keep each file under the cap: 5 MB per drawing in Kerala, 10 MB in Chhattisgarh.

  5. Get the professional certificates signed

    The architect's compliance and area certificates come first; at completion add the licensed agency's installation certificate, structural stability and, at 24 m or more in Mumbai, PWD lift certificates.

  6. Add the occupancy-specific papers

    Bed numbers for a hospital and students' strength for a school in Puducherry; a process flow chart and raw-material list for a factory in Maharashtra.

  7. Attest, scan and upload

    Self-attest each copy where the state asks (Puducherry, and Tripura since October 2026), scan from the originals, then upload and pay. Keep the originals: Chhattisgarh's inspector asks to see them.

The core fire NOC document set, and why the fire service asks for each

Ten papers recur across the 14 official lists. Each one answers a question the fire officer must settle before signing.

  • An application on the state form or on letterhead, signed by the owner or by the architect with an authorisation letter: it fixes who answers for the file (MFS, row 2) MFS e-fire
  • Proof of ownership or tenancy, such as an allotment letter, jamabandi, rent or lease deed, or power of attorney: the certificate goes to the person in control of the premises (Punjab) Punjab Fire Services
  • The applicant's identity: Aadhaar, passport or voter ID in West Bengal, with a power of attorney and PAN WBFES
  • The sanctioned building plan, showing every dimension, the height, the floor area and the type of occupancy: thresholds and fire measures follow from these 4 numbers (Puducherry) Fire Service Department, Puducherry
  • Fire drawings that mark each system: they are the plan the inspector walks the building against (Telangana asks for 7 such drawings) TGFD procedure
  • An area statement: the gross built-up area certificate in Mumbai carries the architect's registration number below the signature, because fees and triggers are counted per m² Mumbai Fire Brigade
  • Details of existing fire fighting arrangements, water sources and fire pump capacity, for a building already in use (Puducherry) Fire Service Department, Puducherry
  • Proof of the fee: in Kerala the treasury challan is 1 of the 4 mandatory site NOC documents Kerala Fire and Rescue
  • The previous NOC, once there is one: Chhattisgarh's renewal set is its post-construction set plus that copy CG Fire NOC
  • A certificate from whoever installed the systems: MFS will not issue a final NOC without one from an approved licensed agency or the local Chief Fire Officer MFS e-fire

Official fire NOC document checklists in 14 states, with form numbers

14 states and UTs publish a document list Flamekite could read on 24 October 2026. Each row names the forms and what the list asks for; states with no published list are marked at the foot.

Forms and stagesWhat the official list asks forPublished as
Maharashtra (MFS) MFS e-fireProvisional and Final NOC; licensed agency Form A; Form B every January and July14 provisional rows, 6 final rows, including Civil Aviation NOC near airports and CCE or MPCB approvals for hazardous stockMFS e-fire web page
Kerala Kerala Fire and RescueSite NOC, Final NOC, Renewal NOC4, 5 and 3 soft-copy documents; plans on the A1 templateKFRS procedures PDF and portal notice
West Bengal WBFESFSR, Revised FSR, FSC, Renewal of FSC, fire licenceDrawings at fixed scales, FAR calculations, ID, power of attorney, PAN; renewal adds the last FSR, registered deed and completion certificateWBFES e-services pages
Tamil Nadu Tamil Nadu Fire and Rescue ServicesPlanning-permission NOC; completion certificate or fire licence; renewalAppendices 1 and 2 with 3 plan sets; NOC copy and fire safety plan; previous licenceTNFRS document page
Telangana TGFD procedureProvisional NOC; Occupancy NOC7 red-marked drawings, the provisional NOC for occupancy, 4 extra upload slotsTGFD procedure PDF
Tripura Directorate of Fire and Emergency Services, TripuraRules 2026: Recommendation in Form G, FSC in Forms I and J; self-certification Forms D, J, N, R; renewal Forms M, N, Q, REarlier SWAAGAT list: Forms A, B, C with Forms 1 and 2; plans in red certified by architect, engineer and licensed agencyAnnexure-A PDF and the 2026 Rules
Assam Sewa Setu AssamForm I buildings, II gas storage, III godowns, IV cinemas, V function halls and buildings below 15 m, VI temporary structures, VII to X petroleum, chemicals, explosives and pharma, XII renewalForm I: site plan, layout plan, service plan, any licence and any agreement, scanned from originals; 28 daysSewa Setu service pages
Goa Directorate of Fire and Emergency Services, GoaInitial NOC, Final NOC, renewal; Forms I, U and F7 documents, Form U dropped at final NOCBRAP 2024 item 284 PDF
Punjab Punjab Fire ServicesNew NOC; renewal4 for a new NOC, 3 for renewalFire NOC portal FAQ
Himachal Pradesh Emerging Himachal single windowForm A application; Form B inspection reportApproved drawings, tenure proof, previous NOC, CO2 explosive certificates and hydraulic pressure test reports for extinguishersEmerging Himachal checklist PDF
Meghalaya Invest MeghalayaNOC before construction3 enclosures: citizenship or ID proof, building plan, fire layout planInvest Meghalaya SOP
Puducherry (UT) Fire Service Department, PuducherryFire NOC or clearance; Categories A, B, C8 self-attested items, with beds for hospitals and students' strength for schoolsFire Service Department PDF
Chhattisgarh CG Fire NOCNew NOC before or after construction; renewal; fire audit2, 2 and 3 documents; affidavit where no building permission existsCG Fire NOC user manual (Hindi)
Gujarat Gujarat FSCOP guideFSPA, FSCA, FSCR on the FSCOP portalAttachments in Section I; 3 self-declarations at FSCAFSCOP Applicant Guide, 2022
Uttar Pradesh Uttar Pradesh Fire and Emergency ServicesNot publishedNo document list found on the UP Fire Service portal on 24 October 2026Not published
Bihar Bihar Fire ServiceProvisional NOC in Form B; final NOC in Form JThe 21-page citizen manual has no document list; only the 15% bank guarantee is in the RulesNot published

Karnataka's fire service site was down, but its Seva Sindhu portal lists the same 9 documents for the high-rise NOC and the Clearance Certificate; the Karnataka page sets them out. Odisha's portal (odishafire.odisha.gov.in) lists documents service by service; the Odisha page sets them out. Jharkhand's three Single Window SOPs list documents for the advisory, the NOC and the renewal; the Jharkhand page sets them out. Not published: Haryana and Andhra Pradesh, where no official list was found on 24 October 2026. Delhi publishes no single list; the Delhi page gathers what its rules refer to.

Fire NOC drawing rules: scales, sheet size, red marking and file limits

Drawings are the heaviest part of the file, and the states that publish rules for them set 4 things: scale, sheet, colour and file size.

West Bengal is the only state Flamekite found that prints a scale for each sheet. Its Fire Safety Recommendation list asks for a key location plan at 1:4000, a site plan at 1:600, sections and floor plans at 1:100, elevations at 1:600, a roof plan at 1:100 and a master plan at 1:100 or 1:200 with a floor-wise area statement in m².

Kerala fixes the sheet. Since 14 July 2025 its portal accepts fire plans only on the A1 template, 84.1 cm x 59.4 cm, with a 10 cm x 8 cm space on the middle right kept for QR code attestation, and it warns that old formats will be rejected. Each drawing uploads as a file below 5 MB.

Colour carries the fire content. Telangana's and GHMC's lists want every fire fighting system marked in red on the site, basement, stilt or ground, floor, terrace, section and elevation drawings. Tripura's checklist asks for the same red marking, with the plans certified by a competent architect, an engineer and a licensed agency.

Paper sets survive in some places: MFS wants 2 sets in the metric system for a Director-area provisional NOC, and the Mumbai Fire Brigade and Tamil Nadu want 3. PMRDA, near Pune, adds a current Google map image of the site.

Drawing and upload rules, as each state or city publishes them
WhatThe ruleSource
West Bengal, sheet scalesKey plan 1:4000, site 1:600, section 1:100, elevation 1:600, floor and basement 1:100, master plan 1:100 or 1:200WBFES
Kerala, sheetA1 template, 84.1 cm x 59.4 cm, 10 cm x 8 cm QR space, from 14 July 2025Kerala Fire and Rescue Services
Kerala, file sizeBuilding drawings below 5 MB eachKerala Fire and Rescue
Chhattisgarh, file typeEach document under 10 MB, JPG or PDF; the layout plan marks where each required system goesCG Fire NOC
Rajasthan, file typePDFs of no more than 2 MB eachRajasthan LSG
Telangana, marking7 drawings in red, signed by the builder or owner and an authorised technical personTGFD procedure
Tripura, certificationPlans in red certified by architect, engineer and licensed agency, at both stagesTripura Home (F&ES)
Maharashtra (MFS), sets2 metric sets, with a floor-wise area certificate that counts basements and underground tanksMFS e-fire
Mumbai, sets3 sets of plans for a fresh or revised proposalMumbai Fire Brigade

Certificates a fire NOC file needs from agencies, architects and engineers

Twelve certificates appear on official lists, each signed by a named kind of professional. The licensed agency's certificate is the one most final-stage files cannot do without.

Architect's compliance certificate
The architect or civil engineer certifies that the plans conform to the development control rules and the building code; the MFS page still names NBC 2005. MFS e-fire
Architect's declaration of liability
PMRDA's format has the architect, with registration number, accept personal liability for any lapse or deviation in the drawings. PMRDA
Gross built-up area certificate
Mumbai's area certificate from the architect, with the registration number printed below the signature. Mumbai Fire Brigade
Form A (Maharashtra)
The licensed agency's certificate that every fire installation the department asked for is in place; Mumbai wants it with its annexure at the occupation stage. Mumbai Fire Brigade
Structural stability certificate
From a registered structural engineer, covering the building, podium and ramps (Mumbai, occupation stage). Mumbai Fire Brigade
PWD lift certificate
Needed in Mumbai for buildings of 24 m or more before the occupation NOC. Mumbai Fire Brigade
Fire door, pump and pressure test certificates
PMRDA's 19-item final list asks for a CBRI or ISI fire door certificate, a pump test, a pressure test with Form A and at least 10 photos of the installed system. PMRDA
Hydraulic pressure test report
Himachal asks for HPT reports of every extinguisher and explosive certificates for CO2 extinguishers. Emerging Himachal single window
Electrical inspector and generator certificates
Vadodara's final NOC list asks for the Assistant Electrical Inspector's certificate, a generator certificate, a lift certificate and a vendor certificate. Vadodara fire
Annual maintenance contract (AMC)
Mandatory on Vadodara's list, and one of Gujarat's 3 self-declarations at FSCA. Vadodara fire
Third-party audit report
Chhattisgarh certificates carry an annual self-declaration plus a third-party audit report; Tripura asks one of medium and large industries. Fire and Emergency Services and SDRF, Chhattisgarh
Agency audit certificate (Puducherry)
Category A and Category B buildings each file audit certificates from any 2 licensed agencies; Category C files a self-affidavit. Puducherry G.O. 61

Affidavits, bonds and self-declarations in fire NOC files, by stamp value

Sworn papers range from none at all in Tripura to a Rs 500 bond in Mumbai. Most states have moved from affidavits to self-attested copies or online self-declarations.

As published

  • Mumbai, undertaking-cum-indemnity bond for a trade NOCRs 500 stamp paperAlso mandatory to renew a health licence Mumbai Fire Brigade
  • Goa, annual self-declaration (Annexure A)Rs 100 stamp paperFiled every year of the 5-year term Directorate of Fire and Emergency Services, Goa
  • Hotel star classification, clearance affidavit (Annexure VI)Rs 100 stamp paperMinistry of Tourism, with the fire NOC uploaded self-attested Ministry of Tourism
  • Ahmedabad, maintenance contract per vendor (2015 list)Rs 100 stamp paper, notarisedA list dated 29 June 2015 that is still online; confirm before relying on it Ahmedabad fire
  • Bihar, provisional NOCBank guarantee of 15%Of the estimated fire-system cost, valid 5 years Bihar Rules 2021
  • Chhattisgarh, building without permissionAffidavit; stamp value not statedAccepted in place of the building permission certificate CG Fire NOC
  • Vadodara, final NOCAffidavit; stamp value not statedOne of 8 status checks before the 15 enclosures Vadodara fire
  • Kerala, NOC applicationAffidavit upload; stamp value not publishedA separate Affidavit tab in the portal Kerala Fire and Rescue
  • Gujarat, Fire Safety Certificate Approval3 self-declarations, no stamp paper statedUploaded on the FSCOP portal Gujarat FSCOP guide
  • Puducherry, every copySelf-attestation onlyThe NOC itself is free Fire Service Department, Puducherry
  • Tripura, self-certification Forms D, J, N and RRs 0: no affidavit, no notaryFrom October 2026 Directorate of Fire and Emergency Services, Tripura

Stamp values are the ones printed on each official list on 24 October 2026. Where a list says affidavit without a value, Flamekite says not stated rather than guessing. The fees themselves are on the fire NOC fees page.

Tripura's October 2026 notice: self-attested copies instead of affidavits

Tripura is the first state Flamekite found to remove the affidavit and the notary from its fire NOC forms by notification.

Word for word

Now, the Fire NOC aspirants are required to submit only self-attested documents, wherever applicable, instead of affidavits or notarized documents for obtaining clearances or fulfilling compliance requirements.

Directorate of Fire and Emergency Services, Tripura, notification F.3-8(DI&C)/TFES, eSigned October 2026, signed by the Special Secretary and Director Directorate of Fire and Emergency Services, Tripura

The notice rests on section 26(A) of the Tripura Fire and Emergency Services Act, 2022, as amended by the Tripura Janvishwas (Amendment of Provisions) Act, 2025, and rewrites the headings of self-certification Forms D, J, N and R under the 2026 Rules. A false self-certificate is still treated as wilful criminal negligence.

Extra fire NOC documents for hospitals, hotels, schools, factories, LPG kitchens and high-rises

The core set is the same everywhere; the occupancy adds papers. These 8 cases come from the lists that name them.

  1. Case 1

    A hospital in Puducherry

    Institutional building applying to the Divisional Fire Officer

    What applies Adds the bed details to the 8 self-attested items: approved plan, land document, type of business, existing systems and pump capacity, previous NOC, ID. Fire Service Department, Puducherry

  2. Case 2

    A school in Puducherry

    School applying for a fire NOC or clearance

    What applies Adds the previous recognition certificate, a stability certificate and the students' strength. Fire Service Department, Puducherry

  3. Case 3

    A hotel seeking a star classification

    Hotel applying to the Ministry of Tourism

    What applies Uploads the fire NOC, current and self-attested, with a Rs 100 stamp-paper affidavit, and shows the original NOC at the HRACC inspection. At project stage it files details of fire fighting measures and hydrants. Ministry of Tourism

  4. Case 4

    A factory in a Director area of Maharashtra

    Industrial or storage building outside the municipal fire brigades

    What applies Adds a certified process flow chart, raw materials and finished goods with quantities marked on the block plan, and approvals from CCE, Excise, MPCB, DISH or FDA where its stock needs them. MFS e-fire

  5. Case 5

    A medium or large industry in Tripura

    Industrial unit at the post-operative stage

    What applies Adds a third-party safety audit report from a technical expert or agency, listing the fire safety measures provided. Tripura Home (F&ES)

  6. Case 6

    A restaurant with LPG cylinders in Mumbai

    Eating house applying for a trade NOC

    What applies Files a layout plan, an architect's plan showing the access road and occupant load, and a Rs 500 stamp-paper bond; with up to 10 cylinders a Station Officer inspects and an ADFO approves it. Mumbai Fire Brigade

  7. Case 7

    A gas or chemical store in Assam

    LPG, CNG, oxygen or chemical storage

    What applies Uses its own form, not the building Form I: Form II for gases, Form VIII for chemicals, Form X for pharmaceuticals and solvents. Sewa Setu Assam

  8. Case 8

    A 30 m tower near an airport, Pune region

    High-rise residential building under PMRDA

    What applies Adds a Civil Aviation NOC at plan stage; at completion, the 19-item final list asks for fire lift, fire door, pump and pressure certificates and a hydraulic calculation. PMRDA

Which fire NOC document set does your file need: new, existing, renewal or changed?

Start from the stage, then the building's history. Each branch names the list that settles it.

  1. If Nothing is built yet

    File the plan-stage set: drawings, area statement, activity note and the architect's compliance certificate; MFS lists 14 rows for this stage. Fire NOC Maharashtra MFS e-fire

  2. If The building is complete and you want the final NOC

    Add the provisional NOC, as-built drawings and the installer's certificate; Mumbai also wants structural stability and, at 24 m or more, PWD lift certificates. Mumbai Fire Brigade

  3. If The building stands but has no building permission (Chhattisgarh)

    The portal accepts an affidavit in place of the building permission certificate. CG Fire NOC

  4. If You are renewing

    Usually the old NOC, ownership proof and ID; Punjab asks for those 3 and no drawing. Punjab Fire Services

  5. If The use changed or the building was altered (Tripura)

    Rule 11 of the 2026 Rules needs a fresh NOC, so the full set again, not a renewal. Directorate of Fire and Emergency Services, Tripura

  6. If Your plans changed after a Gujarat plan approval

    Apply for the Fire Safety Plan Approval afresh; minor changes go in the remarks at FSCA with reasons. Gujarat FSCOP guide

  7. If Your Kerala building is under 1,000 m² of plinth or 15 m

    It self-certifies instead of filing a fire NOC, unless it is a hazardous or assembly occupancy. Kerala Fire and Rescue

  8. If It is a residential apartment below 24 m in Telangana

    No fire NOC, and so no fire NOC file, for fresh provisional applications from 7 October 2026. Fire NOC Telangana TGFD circular 3455

Fire NOC document errors that lead to rejection or a defect notice

Kerala's FAQ names 4 common rejection reasons, and 3 of them are about paperwork. These are the errors official pages warn about.

  • If Incomplete or incorrect forms, or a missing document or fee

    Kerala lists these among its 4 common reasons for rejection. Tick the state checklist line by line before paying. Kerala Fire and Rescue

  • If A fire plan on an old sheet format in Kerala

    Redraw it on the A1 template with the 10 cm x 8 cm QR space; the portal rejects old formats. Kerala Fire and Rescue Services

  • If Expecting the service clock to run while a defect is open

    Kerala's timelines do not apply to a defected application, and Meghalaya restarts its 1 month from the date your clarification arrives. Kerala Fire and Rescue

  • If Pressing Confirm Submit with an error in Chhattisgarh

    Nothing can be amended after it; correct the confirmation page with the Update button first. CG Fire NOC

  • If Splitting a building on paper to fall into a lower risk category

    Tripura's 2026 Rules bar artificial subdivision (rule 12) and read any doubt in favour of more safety (rule 13). Directorate of Fire and Emergency Services, Tripura

  • If Following an official PDF that is years old

    Ahmedabad's list dated 29 June 2015 is still online; ask the fire office whether a list is current before you build a file on it. Ahmedabad fire

  • If Attachments too large or unreadable

    Gujarat asks for small files that stay legible; Assam wants scans of the originals. Gujarat FSCOP guide

Where each fire NOC document is checked, from upload to decision

A file passes at least 5 desks or screens. Meghalaya's SOP, Chhattisgarh's manual and GHMC's procedure show where each paper is read.

  1. Upload

    Each file is checked against the portal's cap: under 5 MB per drawing in Kerala, under 10 MB in Chhattisgarh, 2 MB per PDF in Rajasthan. Kerala Fire and Rescue

  2. Confirm and submit

    Chhattisgarh shows a confirmation page; after Confirm Submit no change is allowed, and a PDF copy of the application is issued. CG Fire NOC

  3. Desk scrutiny

    In Meghalaya the Senior Station Officer checks the documents for completeness and correctness against a 24-item fire measures list. Invest Meghalaya

  4. Site inspection

    The inspector compares the building with the layout plan and, in Chhattisgarh, sees the originals of the uploaded documents. CG Fire NOC

  5. Inspection report

    Meghalaya's report is due within 48 working hours, with photographs of any non-compliance, and a copy goes to the applicant. Invest Meghalaya

  6. Higher scrutiny

    In Himachal the station's Form B report goes to the Fire Prevention Officer in Shimla, then to the Chief Fire Officer. Emerging Himachal single window

  7. Decision

    For GHMC buildings of 15 m or less, the Commissioner decides after the District Fire Officer, the Additional Director and the Chief City Planner, within 7 days. GHMC

Fire NOC paperwork in numbers: list lengths, file sizes, plan sets

Official lists run from 3 to 19 items. These figures come from the lists themselves, read on 24 October 2026.

Five fire NOC document myths, checked against official lists

  • You may have read

    Every fire NOC file needs a notarised affidavit.

    Myth

    What the sources say

    Tripura removed the affidavit and notary from Forms D, J, N and R in October 2026, Gujarat uses 3 online self-declarations, and Puducherry asks only for self-attested copies. Directorate of Fire and Emergency Services, Tripura

  • You may have read

    Renewal means filing the whole file again.

    Myth

    What the sources say

    Punjab's renewal needs 3 documents and Kerala's 3 soft copies: the last NOC, a challan and the civil plan. Punjab Fire Services

  • You may have read

    Drawings certified to NBC 2016 meet a binding national standard.

    Myth

    What the sources say

    NBC 2016 was withdrawn on 30 April 2026, and only Assam had written NBCS 2026 into its fire law by 24 October 2026; your state's rules decide, and the MFS form still names NBC 2005. Gazette of India

  • You may have read

    One national checklist applies in every state.

    Myth

    What the sources say

    There is none. Lists run from 3 to 19 items, and Assam alone uses 12 forms by type of premises. Sewa Setu Assam

  • You may have read

    Paper copies are gone everywhere.

    Myth

    What the sources say

    West Bengal's FAQ still refers to ammonia print copies for the Director General, and Maharashtra and Tamil Nadu still count plan sets. West Bengal Fire and Emergency Services

How fire NOC paperwork changed, 2015 to 2026

In 11 years the file moved from notarised paper to uploads, self-declarations and QR-coded sheets, unevenly by state.

  1. 29 June 2015

    Ahmedabad's fire NOC requirement list is created: notarised Rs 100 contracts, photos on CD or DVD. It is still online in 2026. Ahmedabad fire

  2. 2022

    Gujarat's Regulations make the FSCA papers self-certified: 3 declarations, no affidavits. Gujarat FSCOP guide

  3. 19 July 2024

    Kerala's FAQ PDF names the 4 common rejection reasons. Kerala Fire and Rescue

  4. March 2025

    PMRDA posts its provisional and final checklists, the final one at 19 items. PMRDA

  5. 14 July 2025

    Kerala makes the A1 template with a QR space mandatory for every fire plan. Kerala Fire and Rescue Services

  6. 4 August 2025

    Kerala lets non-hazardous buildings take a 5-year NOC, so the renewal file is filed less often. Home Department, Kerala

  7. 30 April 2026

    BIS withdraws NBC 2016; official forms that cite it are left behind. Gazette of India

  8. 2 June 2026

    Tripura's Fire Safety Rules 2026 bring new Forms D to R and a fresh-NOC rule on change of use. Directorate of Fire and Emergency Services, Tripura

  9. 11 July 2026

    MFS updates Form M, the licence application for the agencies that sign Form A. MFS Form M

  10. 7 October 2026

    Telangana residential apartments below 24 m stop needing a fire NOC for fresh provisional applications. TGFD circular 3455

  11. October 2026

    Tripura removes affidavits and notarisation from its self-certification forms. Directorate of Fire and Emergency Services, Tripura

Where each state publishes its fire NOC document checklist

The 16 official pages and PDFs this page was built from, each checked on 24 October 2026. Download the list from here, not from a copy.

Scanning, attesting and filing fire NOC copies: do's and don'ts

Small habits that the official lists ask for, in 9 lines.

Do

  • Self-attest each copy where the state asks: all 8 items in Puducherry. Fire Service Department, Puducherry
  • Scan from the originals, as Sewa Setu asks for Assam's Form I. Sewa Setu Assam
  • Sign every plan you upload in Telangana: the builder or owner and an authorised technical person, with 4 extra upload slots for anything else. TGFD procedure
  • Take the originals to the inspection in Chhattisgarh: the officer checks them against the uploads. CG Fire NOC
  • Count the free-of-FSI areas, such as basements and underground tanks, in the MFS area certificate. MFS e-fire

Don’t

Penalties for false or deviating fire NOC documents

Signing a document that does not match the building is an offence in at least 3 states, and it reaches the professionals who sign, not only the owner.

OffencePenaltyLaw
Building in deviation from the approved fire drawingsProsecution of the builder, the architect and the site engineerTelangana Fire Service Act, 1999, sections 31 and 32, as printed on the TGFD document list TGFD procedure
A self-certificate that is wilfully falseFine up to Rs 5 lakhTripura Act 2022, section 26(A), as amended in 2025 High Court of Tripura/TFES/2025)
A false self-certificate on e-DistrictTreated as wilful criminal negligencee-District Tripura fire guidelines e-District Tripura
A false compliance certificate1 month to 2 years and/or Rs 10,000 to Rs 1 lakh, plus Rs 3,000 a dayGujarat Act 2013, section 39(1) LegitQueststudy
Non-compliance or misrepresentation in a Gujarat self-declarationSevere penalties, as the guide warns; checked by Fire Safety Officers and state officersFSCOP Applicant Guide, 2022 Gujarat FSCOP guide
A lapse or deviation in plans the architect certifiedPersonal liability accepted by the architect in the declarationPMRDA architect's declaration format PMRDA

The general penalties for running a building without a fire NOC are on the fire NOC pillar page; these 6 rows cover only the documents.

Fire NOC document lists Flamekite could not confirm

8 gaps on 24 October 2026. Where a list is missing, Flamekite says so instead of borrowing another state's.

  • Uttar Pradesh

    No official list

    Neither the UP Fire Service portal nor Nivesh Mitra showed a document list; consultants' lists online are not official. Uttar Pradesh Fire and Emergency Services

  • Bihar

    Manual without a list

    The 21-page citizen manual explains the screens but lists no documents; only the 15% bank guarantee is in the Rules. Bihar Fire Service

  • Andhra Pradesh

    No official list read

    A consultant's copy of a user manual mentions a Rs 100 stamp-paper undertaking; Flamekite could not open an official copy, so it is not used here.

  • Haryana

    No list found

    No official document list was reachable for Haryana. Karnataka's fire service site was down in 6 attempts, but its Seva Sindhu service pages list 9 documents. Seva Sindhu

  • Tamil Nadu

    Extra items above 18.3 m

    A search summary adds a requisition letter and land ownership documents for buildings of 18.3 m and more; the TNFRS page did not render them, so they wait for a browser check. Tamil Nadu Fire and Rescue Services

  • Punjab

    FAQ read from an archived copy

    The portal reset every direct connection on 24 October 2026; the 4 and 3 document lists were read from the Wayback Machine's copy of the official FAQ of 5 August 2025. Punjab Fire portal

  • West Bengal

    Final certificate list

    The Fire Safety Certificate page itself was not read; only the recommendation and renewal lists are used here. WBFES

  • Delhi

    No single list

    DFS publishes no one document list; the Delhi page gathers the papers its rules and pages refer to. DFS

Questions about fire NOC documents

What documents are required for a fire NOC?

Building plans with the fire systems marked, proof of ownership or tenancy, the applicant's ID and the fee receipt, plus an application on the state's form. Later stages add the earlier NOC and a licensed agency's installation certificate. Your state's own checklist decides the final list.

Which documents are needed for a provisional fire NOC?

The plan-stage set: drawings with the fire layout, an area statement, ownership proof and the architect's certificate that the plans follow the rules. Maharashtra's Director lists 14 rows; Meghalaya asks for only 3 enclosures.

Which documents are needed for fire NOC renewal?

Usually the previous NOC, ownership proof and the applicant's ID. Punjab asks for exactly those 3; Kerala for the final NOC, a challan and the civil plan; West Bengal adds the registered deed and the completion certificate.

Is an affidavit required for a fire NOC?

Only where the state's list says so. Tripura dropped affidavits for its self-certification forms in October 2026 and Puducherry wants self-attested copies, while Chhattisgarh accepts an affidavit for a building with no permission and Mumbai wants a Rs 500 bond for trade NOCs.

Who signs the fire NOC drawings?

The architect or engineer who prepared them, and in Telangana also the builder or owner. Tripura wants the plans certified by an architect, an engineer and a licensed agency, and Mumbai's area certificate must show the architect's registration number.

What size should fire NOC drawings be?

Kerala requires the A1 template, 84.1 cm x 59.4 cm, with a QR space, and files below 5 MB. West Bengal sets the scale per sheet, from 1:4000 for the key plan to 1:100 for floor plans. Most other states set no sheet size.

What extra documents does a hospital, school or hotel need?

Puducherry asks hospitals for bed details and schools for the recognition certificate, stability certificate and students' strength. A hotel seeking a star classification uploads its fire NOC with a Rs 100 stamp-paper affidavit to the Ministry of Tourism.

Why are fire NOC applications rejected?

Kerala's FAQ names incomplete or incorrect forms, non-compliance with the fire standards, faulty systems and missing documents or fees. Old sheet formats are rejected in Kerala, and a Chhattisgarh file cannot be corrected after Confirm Submit.

Keep reading

Keep exploring

Sources

Each source was opened and read on the date shown. How Flamekite checks its sources

  1. West Bengal Fire and Emergency Services: Renewal of Fire Safety Certificate: document requirement (opens in a new tab)checked 24 October 2026
  2. Kerala Fire and Rescue Services: NOC portal user manual: drawings below 5 MB, affidavit tab, final clearance (opens in a new tab)checked 24 October 2026
  3. Local Self Government Department, Rajasthan: Fire NOC citizen manual: online application and document upload (opens in a new tab)checked 24 October 2026
  4. e-District Tripura: Guidelines for fire safety certificate and NOC services (Aadhaar e-sign, e-GRAS payment) (opens in a new tab)checked 24 October 2026
  5. West Bengal Fire and Emergency Services: FAQ: fire safety certificate, 14.5 m line, compounding under section 38B (opens in a new tab)checked 24 October 2026
  6. Invest Meghalaya: Standard operating procedure for fire clearance (opens in a new tab)checked 24 October 2026
Show all 50 sourcesShow fewer
  1. Pune Metropolitan Region Development Authority, Fire Department: Final fire NOC file checklist (19 items, Marathi), with the architect's completion certificate (opens in a new tab)checked 24 October 2026
  2. Maharashtra Fire and Emergency Services: E-Approval online application: documents for Provisional and Final NOC, and the 7-working-day service line (opens in a new tab)checked 24 October 2026
  3. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Procedure and documents required for Fire NOC (opens in a new tab)checked 24 October 2026
  4. Kerala Fire and Rescue Services: Fire NOC portal: online NOC, renewal, NOC verification, A1 template for fire plans from 14 July 2025 (opens in a new tab)checked 24 October 2026
  5. Directorate of Maharashtra Fire Services: List of Approved Licensed Agencies Valid Up to 03.07.2028 (847 numbered entries in the copy read) (opens in a new tab)checked 25 October 2026
  6. Directorate of Fire and Emergency Services, Tripura: Notification, October 2026: self-certification forms no longer need an affidavit (with Directorate contacts) (opens in a new tab)checked 24 October 2026
  7. Punjab Fire and Emergency Services, Local Government Department: Fire NOC portal FAQ: mandatory documents for a new NOC and for renewal (opens in a new tab)checked 24 October 2026
  8. Fire and Emergency Services and SDRF, Chhattisgarh: Online form user manual (Hindi): documents before construction, after construction and for renewal (opens in a new tab)checked 24 October 2026
  9. West Bengal Fire and Emergency Services: Issuance of Fire Safety Recommendation: document requirement with drawing scales (opens in a new tab)checked 24 October 2026
  10. Fire Service Department, Puducherry: Documents required for fire NOC and clearance (opens in a new tab)checked 24 October 2026
  11. Municipal Corporation of Greater Mumbai, Mumbai Fire Brigade: List of documents: proposals (fresh or revised building plans) (opens in a new tab)checked 24 October 2026
  12. Kerala Fire and Rescue Services: KFRS procedures: mandatory documents for site NOC, completion NOC and renewal (opens in a new tab)checked 24 October 2026
  13. Tamil Nadu Fire and Rescue Services: Documents for planning-permission NOC, completion certificate or fire licence, and renewal (opens in a new tab)checked 24 October 2026
  14. Directorate of Fire and Emergency Services, Tripura: Tripura Fire Safety Rules, 2026 (Tripura Gazette, 2 June 2026) (opens in a new tab)checked 24 October 2026
  15. Sewa Setu, Government of Assam: Fire NOC for one storied, multi-storied or high-rise building (Form I): required documents, and the Form II to XIII services (opens in a new tab)checked 25 October 2026
  16. Directorate of Fire and Emergency Services, Goa: BRAP 2024 item 284: fire NOC fees and timeline (opens in a new tab)checked 25 October 2026
  17. Emerging Himachal single window: Fire NOC checklist and procedure (Form A) (opens in a new tab)checked 24 October 2026
  18. Gujarat State Fire Prevention Services: Applicant Guide for the Gujarat Fire Safety Compliance Portal (2022, first edition): FSPA, FSCA, FSCR and self-certification formats (opens in a new tab)checked 25 October 2026
  19. Uttar Pradesh Fire and Emergency Services: UP Fire Service online portal (applications and NOC verification) (opens in a new tab)checked 24 October 2026
  20. Bihar Fire Service: Bihar Fire NOC and Audit portal: introduction and State Fire Office contacts (opens in a new tab)checked 24 October 2026
  21. Home (F&ES) Department, Government of Tripura: Annexure-A: checklist for Provisional NOC (Form A), NOC (Form B) and renewal (Form C) (opens in a new tab)checked 25 October 2026
  22. Pune Metropolitan Region Development Authority, Fire Department: Provisional fire NOC file checklist, with the architect's declaration and Annexure A (opens in a new tab)checked 24 October 2026
  23. Municipal Corporation of Greater Mumbai, Mumbai Fire Brigade: List of documents: occupation-stage fire NOC (opens in a new tab)checked 24 October 2026
  24. Vadodara Municipal Corporation, Fire and Emergency Services: Fire NOC application details and final fire NOC document checklist (Gujarati) (opens in a new tab)checked 24 October 2026
  25. Fire and Emergency Services and SDRF, Chhattisgarh: HQ order No. 204/Agnishaman/2025, 16 October 2025: risk-based NOC validity of 3, 2 or 1 years (opens in a new tab)checked 24 October 2026
  26. Government of Puducherry, Home Department (copy hosted by the Fire Service Department): G.O.Ms.No.61, 10 September 2025: Fire Safety Audit and Issue of NOC, Third Party Fire Safety Audit, Categories A, B and C, renewal, temporary licences, and Annexures I to V on licensed agencies and the Category C protocol (opens in a new tab)checked 25 October 2026
  27. Municipal Corporation of Greater Mumbai, Mumbai Fire Brigade: FB_06: documents for a new trade, including the undertaking-cum-indemnity bond on Rs 500 stamp paper (opens in a new tab)checked 24 October 2026
  28. Directorate of Fire and Emergency Services, Goa: Ease of Doing Business: online fire NOC on Goa Online (FES91, FES92, FES93), annual self-declaration (opens in a new tab)checked 25 October 2026
  29. Ministry of Tourism, Government of India: Revised guidelines for approval of hotels at project stage and star classification, No. 8-TI-I-1(3)/2013-PI-1 (opens in a new tab)checked 25 October 2026
  30. Ahmedabad Municipal Corporation, Fire Department: Documents required for obtaining an NOC from the Ahmedabad fire department (PDF created 29 June 2015) (opens in a new tab)checked 24 October 2026
  31. Government of Bihar, Home Department (English copy hosted by Bihar Fire Service): Bihar Fire Service Rules, 2021: rule 15 (NOC thresholds, forms, validity, renewal), rules 20 to 26 and Schedule C (opens in a new tab)checked 24 October 2026
  32. Telangana Fire, Disaster Response, Emergency and Civil Defence Department: Circular Memorandum Rc.No.3455/MSB/2026, 26 September 2026: revised requirements for Fire NOCs in the context of G.O.Ms.No.95 (in force 7 October 2026) (opens in a new tab)checked 25 October 2026
  33. Kerala Fire and Rescue Services: Frequently asked questions (PDF of 19 July 2024): question 13, common reasons for rejection (opens in a new tab)checked 24 October 2026
  34. Greater Hyderabad Municipal Corporation, Town Planning: Important instructions for applying for a fire NOC (buildings of 15 m and below) (opens in a new tab)checked 24 October 2026
  35. Gazette of India (Bureau of Indian Standards notification): Gazette of India Extraordinary, Part III Sec 4, No. 299, 30 April 2026: SP 7:2026 established, SP 7:2016 withdrawn (Ref HQ-PUB013/1/2020-PUB-BIS (1529)) (opens in a new tab)checked 25 October 2026
  36. Home (F) Department, Kerala (on the Kerala Fire and Rescue renewal portal): G.O.(Ms)No.143/2025/HOME, 4 August 2025: fire NOC valid 5 years (non-hazardous) or 2 years (hazardous) (opens in a new tab)checked 24 October 2026
  37. Maharashtra Fire and Emergency Services: Application for Fire Licence Agency, Form M and checklist (updated 11.07.26) (opens in a new tab)checked 25 October 2026
  38. Tamil Nadu Fire and Rescue Services: NOC procedure: Director above 18.3 m, District Officer up to 18.3 m (opens in a new tab)checked 24 October 2026
  39. High Court of Tripura (copy with the 2025 amendments and Home notice F.3-8(NOC)/TFES/2025): Tripura Fire and Emergency Services Act, 2022, section 26(C) and renewal lapse fee (opens in a new tab)checked 24 October 2026
  40. Seva Sindhu, Government of Karnataka: Application for No Objection Certificate (High rise Building) - Fire & Emergency: documents, fee under G.O. of 13-09-2019, 60 working days (opens in a new tab)checked 24 October 2026
  41. Directorate of Punjab Fire and Emergency Services (Wayback Machine copy of 5 August 2025): Frequently Asked Questions: payment, cash at the fire station, download, documents for new, provisional and renewal NOC (opens in a new tab)checked 24 October 2026
  42. Delhi Fire Service: Frequently asked questions (opens in a new tab)checked 25 October 2026
  43. LegitQuest (legal database): Gujarat Fire Prevention and Life Safety Measures Act, 2013: sections 21, 26 and 39 (opens in a new tab)Peer-reviewed study · checked 24 October 2026
  44. cgwanoc.in (consultant blog): Fire NOC documents checklist (the best-ranked HTML competitor; 6 information headings) (opens in a new tab)News report · checked 24 October 2026